1. PURPOSE
The aim of this document is to list out all instrument serving as input or output of control
system to be supplied and installed for WORK.
2. SCOPE
The scope of this document applies to the whole control system be supplied and
installed for WORK.
3. DEFINITION
5. ATTACHMENT
ATTACHMENT 1
BES Control System I/O List
PROPOSED CONTROL SYSTEM Date: 1/3/2023
TNB Gold ETS ‐ I/O POINTS LIST Revision: 0.0
PARAMETER QTY Tagname DIGITAL HLI RTD ANALOG TREND LOG ALARM REMARKS
DO DI AI AO
Cooling Energy Meters
TNB Tower Energy Meter 1 EMTNBT
TNB Tower cooling power (kW) 1 1
TNB Tower cooling energy (MWhr) 1 1
TNB Tower flowrate (m3/hr) 1 FTTNBT 1 1
TNB Tower return temperature 1 TETNBT1 1 1
TNB Tower supply temperature 1 TETNBT2 1 1
Modulating Valves
TNB Tower temperature control valve 1 1 FCVTNBT1
TNB Tower temperature control valve 1 output signal 1 1
TNB Tower temperaturecontrol valve 1 shutoff status 1
Transmitters
TNB Tower network supply pressure 1 PTTNBT 1 1
TNB Tower network differential pressure 1 PDTTNBT 1 1
TNB Hotel network supply pressure 1 PTTNBH 1 1
TNB Hotel network differential pressure 1 PDTTNBH 1 1