Download as pdf or txt
Download as pdf or txt
You are on page 1of 44

DESIGN, SUPPLY, INSTALL, TESTING AND COMMISSIONING WORKS FOR:

PHASE 1 – COOLING TOWERS, CONDENSER WATER PIPEWORKS,


MAKEUP WATER TANK REPLACEMENT, NEW AIR CONDITIONING MAIN
SWITCHBOARD AND ALL RELEVANT WORKS AND,
PHASE 2 – CHILLERS, CHILLED WATER DISTRIBUTION PIPEWORKS,
PUMPS, PLATE HEAT EXCHANGERS AND ALL RELEVANT WORKS FOR
BANGSAR ENERGY SYSTEM (BES) PLANT, BANGSAR, KUALA LUMPUR

COOLING TOWER COMMISSIONING


PROCEDURE
Document/Drawing Number: BES-SEG-RHB-PR-COM-001
Revision: 0

1 APPROVED

2 APPROVED WITH COMMENT

3 REJECTED

Prepared by Approved by Reviewed by


Rev Date Status
the the the
Contractor Contractor Engineer
A 30/11/20 IFR – Issue for Review Phoa Khairi Sharil
B 28/12/20 IFA – Issue for Approval Phoa Khairi Sharil
0 19/03/21 FIN - FINAL Phoa Khairi Sharil
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 2 of 15

1. PURPOSE

The aim of this procedure is to ensure overall quality and safety of the commissioning work for cooling
towers.

2. SCOPE & OBJECTIVE

The Scope covers for pre-commissioning and commissioning procedure for cooling towers.

3. REFERENCES

This document shall be based on following specification and references:

• Cooling Tower Specification


• Drawings
i. Equipment Layout Roof Floor Drawing BES-SEG-RHB-ME-DR-003
ii. P & ID (Overall Plant) Drawing BES-SEG-RHB-CI-DR-001

4. DEFINITION

EMPLOYER Means BANGSAR ENERGY SYSTEMS SDN. BHD.


ENGINEER Means person appointed by the EMPLOYER to act as engineer for the
purposes of contract
CONTRACTOR Means the person(s) named as contractor in the letter of tender
accepted by the EMPLOYER – SEGATRANS SDN BHD
WORK means DESIGN, SUPPLY, INSTALL, TESTING AND
COMMISSIONING WORKS FOR: PHASE 1 – COOLING TOWERS,
CONDENSER WATER PIPEWORKS, MAKEUP WATER TANK
REPLACEMENT, NEW AIR CONDITIONING MAIN SWITCHBOARD
AND ALL RELEVANT WORKS AND, PHASE 2 – CHILLERS, CHILLED
WATER DISTRIBUTION PIPEWORKS, PUMPS, PLATE HEAT
EXCHANGERS AND ALL RELEVANT WORKS FOR BANGSAR
ENERGY SYSTEM (BES) PLANT, BANGSAR, KUALA LUMPUR
SUBCONTRACTOR Means any person or company approved by the CONTRACTOR, to
whom part of the WORK is subcontracted by CONTRACTOR for the
purpose of carrying out the WORK.
SCHEDULES Means the planning document, including Master Project Schedule,
agreed between the EMPLOYER and CONTRACTOR, for the
execution of the WORKS.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 3 of 15

5. GENERAL INFORMATION

5.1 Design Condition

Wet bulb temperature : 27.78℃


Water temperature inlet : 36.11℃
Water temperature outlet : 30.56℃
Cooling water flowrate : 1800usgpm/ 408.82m3/h (per cell)
Number of cell : 2 cells per cooling tower
Fan power : 22 KW per cell

Heat rejection = 408.82 x (36.11-30.56) = 2,268,951kcal/hr

5.2 Equipment

Cooling Tower (CT 1, CT 2, CT 3, CT 4, CT 5, CT 6, CT 7, CT 8, CT 9, CT 10)

Make : Truwater
Selection : EC-S Series
Tower Model : ECS 2213G1-1B
Type : Induced Draft, Counterflow Square
Heat Load : 2,270,455kcal/hr, or 2639kW
No. of Cells : 2 x 10
Water Flow : 818 m3/h per cooling tower
Inlet Temperature : 36.11℃
Outlet Temperature : 30.56℃

