Professional Documents
Culture Documents
CILT International Diploma in LT DIP-08 Production Planning Material V1.1 (1)
CILT International Diploma in LT DIP-08 Production Planning Material V1.1 (1)
CILT International Diploma in LT DIP-08 Production Planning Material V1.1 (1)
DIP-08
Production Planning
AO/INT/0064 – V1.1
Acknowledgements
We are grateful to the following contributors for their authorship of the material contained
in this document.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior written permission of the Chartered
Institute of Logistics and Transport (UK).
AO/INT/0064 – V1.1 II
Introduction to Study
Welcome to the study guide for the unit DIP-08 Production Planning, which is intended to
assist students in successfully completing the CILT International Diploma in Logistics and
Transport.
These icons represent key activities to be undertaken – specific activities have been set to
assist learning and references are made to the recommended textbook. Keywords and
important information are reinforced, where appropriate. The aims are clearly set out at
the beginning of each section and key benchmarks are listed on completion of these
sections to enable you (the learner) to monitor your own progress.
Key to icons:
Tasks
Case study
Suggested reading
Reading List
Make clear notes and bullet points where appropriate – make use of the highlighted
sections and icons within the course manual to guide you to the key information. Refer to
the recommended reading as directed. Develop all core information with wider reading.
Always remember that you will learn better when you have support available and that you
follow the learning process of reflecting, reconstructing alternative ways and then revising
what is done or thought about the subject. Support can be available via the Institute’s
Knowledge Centre as well as from colleagues and friends. Learning skills are important
also, more information is available in the bibliography at the end of this unit.
The International Knowledge Centre gives you access to information around the
world.
Students taking the CILT International qualifications will have e-access to the online
Knowledge Centre resources for duration of their studies. The password will be
provided to the training provider and it is their responsibility to ensure that it stay
confidential for use only by students, lecturers and learning resource managers
within the specific institution.
AO/INT/0064 – V1.1 IV
Contents
AO/INT/0064 – V1.1 V
List of Tables/Figures
Figure 1.1 Production Planning – From Idea to Customer ........................................................ 19
Figure 1.2 Production Planning Horizon ................................................................................... 29
Figure 1.3 Planning Stages from Forecast Demand to Production ............................................ 30
Figure 1.4 Combining Known Order and Forecast Orders ........................................................ 31
Figure 1.5 Materials Requirement Planning (MRP) Diagram .................................................... 38
Figure 1.6 Inputs into the Master Production Schedule (MPS) .................................................. 39
Figure 1.7 The Three Dimensions of Forecasting Techniques and Examples of Data and
Intelligence Sources ..................................................................................................................... 51
Figure 4.1 Typical Management Activities involved in Production Planning ............................ 131
AO/INT/0064 – V1.1 VI
Abbreviations
APS Advanced Planning and Scheduling
BOM Bill of Material
CILT The Chartered Institute of Logistics and Transport
CPOF Capacity Planning using overall factors
CPFR Collaborative Planning Forecast and Replenishment
CRM Customer Relationship Management
CRP Capacity Requirements Planning
CSR Corporate Social Responsibility
DSS Decision support system
EDI Electronic Data Interchange
EIA Environmental Impact Assessment
ERP Enterprise Resource Planning
ES Expert System
FMEA Failure Modes Effects Analysis
GPS Global Positioning System
IT Information Technology
JIT Just In Time
LAN Local Area Network
MIS Management Information System
MPS Master Production Schedule
MRP Material Requirements Planning
MRPII Manufacturing Resource Planning
MTBF Mean time between failures
MTO Make to Order
MTS Make to Stock
RCCP Rough Cut Capacity Planning
RF Radio Frequency
RFID Radio Frequency Identification
SAP Leading ERP software
TQM Total Quality Management
WAN Wide Area Network
WEEE Waste electronic and Electrical Equipment (regulations)
WIP Work in Progress
Activity Based Costing (ABC) - an accounting system that links costs directly to the
activities that drive them.
Alternative Dispute Resolution (ADR) - is the collective term for the ways that parties
can settle civil disputes, with the help of an independent third party and without the need
for a formal court hearing.
Bill of Materials (BoM) - is the quantification of the materials and components that are
necessary for the manufacture of the products required from the MPS.
Bottleneck items - Need to ensure the supply and reduce the risk on non-supply and
disruption to the business.
Buffer stock - is that held to cover the unexpected use during the supply lead time, any
uncertainty in supply and/or in demand and to provide a higher levels of stock cover for
availability. It is also known as safety stock.
Cycle stock is that held to cover the normal in/out movements from normal order policies;
it is also known as replenishment stock.
Cycle time - the actual time between receipt of an order or initiation of an activity to the
time the activity ends or the time the order is received.
Direct costs - are costs that are tied directly to an activity, product or service.
E- commerce - the buying and selling of products and services over the internet, the term
now used to refer to the whole process of developing, marketing, selling, delivery and
payment of products and services online.
E- fulfilment - the complete electronic process from point of sales inquiry to delivery of a
product to the customer.
E-business - a term used to refer to trading between organisations and their business
customers by electronic means, i.e., business-to -business (B2B).
