CONSTRUCTION MANAGEMENT MAIN CONTRACTOR PROJECT EMPLOYER

CHINA SONANGOL
MEDIA INVESTMENT

DAILY REPORT
( DRP )
Project : INDONESIA 1 S : Sunny D : Drizzling
Wheather S S S S S S S S S S S R R R R R R S S S S S S S S
Date : 20/08/2016 C : Cloudy
Temp. : 21 C
o Time 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8R : Rain

MAN POWER QTY DONE (TODAY) PLAN (TOMORROW)


1. MANAGEMENT
Project Director 1 Water stagnate at many area at site project
Project Manager 2 lifting plan
Site Engineer 4 moving material pvc and cement
QS 2
QC 5
Supervisor 4
Surveyor 7
Administration & Finance 23
Logistic & Storage 15
HSE Officer 3
Security 25
TOTAL 91
2. SKILLED WORKER
Operator TC 4
Riger 2
Other Heavy Eqpt Operator 8
Maintenance -
Welder 2
Foremen -
Mandor 3
TOTAL 19 PROBLEM OCCURRED SOLUTION / REMEDY
3. WORKER
Carpenter/Formwork 21 elektricity is not available
Masonry/Stone - pump cannot used
Steel/rebar 25
Electrical 4
Mechanical 4
Paint 4
Cut & Fill -
Cleaning 9
Waterproofing -
Finishing -
Helper 2
Dewatering 15
Other
TOTAL 84
MAIN EQUIPMENT MAIN MATERIAL

Item Unit Item Unit Item Unit

EXSAVATOR /PC 200 3 BAR BANDER 1 STELL SIZE { 32,22,25,16,13,10}

3 PVP
PC BRAKER

CRANE 50 T 1
BOR DRILL 1
COMPRESSOR 1
BAR BANDER 1
REMARKS / HIGHLIGHT ITEM or ACTIVITY

Prepared by Field Coordinator Verified by Site Engineer Acknowledge by Construction Manager


Signature

Name SAHRUL DEDI AGUS


Date 18/08/2016 18/08/2016 18/08/2016
(R.00 - 05082016)
MAIN CONTRACTOR MAIN CONTRACTOR PROJECT

DAILY REPORT
( DRP )
Project : INDONESIA 1
Wheather S S
Date :19 AGUSTUS 21016
Temp. : 21 C
o Time 8 9 10 11 12 13 14 15 16 17 18 20 21

MAN POWER QTY DONE (TODAY)


1. MANAGEMENT
Project Director
Project Manager
Site Engineer
QS
QC
Supervisor
Surveyor
Administration & Finance
Logistic & Storage
HSE Officer 2
Security
TOTAL
2. SKILLED WORKER
Operator TC
Riger
Other Heavy Eqpt Operator
Maintenance
Welder
Foremen
Mandor
TOTAL PROBLEM OCCURRED
3. WORKER
Carpenter/Formwork
Masonry/Stone
Steel/rebar
Electrical
Mechanical
Paint
Cut & Fill
Cleaning
Waterproofing
Finishing
Helper
Dewatering 15
Other
TOTAL
MAIN EQUIPMENT MAIN MATERIA
Item Unit Item
EXSAVATOR /PC 200 3 BESI
PC BRAKER 3
CRANE 50 T 1
BOR DRILL 1

REMARKS / HIGHLIGHT ITEM or ACTIVITY

Prepared by Field Coordinator Verified by Site Engineer


Signature

Name ROCHMAD SANTOSO SAHRUL


Date 18 AGUSTUS 2016 18 AGUSTUS 2016
PROJECT EMPLOYER

CHINA SONANGOL
MEDIA INVESTMENT

ORT
S : Sunny D : Drizzling
C : Cloudy
22 23 24 1 2 3 4 5 6 7R : Rain

PLAN (TOMORROW)

SOLUTION / REMEDY

MAIN MATERIAL
Unit Item Unit

Acknowledge by Construction Manager

DEDI
18 AGUSTUS 2016
(R.00 - 05082016)