5.3 System Description

Cooling tower is part of the cooling water system for providing cooling water to the plant. Total 10 units
of cooling tower are provided and the capacity per unit is 2,270,455kcal/hr. The cooling water will be
circulated by cooling water pump to chiller and cooling tower. The design temperature for cooling water
supply is 30.56℃ and return is 36.11℃.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 4 of 15

5.4 Pre-commissioning Activities


Description Employer Contractor Truwater Remarks
(BES) (SEG)
1. Cooling tower basin cleaning W S S
2. Equipment installation physical check W S S
3. Drive shaft alignment W S S
4. Fan blade angle adjust and check W S S
Legend :
W : Witness Inspection
S : Execute and Submit Inspection

5.5. Commissioning Activities


Description Employer Contractor Truwater Remarks
(BES) (SEG)
1. System Water Filling W S S
2. Water Basin Leak Test W S S
3. Belt Drive System Check W S S
Legend :
W : Witness Inspection
S : Execute and Submit Inspection

6. PRE-COMMISSIONING
Pre-commissioning form shall be used to ensure all pre-commissioning items are completed
prior to the commissioning.

Before proceed, remove any dirt, sediment and trash from cold water basin, sump and
screen.

6.1 Mechanical Equipment Check

6.1.1 Fan Blade Angle and Tip Clearance Adjust and Check
a. Rotate fan by hand to ensure free rotation.
b. Ensure tip clearance is within the allowable range of 20mm to 40mm.
c. Measure fan pitch angle as per technical data sheet.
d. The maximum admissible tolerance is ±1°. Re-setting if required.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 5 of 15

For calculation of tip clearance, refer to formula below:

Theoretical tip clearance= 0.5% of the fan cylinder diameter

6.1.2 Belt Drive System Check


6.1.2.1 V-belt and Pulley Alignment and Measurements

a. Place a string at position A.


b. Pull string backward to get a straight horizontal line across the mechanical equipment.
c. Ensure that the string touching point A, B, C and D evenly.
d. Adjust the motor pulley surface using adjusting bolt if necessary.

6.1.2.2 V-belt Tensioning

a. Put the belts around the pulleys.


b. Set them to the appropriate tension value stated in the table above.
c. Resetting to catalogue value if necessary.
d. Cogged raw edge belts should be tensioned to the higher values given in the table.

6.1.3 Check tightness of bolts for the whole assemblies.

6.1.4 Motor Rotational Check


a. Pressing the green start button followed immediately by the red stop button.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 6 of 15

b. Check the motor rotation is in correct or wrong direction. If wrong, the power must be
isolated at the main panel and any two wires on the electric motor changed over.
c. Start and stop the cooling tower immediately again.
d. Confirm the motor rotation is correct.

6.1.5 Motor Megger Test


Ensure the electrical power connected to the cooling tower is disconnected at all time.
a. Check the motor insulation between phase and earth and between phases with 1000DC
voltage MEGGER for 1 minute. The reading must not less than 5 megaohms for low voltage
motor.
b. Check motor terminal wiring connection by referring to motor nameplate or the connection
diagram on the inside of the terminal box. Ensure that the motor is connected in the correct
manner for starter.
c. Ensure a reliable and permanent connection of the motor to the provided earthling point with
the protective conductor.

7. COMMISSIONING

Commissioning form shall be used to ensure all commissioning items are completed prior to the overall
commissioning.
Before proceed, remove any dirt, sediment and trash from cold water basin, sump and screen.

7.1 System Water Filling


a. Fill the cold- water collection basin
b. Circulating water system until operating water level is reached.
c. Prime and start the circulating water pumps.
d. Increase the flow of circulating water gradually to design water flow rate.
e. Inspect the water distribution system to ensure uniform water distribution at spray nozzles.