Economic Order Quantity (EOQ) - result of a calculation that determines the most cost
effective quantity to order (purchased items) or produce (manufactured items). The
formula basically finds the point at which the combination of order cost and carrying cost is
the least.
End customer – the ultimate user of the product, which may not be the same as the
organisation or individual who places the order and/or pays for the product.
Fixed costs – costs that an organisation incurs regardless of the level and timing of
activities, and cannot be changed very quickly.
Indirect costs - these are costs that are not tied to a product/service or level of
operations.
AO/INT/0064 – V1.1 IX
Inventory - stocks and items used to supply organisational operations and customer
service.
Lead Time (LT) - the time elapsed between the receipt of an order or request to the time
that order or request is fulfilled.
Leverage items are those where a high volume is purchased. Here therefore the need is
to obtain at the lowest cost.
Life Cycle costing and can be defined as: “The systematic consideration of all relevant
costs and revenues associated with the acquisition and ownership of the asset.” It is the
same with whole life costing.
Master Production Schedule (MPS) - the total requirements from customer orders and
any provisional demand for a specific time period.
Material Requirement Planning (MRP) – a planning process that translates the master
production schedule (MPS) into planned orders for actual parts and components (based
upon the BoM) needed for the production of items on the MPS.
Open tenders - invite everyone and are only really useful where a small number of
suppliers are expected to respond.
Opportunity costs - the cost of not having the money available for alternative
investments, which would earn money or the interest payable on loans to finance work.
AO/INT/0064 – V1.1 X
Postponement - a manufacturing/distribution strategy where specific operations
associated with a product are delayed until just prior to shipping. Storing product in a
generic state and then applying custom labels or packaging before shipping is an example
of postponement.
Product Life Cycle (PLC) - a concept that states that products and services evolve
through a life cycle so that specific management techniques apply at each of the stages in
the life cycle.
Primary sector - these companies are engaging in the extraction of raw materials or
products from ‘mother earth’ from, farming/fishing (food, beverages, and forestry),
quarrying/mining (minerals, coals and metals) or drilling (oil, gas, water).
Proof of Delivery (POD) - evidence that goods or a service has been received, usually
signed document by recipient or their representative.
Purchasing ‘Rights’ - Securing supplies, materials and services of the right quality in the
right quantity at the right time from the right place (source) at the right cost.
Purchasing cycle - the whole procurement process from need identification to receipt of
goods including supplier performance appraisal.
Quick Response (QR) – an information and logistics system that aim to provide and
supply the right product of the right quality to the right place at the right time. This derives
from the need to be competitive by responding to market needs quickly.
Reverse logistics - the management of the flow of goods upstream, usually unwanted,
used, damaged or packaging materials.
AO/INT/0064 – V1.1 XI
Safety stock - is that held to cover the unexpected use during the supply lead time, any
uncertainty in supply and/or in demand and to provide a higher levels of stock cover for
availability. It is also known as buffer stock.
Service or tertiary sector - business, personal and entertainment services, which involve
the channels of distribution from suppliers to customers via direct, wholesale or retail
channels. Services include packaging, physical distribution, transport, hotels, catering,
banking, insurance, finance, education, public sector, post, telecoms, retail, repairs, etc.
Six rights – refers to the objectives of logistics planning, i.e., ensuring that the right
product, is delivered to the right place, at the right time, in the right quantity and quality
with the right supporting information.
Supply chain - comprises all activities associated with the flow and transformation of
goods from raw material stage through to the final consumer.
Supply chain flows - the movements as ‘material, information and money flows’ in a
supply chain.
Supply chain integration - the coordination of the flows of information and materials from
source through production up to final consumption in a supply chain.
Trade-off - a compromise of one activity or function in order to gain in another for the
overall benefit of the system or whole.
Upstream - relates to activities and partners from the supply side of a supply chain.
Variable costs these are cost that change with the scale of level of operational activity.
Whole Life Costing (WLC) - is the same as Life Cycle costing and can be defined as:
“The systematic consideration of all relevant costs and revenues associated with the
acquisition and ownership of the asset.”
AO/INT/0064 – V1.1 XV
This page is intentionally blank
1.1.1 Introduction
Important terminology used within this element is categorised below.
Definitions of these terms and concepts are given in the text.
Aggregate plan;
Demand management;
Just in Time (JIT);
Lean production;
Master Production Schedule (MPS);
Material Requirement Planning (MRP);
Strategic planning;
Production planning.
AO/INT/0064 – V1.1 17
1.1.2 The Basic Concepts of Production Planning
Nowadays global developments have a
profound effect on industry,
necessitating frequent and on-going
revaluation of business practices and
priorities, particularly (but not
exclusively) in areas of production
planning.
18 AO/INT/0064 – V1.1
Figure 1.1 Production Planning – From Idea to Customer
Idea
Design
Marketing Procurement
Test
Sales Finance
Prove
Manufacturing product or Prototype Logistics
idea
I.T.
Planning
Forecasting
Product/idea
launch
Launch
On-going
Production
Customers
sales forecast;
customer expectations;
AO/INT/0064 – V1.1 19
production capacity (change over times and cost/run sizes);
warehouse capacity;
maintenance plan/strategy;
quality issues;
The broad objective(s), which any operations within the company must
pursue to satisfy the stakeholders, form the foundation for all production
and operational decision making.
20 AO/INT/0064 – V1.1
Task 1.1
Quality of product;
Speed of production;
Dependability;
Flexibility;
Cost consideration.
AO/INT/0064 – V1.1 21
Task 1.2
22 AO/INT/0064 – V1.1
1.1.3 Production Planning in a Changing Business
Environment
capital budgets for plants and equipment and shorter term operating
budgets;
production plans;
personnel needs;
transportation requirements.
AO/INT/0064 – V1.1 23
Task 1.3
A computer company estimates that it will sell 4 million units per annum.
In reality it only sells 2.7 million.
What are the effects that this might have on the following:
a) the whole organisation; and
b) the production department?
For example, a small engineering firm with lathes, milling and polishing
machines will have to manage production of many different orders for
many different customers all at the same time every week. A production
plan for all the different parts required each week and the raw material
requirement will be more complicated than that of a business with only
standard products and dedicated production lines and operating staff.
24 AO/INT/0064 – V1.1
1.1.4 Links between Production Planning and Business
Planning
When the customer places an order, one of the models in their chosen
colour, with the correct sized engine will already be in production and is,
therefore, allocated to that customer.
Customers (as any discussion with a car salesman will reveal) are then
also able to choose from a wider range of options, in terms of external
trim, audio systems, interior colour and vehicle accessories – all of which
can be added to the manufacturing assembly, effectively giving the
impression of customisation.
AO/INT/0064 – V1.1 25
Therefore, the manufacturer has to predict ahead the likelihood of the
required mix of models and colours and the likely mix of options that its
customers may choose to purchase and have these products available in
its inventory.
Making the production plan work involves managing all the elements to
ensure raw materials, parts and sub-assemblies of the right quality and
quantity are at the correct location on time to contribute to the production
of finished goods in time to meet customer expectations. To assess the
progress being made the actual production needs to be compared with the
forecast at a convenient stage to identify any issues.
Customers will sometimes change their minds about what they require,
even after having placed their orders. Because customer service and
flexibility are becoming increasingly competitive factors, the opportunity to
change their requirements and specification is becoming an increasingly
common feature in many manufacturing operations.
26 AO/INT/0064 – V1.1
In fact, in a business-to-business supply chain relationship, it may be the
customers’ customers who are the cause of the change in requirements.
The term planning covers all those activities required for the
organisation’s/company’s desired objectives to be met.
In business, the planning process generally has its roots in the strategic or
long range plan, which is then broken down into a more detailed operating
plan:
A strategic plan has a nominal time horizon of about five years; through
this period may be longer or shorter depending on the nature of the
industry and organisation.
The time horizon for the operation/production plan is usually around one
year – but again this figure may vary and for some businesses may be
up to 18 months.
Short range plans usually consider the activities over less than a 3 month
period and perhaps in some cases just one week or one day time periods.
AO/INT/0064 – V1.1 27
The business activities usually considered in such plans may include:
Within the short term planning period Just In Time (JIT) and Lean
Production management methods are used.
sales plans;
staffing levels;
production planning.
28 AO/INT/0064 – V1.1
Figure 1.2 Production Planning Horizon
J.I.T. MRP
TASKS TASKS
Depending on business
3 Months 18 Months
These plans are closely interlinked (see Figure 1.3) and when a change
occurs to any one variable in one plan, other variables and options in both
that and the other plans occur.
AO/INT/0064 – V1.1 29
Figure 1.3 Planning Stages from Forecast Demand to Production
Firm order or
forecast demand
Aggregate plan
Master production
schedule (MPS)
Material requirement
plan (MRP)
Production schedule
Similarly, poor planning for labour and/or machinery use can diminish an
organisation’s capacity, meaning that products cannot be produced and
delivered to the customers when promised.
Task 1.4
Consider and then evaluate, for any chosen manufacturing company the
impact that a customer, who, having placed and confirmed their order,
then makes:
30 AO/INT/0064 – V1.1
Combining known and forecasted orders is used to represent the demand
in many businesses – this should be the best estimate, at any time, of
what reasonably could be expected to happen in terms of customer
demands and orders for the product(s).
Total demand
Forecast
Demand
Known orders
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
Most businesses have knowledge about the short term demand for
individual orders; however, very few customers place their orders well into
the future. Based on history and market information (from sales reports) a
forecast is put together to reflect likely demand.
As orders come in, the forecast element of the demand profile should be
reduced, giving the impression of the forecast being ‘consumed’ over time
by ‘firm’ orders.
AO/INT/0064 – V1.1 31
It must be appreciated that the above explanation is just an overview of
the way customers order are anticipated and combined with planning for
the actual production of the product(s). Different types of operations have
different profiles, in terms of the mix of known and forecast orders.
From the planning and control perspective – the output from the demand
management is a predication into the future about what the customer will
require to purchase – both in terms of quantity and specification.