7.2 Water Basin Leak Test Procedure


a. Ensure that all the joints and footing bracket and nuts have already been tightened and the FRP
lamination is to satisfaction.
b. Blind off the entire water outlet, drainpipe and balancing pipes flanges.
c. Fill up water into basin until overflow level.
d. Check thoroughly the whole water basin for any leakage.
e. If there is water leakage, find the source of leaking and mark that particular point.
f. Drain all the water and mop the leaking points before repair.
g. Repeat step a to f until no further leakage is found.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 7 of 15

7.3 Motor Vibration Check

Frequency Specific Vibration Guidelines


(Based on CTI 163- Standard for Vibration Limits in Water Cooling Towers)

Zone A: Low vibration levels associated with well aligned and balanced equipment on high quality structures.
Zone B: Acceptable vibration levels suitable for unrestricted long term operation.
Zone C: Suggested value for initial Alarm level setting of continuously monitored systems.

Noted: For vibration level over than Zone C, cooling towers shall stop immediately for safety of the cooling
tower and personnel in the vicinity. Correction must be made to the fan drive system before starting the fan
again.

Procedure:

a. The readings of vibration level are preferably to be carried out when cooling tower is in services
with full load.
b. Take readings in three different directions of motors (Axial, Vertical and Horizontal).
c. Compare the results taken to the vibration chart (table above).
d. If the vibration level is exceeding the standard vibration level, solving the cause is necessary.

7.4 Belt Drive System Check


Refer to procedure in Section 6.1.2.
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 8 of 15

8. ATTACHMENT

ATTACHMENT 1 INSPECTION AND TEST PLAN


ATTACHMENT 2 OVERALL TOWER INSPECTION CHECKLIST – BELT DRIVE
ATTACHMENT 3 FAN PITCH ANGLE AND TIP CLEARANCE INSPECTION CHECKLIST – BELT DRIVE
ATTACHMENT 4 MOTOR FAN SET INSPECTION CHECKLIST
ATTACHMENT 5 COOLING TOWER PRE-COMMISSIONING FORM
ATTACHMENT 6 COOLING TOWER COMMISSIONING FORM
ATTACHMENT 7 MEASURING INSTRUMENT CALIBRATION CERTIFICATE
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 9 of 15

ATTACHMENT 1

INSPECTION AND TEST PLAN


Form : TCT-F40
Rev : 0
……providing solutions to your cooling needs Page : 1 of 1
Truwater Cooling Towers Sdn Bhd (company No:188113-A)

INSPECTION AND TEST PLAN


- SITE / CONSTRUCTION -
CLIENT : DRIVE TYPE Pulley Belt Drive
PROJECT : REVISION REV.0
MODEL : PAGE 1 OF 1
JOB NO. :
SECTION : MECHANICAL
ITEM PROCESS DESCRIPTION / ACCEPTANCE INSP.REPORT INSPECTION PARTIES
NO INSPECTION / TEST DETAIL CRITERIA (FORM NO.) TRUWATER CLIENT OWNER
1 Bracket Allocation
- Dimension Vendor drawing TCT-F41 P M W

2 Mainframe structure
- Bolts and nuts Properly tightened TCT-F41 P M W

3 Internal Components
- Fill properly installed Vendor drawing TCT-F41 P M W

- Drift Eliminator properly installed Vendor drawing TCT-F41 P M W


- Water Distribution or Nozzles properly installed Vendor drawing TCT-F41 P M W
- Inlet Piping connection properly installed Properly tightened TCT-F41 P M W

- Outlet Piping connection properly installed Properly tightened TCT-F41 P M W

- Overflow, Make-up and drain Pipe connection Properly tightened TCT-F41 P M W

4 Casing, Partition and Louvers


- Nails and screw Properly tightened TCT-F41 P M W

5 Mechanical Equipment
- Fan
a) Fan blades installed in proper sequence Vendor spec TCT-F41 P M W
b) Fan blades pitch angle Vendor spec TCT-F42 P M W
c) Fan tip clearance 20 - 40 mm TCT-F42 P M W

d) Fan hub bolt and nuts Vendor spec TCT-F41 P M W

- Motor
a) All bolt and nuts Properly tightened TCT-F41 P M W

- Fan support
a) All bolt and nuts Properly tightened TCT-F41 P M W

- V-belts and Pulley


a) All bolt and nuts Properly tightened TCT-F41 P M W
b) V-Belts tensioning Tension Force Table TCT-F45 P M W

c) Alignment Assembly manual TCT-F45 P M W

Legend :