32 AO/INT/0064 – V1.1
1.2.3 Management Development
The effectiveness of any business may be measured by a number of
factors, such as:
The right skill set of labour and management is essential to the successful
running of a production process. It is recommended to train and develop
labour, as well as to develop succession plans and put in place holiday
cover for every skill required.
Skills gap analysis can define the requirements of the training and
development needs of all the staff. The training plan may include group
training as well as individual training requirements for key skills.
AO/INT/0064 – V1.1 33
Typical training courses that may be considered are as follows:
presentation skills;
time management;
sales;
customer service;
communication.
34 AO/INT/0064 – V1.1
The better and more up to date the data the better the forecast will be.
It can be argued that the best estimate of the future is the present and so
we should allocate more importance to the most recent data in trend
estimating.
Short term forecasts are more tangible and based on historic usage in
disaggregated form with every detail on each item and component. It
needs to consider availability of raw material items from stock, from order
and lead times from suppliers, as well as production capacity available
and capacity required, labour required (skilled and unskilled), cash flow
implications and warehousing capacity for raw materials and finished
goods. Planned maintenance of machinery may also need to be
considered.
Task 1.5
Discuss the differences between long term and short term forecasting
and the implications of changes in customer demand.
AO/INT/0064 – V1.1 35
1.2.6 Demand Management
Demand management is the combination of the management of sales
forecast and customer orders.
demand forecasting;
order promising;
customer service;
physical distribution.
For example when you contact any customer services department on the
telephone about the delivery date of any goods, the operator will use a
computer to access the details of your particular order and be able to
advise the current status of the order and provide the expected delivery
date and the way it will be delivered, by post or by courier.
The interaction with customers and the resulting requirements from that
interaction, make a chain reaction of production planning requirements.
To meet the customer expectation, the item needs to be picked from stock
in the warehouse; the warehouse needs to have the details to ensure the
correct item is selected and a courier or other means of transport needs to
be arranged for a particular time.
36 AO/INT/0064 – V1.1
Case Study – Demand Forecasts
AO/INT/0064 – V1.1 37
1.2.7 Master Production Schedules (MPS)
The master production schedule (MPS) is the most important planning and
control schedule in business and forms the main input to materials
requirements planning, as shown in Figure 1.5.
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
The MPS contains a statement of the production volume and timing of the
finished goods to be manufactured. This schedule drives the operation
and determines what is assembled, what is ordered and what is
manufactured.
planning;
38 AO/INT/0064 – V1.1
Figure 1.6 Inputs into the Master Production Schedule (MPS)
Known orders
Forecast demand Key capacity
constraints
Inventory
Sister plant demands levels
Spare demand
Research &
Development
Safety stock requirements
Promotional requirements
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
AO/INT/0064 – V1.1 39
It is important that all sources of demand are considered when the MPS is
created – it is usually the loss/lack of the odds and ends of the stock
required by the business that may disrupt the whole of the planning
system. For example, certain parts/components or materials may be
taken to build a demonstration model, the factory will/may then be short of
the required components; also, a sister company may ‘borrow’ a spare
part at short notice for their own needs – which if not incorporated into the
plan, may lead to a deficit at the company and ultimately disruption if that
unit/part is subsequently required.
The output from the MRP system comprises purchase orders, materials
plans and works orders which trigger the purchasing and/or manufacture
of parts.
The Master Schedule drives the rest of the MRP process. Having
established this top level schedule, it performs the calculations to work out
the volume and timing of assemblies, sub-assemblies and the materials
needed to meet the master system.
40 AO/INT/0064 – V1.1
Case Study
1.3 Summary
Having completed this element you should now have a clear
understanding of:
AO/INT/0064 – V1.1 41
Task 1.6
The company is a market leader with a turnover £50 million per year.
The MRP translates orders and forecasts into work instructions for
purchasing and manufacturing of the parts, sub-assemblies and finished
products.
The main problem encountered by the company, was that after running
the MRP process, finished goods were put into stock to await a
customer order.
When the order was received, the finished goods never exactly matched
the forecasted demand. Some products had to go back into stock to be
re-manufactured into a configuration that the customer really wanted;
while other finished goods for customers remained on the shelves.
Discuss:
b) The solutions (in terms of planning and control) that may help the
company redress the situation.
42 AO/INT/0064 – V1.1
2. Fundamentals of Production Planning
Learning Outcomes
Aggregate plan;
Bill of Material (BoM);
Capacity Requirement Plans (CRP);
Closed loop material requirement plans;
Master schedule;
Material Requirement Planning (MRP);
Produce to order;
Produce to stock;
Resource requirement plans;
Rough cut capacity plans.
AO/INT/0064 – V1.1 43
Master scheduling is the key-planning tool that determines a time horizon
in weeks or months (depending on the company or nature of the
manufacturing process) indicating what end items need to be completed.
These may include:
44 AO/INT/0064 – V1.1
2.1.2 Rough Cut Capacity Planning (RCCP)
The master schedule is developed from:
forecasts;
The most urgent orders are placed in the first available open slot of the
master schedule and then, as all the orders are slotted, in a rough cut
capacity plan emerges that shows the load of the production work centre
in relationship to the available capacity.
The load may equal the capacity or the system may be under loaded or
overloaded.
Week 1 2 3 4 5 6 7 8 9 10 11 12 13
Committed 220 180 160 45
TOTAL 220 180 265 275 240 190 275 270 210 215 250 180 140
The data in Table 2.1 shows, for a manufacturing company, the number of
schedule units that have to be finished each week over a time horizon of
13 weeks according to whether they are committed (that is a firm
customer’s order) expected (not a firm order, but an order that is fairly
definite) and forecasted (based on anticipated/expected) sales.
The production capacity for this (and any) company is fixed according to
the capacity of the machinery and the labour force (when the data is
transposed on to the MPS) – in this instance it is determined at 240 units
per week.
AO/INT/0064 – V1.1 45
Unloading is where, on the initial MPS, not enough production has been
scheduled, so that the facility is not fully loaded (and thus not operating at
optimum capacity) – in this instance, this is occurring in weeks 1, 2, 6, 9,
10, 12 and 13.
Overloading occurs when too much production has been scheduled and
the production schedule is at over capacity. For the above company, this
is occurring in weeks 3, 4, 7, 8 and 11.
The purpose of the rough cut capacity plan is to see where any
adjustments to production can be made – with the aim of balancing the
manufacturing production process.
Table 2.2 Loaded Demand Data with Balanced Capacity for a Manufacturing
Company
Week/
1 2 3 4 5 6 7 8 9 10 11 12 13
Period
Committed 240 240 125 0 0
Planned 0 0 115 240 240 240 240 155 150 100 30 10
Forecast 0 0 0 0 0 85 90 140 210 230 140
TOTAL 240 240 240 240 240 240 240 240 240 240 240 240 140
Table 2.2 shows how the total units for each category has remained the
same, but that by adjusting the production loading, adjusting the weeks
that had over and under loa ding, the system is now completely balanced
and any excess load and spare capacity has been left for week/period 13.
46 AO/INT/0064 – V1.1
Table 2.3 Master Production Schedule: Balanced
Production Froz Froz Fixed Fixed Fixed Full Full Full Full Open Open Open Open
240
220
200
180
160
140
120
100
80
60
40
20
Week 1 2 3 4 5 6 7 8 9 10 11 12 13
The frozen period (the first stage) covers the weeks/periods where there
are all the committed units, as shown in Table 2.3 for weeks 1 and 2. The
implication of the definite planning is made in terms of using the staff,
machines and materials optimally and during this time frame any changes
would seriously disrupt the operations.
The fixed period (the second stage) is programmed for the remaining
committed and some planned units, as illustrated in Table 2.3 during
weeks 3 to 5. This time frame is considered as being fairly rigid, though
less so than the frozen period.
The plans during this period may be modified, but only under exceptional
circumstances and in reality any changes would be resisted as much as
possible.
The full period (the third stage) contains the planned and forecast units
(weeks 6 to 9 in Table 2.3). During this period all available production
capacity has been allocated, but changes may be made without an
excessive increase in production costs.
AO/INT/0064 – V1.1 47
The open period (the fourth and final stage) is the most flexible in terms of
modifications to the productions schedule. Here not all the production
capacity has been allocated (as shown in week 13 in Table 2.3) and so
this is where any new orders may be allocated.
Task 2.1
Whilst the schedule, once established is not flexible, especially in the early
frozen and fixed periods, it does reinforce the importance for effective
supply chain management and that the production, sales and finance
aspects of the business should be closely involved in the preparation of
the master schedule and that ALL should make the commitment to support
the plan, once an agreement has been made.
Any last minute changes may represent cost (both in terms of financial
and time inconvenience) to the company, whether this arises through
under-utilisation of the machinery and stock, stock lying on shelves, delays
to customer orders, lack of adequate components to complete orders,
customer dissatisfaction, etc.
48 AO/INT/0064 – V1.1
Case Study – Increased Productivity
His analysis showed that the method of production was wasteful on time
and also materials, resulting in cost of production that was too high and
non-competitive. He re-organised the factory unit into areas of expertise
which still allowed the joiners to use their skills, but it dramatically
increased productivity. Without this intervention, the company would have
gone out of business.
Task 2.2
Aside from the business closure, what were the implications of their
business practices for:
AO/INT/0064 – V1.1 49
2.1.3 Demand Forecasting
Demand forecasting is a most important element in production planning.
The outcomes of such forecasting will affect the:
volume of output;
inventory levels.
opinion;
the analysis of correlation with one or more variables that can be linked
to product demand.
50 AO/INT/0064 – V1.1
Opinion based forecasts may draw on information and data from a variety
of sources, including:
AO/INT/0064 – V1.1 51
It is, therefore, essential to understand what a forecast is and the
strengths and weaknesses of different methodologies used in estimating
demand. The latest software systems continually strive to improve
forecasting. It is not an exact science as there are many dynamic
variables, both internally but also external factors are now so important.