P - Party which perform specific work / activity

M - Monitoring / specific work / activity

W - Witness the inspection


Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 10 of 15

ATTACHMENT 2

OVERALL TOWER INSPECTION CHECKLIST – BELT


DRIVE
FORM : TCT-F41-BD-0
…..providing solution to your cooling needs REV : 0
Truwater Cooling Towers Sdn Bhd (company No:188113-A) PAGE : 1 of 1

OVERALL TOWER INSPECTION CHECKLIST - BELT DRIVE

CUSTOMER : DATE :
PROJECT : JOB NO. :
TOWER MODEL : CELL NO.:

TYPE OF WORKS DESCRIPTION APPROVAL REQUIREMENT CHECKED


1. Bracket Allocation All bolts installed and properly Randomly check on the tightened
tightened bolts and nuts.
Location of the bracket installed as
per installation drawing
2. Mainframe Structure All bolts installed and properly Randomly check on the tightened
tightened bolts and nuts.

3. Internal Components
Infill Neat and properly installed As per installation drawing
Drift Eliminator Neat and properly installed As per installation drawing
Inlet connection All bolts installed and properly Randomly check on the tightened
tightened bolts and nuts.
Spray nozzles All nozzle properly installed As per installation drawing
4.External Components
Casing Properly installed As per installation drawing
Louver Properly installed As per installation drawing
5. Mechanical Equipment
Mechanical Bolts and nuts properly tightened All bolts and nuts for were properly
Support tightened
Fan Blade Properly installed & bolts and nuts All bolts and nuts for were properly
were tightened tightened
Fan Hub Properly installed & bolts and nuts All bolts and nuts for were properly
were tightened tightened
Motor Properly installed & bolts and nuts All bolts and nuts for were properly
were tightened tightened
V-Belts and Properly installed & bolts and nuts All bolts and nuts for were properly
Pulley were tightened. tightened

Maintenance Properly installed with sufficient Grease nipple properly tightened and
Grease Line grease proper connect to grease hose

4. REMARK (IF ANY)

Please tick [ ✓ ] the checkbox for compliance


INSPECTED/CHECKED BY: VERIFIED BY: WITNESSED BY:
Truwater's Representative Customer's Representative End User's Representative

(Signature) (Signature & Co. Stamp) (Signature & Co. Stamp)


Name : Name : Name :
Date : Date : Date :
Position : Position : Position :
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 11 of 15

ATTACHMENT 3

FAN PITCH ANGLE AND TIP CLEARANCE INSPECTION


CHECKLIST – BELT DRIVE
FORM : TCT-F42-PB
REV : 01
PAGE : 1 of 1

FAN PITCH ANGLE AND TIP CLEARANCE INSPECTION CHECKLIST - BELT DRIVE

CUSTOMER : DATE :
PROJECT : JOB NO. :
TOWER MODEL : CELL NO.:

FAN

Fan Specifications:

Brand : Model :

Blades quantity : Theoretical blade angle : (°)

Diameter : (mm) Modified blade angle after commissioning : (°) ( if any )

Fan Pitch Angle Fan Tip Clearance

Fan Cylinder Installation:

Quantity of Fan Cylinder segments:

Tip Clearance Measurement, S:


Quantity of location based on quantity of segments.
Standard Tip Clearance: ( 20mm - 40mm )
Location 1 2 3 4 5 6 7 8 9 10
Result (mm)

Fan Pitch Angle Measurement:


Allowable Result Remark
Blade 1 pitch angle (°) ±1°
Blade 2 pitch angle (°) ±1°
Blade 3 pitch angle (°) ±1°
Blade 4 pitch angle (°) ±1°
Blade 5 pitch angle (°) ±1°
Blade 6 pitch angle (°) ±1°
Blade 7 pitch angle (°) ±1°
Blade 8 pitch angle (°) ±1°

INSPECTED/CHECKED BY: VERIFIED BY: WITNESSED BY:


Truwater's Representative Customer's Representative End User's Representative

(Signature) (Signature & Co. Stamp) (Signature & Co. Stamp)


Name : Name : Name :
Date : Date : Date :
Position : Position : Position :
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 12 of 15

ATTACHMENT 4

MOTOR FAN SET INSPECTION CHECKLIST


FORM : TCT-F45
REV : 01
PAGE : 1 of 1

MOTOR FAN SET INSPECTION CHECKLIST

CUSTOMER : DATE :
PROJECT : JOB NO. :
TOWER MODEL : CELL NO.:

Belt Drive

Belt Alignment:

A Bad Alignment

B Good Alignment

Presence of gap on either / both pulley(s) resulted in pulley misalignment.


Allowable tolerance: ± 3mm

Belt Tensioning Measurement:

Diameter of Pulley
SN / cell no. L A* Force w'(kg) Judgement Test Date
Large (D) Small (d)

A*: Deflection of Belt = Allowable clearance: Center distance (meter) X 16 mm (deflection) = Actual belt deflection

Deflection (mm) = x 16 =

Force required to deflect belt 16mm per meter of span


Belt section Basic setting forces
Small Pulley Diameter (mm)
Newton (N) Kilograms (kgf)
56 to 71 16 – 20 1.6 – 2.0
75 to 90 18 – 22 1.8 – 2.2
SPZ
95 to 125 20 – 25 2.0 – 2.5
over 125 22 – 28 2.2 – 2.8
80 to 100 22 – 28 2.2 – 2.8
106 to 140 30 – 38 3.0 – 3.9
SPA
150 to 200 36 – 45 3.7 – 4.6
over 200 40 – 50 4.0 – 5.1
112 to 160 40 – 50 4.0 – 5.1
170 to 224 50 – 62 5.1– 6.3
SPB
236 to 355 62 – 77 6.3 – 7.0
over 355 65 – 81 6.6 – 8.3
224 to 250 70 – 87 7.1 – 8.9
SPC 265 to 355 92 – 115 9.4 – 12.0
over 375 115 – 144 12.0 –15.0

INSPECTED/CHECKED BY: VERIFIED BY: WITNESSED BY:


Truwater's Representative Customer's Representative End User's Representative

(Signature) (Signature & Co. Stamp) (Signature & Co. Stamp)


Name : Name : Name :
Date : Date : Date :
Position : Position : Position :
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 13 of 15

ATTACHMENT 5

COOLING TOWER PRE-COMMISSIONING FORM


FORM : TCT-F-PC-0
…..providing solution to your cooling needs REV : 01
Truwater Cooling Towers Sdn Bhd (company No:188113-A) PAGE : 1 of 1

COOLING TOWER PRE-COMMISSIONING FORM

CUSTOMER : DATE :
PROJECT : JOB NO. :
TOWER MODEL : CELL NO.:

1. FAN Applicable Non-applicable

Fan hub and blades installed accordingly Fan blades free rotation (for gear drive without back stop)
Fan blades installed in proper sequence
Fan blades pitch angle shall properly set at °
Blade No. 1 2 3 4 5 6 7 8
Pitch Angle (°)
Fan tip clearances are properly set within the allowable range (Tolerance: 20mm - 40mm)
Fan bolts are properly tighten / torque
2.1 BELT DRIVE Applicable Non-applicable
Motor greasing No grease leaking found
Bearing housing and motor bolts are properly tighten / torque
Pulley properly tightened and aligned
2.2 GEAR DRIVE Applicable Non-applicable

Check gear oil level before commissioning


Check gear oil level after commissioning No gear oil leaking found
Gearbox and motor bolts are properly tightened / torque
Axial Alignment (Tolerance: within 0.5mm) Angular Alignment (Tolerance: ±0.25mm)
Position 0° 90° 180° 270° Position 0° 90° 180° 270°
Motor End Motor End
Gear Drive End Gear Drive End
Shaft alignment measurement within tolerance
Drive shaft DBSE (Distance Between Shaft End) : required mm actual mm
3. EXTERNAL & INTERNAL COMPONENTS Applicable Non-applicable
Fill and Drift Eliminator neat and properly installed
Distribution system and spraying nozzle properly installed
Casings are properly installed
Louvers (if applicable) are properly installed
Fan stack bolts are properly tightened / torque
4. REMARK (IF ANY)