Most businesses are operating in a global market, and so many external
events can also affect demand forecasts. In the early 21st century we
have experienced national events that immediately have impacted
companies worldwide. For example: earthquake and tsunami in
Fukushima, Japan. This impacted the supply lines of many industries
such as auto manufacturing and hi-tech electronics worldwide especially
within Europe where car factories went on short time working for a number
of months due to supply chain disruptions to auto assembly components
manufactured in Japan.
Where, for example, the annual sales of a product are plotted on a graph,
and then from the scatter of these points a trend line is added, indicating
the best fit between all these variables. At this simplest level, this trend
line can be drawn by eye; although there are now computer packages
which will do this and more complex trend lines (such as regression lines;
least squares regression lines, etc.)
The simple way of smoothing out the effects of random variation in, say
product demand, is to take a moving average.
The term moving average is used when each time the average is taken for
the latest (n) set of data. The set moves forward each time by dropping
the earliest piece of data and incorporating the most current figure.
52 AO/INT/0064 – V1.1
Figure 2.1 Moving Averages
Task 2.3
a) garden furniture?
AO/INT/0064 – V1.1 53
2.1.5 Basic Process
MPS in manufacturing contains details of volume and timing of the finished
goods. This schedule drives the whole production process in terms of
what is purchased, what is manufactured and what is assembled.
stock levels;
spares demand;
customer orders;
safety stocks;
promotional requirements;
seasonality;
Week no.
1 2 3 4 5 6 7 8 9
Demand 20 10 20 10 15 15 15 20 20
Available 15 5 0 0 0 0 0 0 0
MPS 0 0 15 10 15 15 15 20 20
On hand 35
54 AO/INT/0064 – V1.1
In this example (Table 2.4) the opening balance of stock for the item is 35.
The demand in week 1 is 20, leaving 15 available for the following week.
In week 3 the demand is 20, 5 are available from week 2 and therefore
MPS needs to be 15 to produce the balance.
The accuracy of the data in the latter part of the schedule is not as reliable
as the early weeks, which are usually dominated by firm customer orders,
whereas the latter end is dominated by forecast information and data.
The planning horizon for the MPS can be increased from a few weeks to
months. Whilst this largely depends on the nature of the industry, the time
horizon should at least be equal to the longest cumulative end item lead
time.
The cumulative end item lead time is based on the length of the supply
chain and is the amount of time taken to:
assemble items;
It is the end item with the greatest cumulative lead time in the supply chain
that determines the span of the planning horizon, although in reality, the
planning horizons are usually greater than this minimum figure.
AO/INT/0064 – V1.1 55
2.1.6 Produce to Order Master Scheduling
The total throughput time in
production planning includes three
elements:
purchase time;
manufacturing time;
delivery time.
The demand time is shorter in MTS scheduling and this method will
provide the quickest delivery to customers, the disadvantage with this
approach is that the business will need to carry a stock of each item and
determine what quantity of each item to hold in stock. This stock will have
to be financed and that will impact on the available working capital.
Scheduling work in from backlog and the product forecasts may never be
used.
In updating the MPS, orders in the backlog are assigned open production
slots and the number of products to produce in an order (lot size) is
usually determined by the customer requirements.
If a customer orders, say 1000 desks, ordinarily 1000 of these desks will
be produced for that order. This approach to lot sizing is call lot-for-lot.
56 AO/INT/0064 – V1.1
Since the product to order firms have many product designs, the number
of product references that have to be placed in the MPS can be very large.
Lot size is an important part of MRP and depending on lot size, ordering
components by lots, results in periods of high inventory when the materials
arrive, interrupted by longer periods with falling inventory as the materials
are consumed.
In the early part of the MPS, the warehouse orders, which were based on
forecasts, may be backed up by actual customer orders.
AO/INT/0064 – V1.1 57
When large lot sizes are produced in any one period then:
the carrying costs are higher for finished goods than for the raw
materials, this is because of the value added activity in the production
process.
If small lot sizes are produced (i.e. as in Just in Time and Lean Production
Methods) in any one period then:
Task 2.4
c) The types of products that may be produced in large and small lots.
Task 2.5
58 AO/INT/0064 – V1.1
Measuring Performance
quality;
speed;
dependability;
flexibility;
cost.
impact of measurement;
The MPS within MRP is said to be open loop, as the system has no
feedback loop to confirm the actual production quantity at the end of each
time period or time bucket.
Rough-cut capacity plans fill this gap and provide a link to effectively close
the loop for MRP.
Rough cut capacity plans (RCCPs) are a form of closed loop MRP.
They provide a feedback loop at the end of each weekly or monthly time
bucket in MPS to check the MPS against known capacity bottlenecks and
key resources to ensure they are feasible.
AO/INT/0064 – V1.1 59
2.2 Materials Planning and Capacity Management
2.2.1 Planning and Control
The division between planning and control changes over time.
The blend of planning and control will vary over time. Planning will tend to
dominate in the long term (months, years) and control will tend to
dominate in the short term (hours, days).
The MRP system is a computer based system and many companies have
developed or purchased one of the commercial available software
packages.
60 AO/INT/0064 – V1.1
The MRP is driven by the MPS (see Figure 2.2) and the basic purpose is
to indicate:
When to place the orders, either for purchases from outside or inside
the company, taking into account the lead time for the materials to
arrive or be produced.
As a planning tool the MRP provides the precise control for manufacturing
operations regarding the amount and timing of the deliveries of the
materials needed to produce the end items, as identified in the MPS.
Such a planning tool helps to:
MRP is one of the major planning tools for supply chain management –
linking the purchasing and manufacturing activities within the company.
AO/INT/0064 – V1.1 61
Figure 2.2 Material Requirement Plans (MRP) Open Loop System
62 AO/INT/0064 – V1.1
A detailed file would provide details of the following:
transactions;
receipts;
disbursements;
scrapped material;
planned orders;
Also in the inventory file will be the lead time or the time required to
produce a production lot in-house or to receive a lot purchased from a
supplier.
To take account of the lead time a requirement in one time period will
necessitate the release of the order in some earlier period according to the
estimated delivery period.
When the inputs have been estimated, the MRP will generate the
necessary outputs, which will be the purchase requirements for any
products needed to be obtained from outside the company and also the
products required to be made in-house.
AO/INT/0064 – V1.1 63
Some of the more common generally used terms, and their definition are:
Gross Requirements
The material available for use during the corresponding time period.
These may include units held in storage from previous time periods, safety
stock or schedule receipts expected to arrive during the time period in
question.
Allocated Inventory
Material in storage but which is destined for purposes other than the MRP
being developed, for example, spares held for another production process.
Safety Stock
Schedule Receipts
Net Requirements
64 AO/INT/0064 – V1.1
Planned Order Releases
Quantities of the units that need to be planned for release, within a certain
time period, so that they are available to meet planned order receipts at a
future date. The formula for calculating the lead time is:
Whilst, it is hoped that 100% of the material will be available and used, in
reality this may not be the case – especially as some parts and/or
materials may:
be damaged;
In these cases, and to allow for such situations, the yield of the component
needed to be at a higher level will be less than that actually put into
operation at the lower level.
The yield rate is % of the starting material that actually ends up being
utilised and incorporated into the final product.
This yield rate takes into account the proportion of the material that does
not conform to the specified requirement and is, therefore, unusable in the
production process.
AO/INT/0064 – V1.1 65
The actual order quantity (Q) is given by the relationship:
net requiremen t
Q
100 scrap %
Where (100 - Scrap %) is the yield rate.
For example:
800
Q
1.0 0.04
Bills of material contain a full list of all parts and which parts fit on to other
parts to form sub-assemblies. The same part may be used on several
sub-assemblies in different quantities. The total quantity required for each
part to complete one finished product including packaging, is held in the
Bill of Materials.
Bills of Material for different product types are defined in product structures
or shapes, which relate to product designs.
Typical shapes of BoM product structures are ‘A’, ‘T’, ‘V’, and ‘X’.
66 AO/INT/0064 – V1.1
‘V’ shaped product structures describe products which are similar to the
‘T’ shaped structure but with more possibility to combine and mix the
sub-assemblies to form different products. For example, the mixing and
blending of different liquids to produce a range of shampoo products.
Task 2.6
Prepare a bill of materials (BoM) for a plastic ballpoint pen (e.g.: Bic).
AO/INT/0064 – V1.1 67
The MRP system will be able to determine the quantities of each part for
each sub-assembly to ensure that the customer order is satisfied. If a
particular item is used in more than one sub-assembly then the MRP will
calculate the total quantity and the due dates for the items to ensure the
finished vehicle is available for the customer on time.
what is required?
when is it required?
68 AO/INT/0064 – V1.1
Combining this information with knowledge of the lead times for the
delivery of the components and the materials from the suppliers enables
the purchase dates for the components and materials to be determined.
The success of the MRP is dependent on the inputs from the other
components - an accurate BoM; realistic MPS and accurate inventory
records.
The plans will project the forecast work loading and if necessary
temporary labour or resources can be used to support the future workload.
AO/INT/0064 – V1.1 69
2.2.5 Links to Other Planning Systems
MRP or ‘baby MRP’ as it is sometimes called was created in the 1960s
and has been developed and refined to include feedback loops to plan and
control production and inventory in manufacturing businesses.
When the MRP was originally used in manufacturing, material plans were
instigated at the beginning of each week, then a complete re-planning
exercise took place the following week – creating a new set of plans.
This process was repeated weekly but there was no feedback mechanism
to identify and determine either:
Closing the planning loop in the MRP system, involves checking the
production plans against the available resources, so that capacity is
checked throughout the process and if the proposed plans are NOT
achievable at any levels they are revised.
Today the simplest MRP systems are now ‘closed-loop’, using three
planning routines to check the production plans against the operation’s
resources.
70 AO/INT/0064 – V1.1
Figure 2.3 Closed-Loop MRP System
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
These plans are static level plans that involve looking forward in the long
term to predict the requirement for large structural parts in the operation,
such as the numbers, locations and size of new plants and factories.
Because they are attempting at facilitating the long term production plan
by making arrangements to have the required resources available, they
are sometimes termed ‘infinite capacity plans’; as they assume on an
almost infinite ability to step up production, if demand warrants it.
These plans are focused towards the medium and short term planning of
the organisational and production processes.