Please tick [ ✓ ] the checkbox for compliance


INSPECTED/CHECKED BY: VERIFIED BY: WITNESSED BY:
Truwater's Representative Customer's Representative End User's Representative

(Signature) (Signature & Co. Stamp) (Signature & Co. Stamp)


Name : Name : Name :
Date : Date : Date :
Position : Position : Position :
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 14 of 15

ATTACHMENT 6

COOLING TOWER COMMISSIONING FORM


FORM : TCT-F-TNC-0
…..providing solution to your cooling needs REV : 0
Truwater Cooling Towers Sdn Bhd (company No:188113-A) PAGE : 1 of 1

COOLING TOWER COMMISSIONING FORM

CUSTOMER : DATE :
PROJECT : JOB NO. :
TOWER MODEL : CELL NO.:

1. MECHANICAL EQUIPMENT Applicable Non-applicable

Fan rotate in correct direction


Cooling tower motor rated Amp = A Flowrate = m3/h
Cooling tower motor running Amp = Red line A Water supply temp = °C
Yellow line A Water return temp = °C
Blue line A Ambient DB = °F
Cooling tower motor running Amp (Average) = A Ambient WB = °F
Cooling tower running at % of the rated Amp Motor voltage = V
Motor Running Amp (Average) Power consumption = kW
Efficiency (%) =
Motor Rated Amp
2. WATER DISTRIBUTION SYSTEM Applicable Non-applicable

Water evenly spray from nozzle


3. MOTOR VIBRATION Applicable Non-applicable
Acceptable vibration: ≤ mm/s (Vibration Severity Criteria: Max 7.6mm/s for standard cooling towers)

Vibration (mm/s.)
Check Point Horizontal Vertical Axial
Drive End
( DE )
Non-drive End
( NDE )

4. VIBRATION SWITCH (If applicable) Applicable Non-applicable


Brand : Model:
Adjustment done / Properly set
5. OIL LEVEL SWITCH (If applicable) Applicable Non-applicable
Brand : Model:
Adjustment done / Properly set
6. OVERALL COMMISSIONING
Overall commissioning activities had beed carried out to satisfaction
7. REMARK (IF ANY)

Please tick [ ✓ ] the checkbox for compliance


INSPECTED/CHECKED BY: VERIFIED BY: WITNESSED BY:
Truwater's Representative Customer's Representative End User's Representative

(Signature) (Signature & Co. Stamp) (Signature & Co. Stamp)


Name : Name : Name :
Date : Date : Date :
Position : Position : Position :
Commissioning
Doc No BES-SEG-RHB-PR-COM-001
COOLING TOWER COMMISSIONING PROCEDURE Revision 0

Page Page 15 of 15

ATTACHMENT 7

MEASURING INSTRUMENT CALIBRATION


CERTIFICATES
CALIBRATION CERTIFICATES OF TEST INSTRUMENT

INSTRUMENT BY TRUWATER

TRUWATER COOLING TOWERS SDN BHD


EXECUTIVE SUITE 702, BLOCK B
KELANA BUSINESS CENTRE
NO.97, JALAN SS7/2 KELANA JAYA
47301 PETALING JAYA,
SELANGOR DARUL EHSAN
TEL: 03 7880 8800 FAX: 03-7804 5519

Acceptance Test Instrument Certificates


1
ULTRASONIC WATER
FLOWMETER

Acceptance Test Instrument Certificates


3
DIGITAL POWER
METER

Acceptance Test Instrument Certificates


5
DIGITAL
THERMOMETER

Acceptance Test Instrument Certificates


9
WHIRLING
HYGROMETER

Acceptance Test Instrument Certificates


10
DIGITAL
INCLINOMETER

Acceptance Test Instrument Certificates


2
TENSION TESTER

Acceptance Test Instrument Certificates


3
VIBRATION
METER

Acceptance Test Instrument Certificates


4

You might also like