The feedback loop at this level only checks the MPS against known
capacity bottlenecks and key resources.
If the MPS is identified as NOT being achievable (at this phase/level) then
it needs to be adjusted.
AO/INT/0064 – V1.1 71
Unlike the RRP, the rough-cut capacity plans are ‘finite capacity plans’, as
they must operate within certain (pre-determined) constraints.
On the day-to-day basis, the work orders intended to be issued from the
MRP will often have a variable effect on the work (and production) loading
of particular machines and/or workers. CRPs project and anticipate the
potential future effects of any loading.
CRPs are ‘infinite capacity plans’, in so much as they do not take the
capacity constraints of each machine or work area into account. If the
loading is lumpy, it may be smoothed by re-planning to a ‘finite capacity’ or
by allocating temporary resources to that work area.
The closed-loop system of the MRP can (and often is in industry) further
be developed to drive very short term plans, such as that show in Figure
2.4.
Figure 2.4 Closed-Loop MRP System in Reality
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
72 AO/INT/0064 – V1.1
2.2.6 Production Control
Responsibilities of production control include the following:
training of labour;
lead times;
contact details;
emergency procedures;
waste handling;
AO/INT/0064 – V1.1 73
The number of possible schedules rapidly increases as the number of
activities and processes increase. The task of scheduling needs to be
repeated frequently to reflect any changes in the market and product mix.
Minor changes to the product mix may result in capacity constraints
creating bottlenecks that will move around the facility.
In an ideal situation the company would have a plan that is repetitive and
can be effected with a steady rhythm – such as producing similar
quantities of materials each week using the same machines and a level
labour force – all this would make the organisation process very simple.
However, in reality, client requirements are rarely constant and there may
be peaks of high demand and troughs of low demand.
74 AO/INT/0064 – V1.1
The efficiency of the aggregate plan is expressed as:
Actual output
Efficiency
Facility capacity
labour force;
financial resources;
materials; and
machines.
In the short term, the physical space is not normally a variable – and being
fixed, is considered and included as part of the longer term capacity plans.
Temporary workers;
Weekend working;
AO/INT/0064 – V1.1 75
Demands of backordering – where the customer’s order is booked and
it is indicated that the delivery will be made some time in the future –
the details are then recorded on the manufacturing company’s books.
However, while backordering may be appropriate for custom made
products, the client may not accept such ordering, preferring a set date
for delivery.
Task 2.7
76 AO/INT/0064 – V1.1
2.3 Summary
Having completed this element you should now have a clear
understanding of:
Desegregation forecasting.
Task 2.8
A company manufactures, for retails stores, racking and the wire basket
containers that fit into the racks.
1 meter rack;
2 meter rack;
3 metre rack.
The 1 metre rack requires 10 metres of section and is supplied with 12
nuts and bolts and 3 small baskets.
AO/INT/0064 – V1.1 77
The 3 metre rack requires 37 metres of section and is supplied with 30
nuts and bolts and 6 small baskets, 4 medium baskets and 2 large
baskets.
The production department can produce at the rate of 100 of the 1 metre
pack per day or 80 of the 2 metre packs per day or 60 of the 3 metre
packs per day.
An allowance of 10 per cent has to be made for scrap with the work
involved with the galvanised steel section.
(a) Draw up a bill of materials for the three standard racking packs.
(b) The company has decided to plan for steady requirements for 100
of the 1 metre packs per week; 200 of the 2 metre packs per
week and 120 of the 3 metre packs per week. The Table below
shows current stock levels and lead times for additional stocks to
arrive. Draw up an assembly schedule and MRP, indicating
clearly the size of the orders to be placed and when.
78 AO/INT/0064 – V1.1
3. Current Manufacturing and Materials
Planning Systems
Learning Outcomes
Benchmarking;
Customer Relationship Management (CRM);
Customer service performance measures;
Enterprise Resource Planning (ERP);
Just in Time (JIT);
Kaizen;
Kanban;
Lean production;
Manufacturing Resource Planning II (MRP II);
Master production schedule;
Operational audit;
Performance measures;
Route master planning schedule.
AO/INT/0064 – V1.1 79
3.1 Current Manufacturing and Materials Planning
Systems –Introduction
3.1.1 Monitoring and Improving Performances
All businesses, in order to survive must
be competitive and attract (and retain)
customers. They must also be efficient,
perform quality work and operate at the
lowest possible cost.
80 AO/INT/0064 – V1.1
The emphasis of such an approach is determining and optimising the level
of customer satisfaction – as, irrespective of the product, these are the
clients for whom the business is in existence – and any shortfall in quality
(of goods/products and/or service levels) may result in:
Once the global perspective has been established, the whole business
organisation is then broken down into the different operational
components/segments (i.e. production process; specific elements in the
assembly line, etc.) and a detailed audit of each undertaken sequentially.
All organisations, no matter how well they are managed or how profitable
the company accounts show it to be, are capable of some improvement,
Figure 3.2 shows how the following techniques:
improvement techniques and approaches;
These are inter-related and together they can combine to identify business
shortfalls and meet operational improvement targets.
Measurement
Enhancements Benchmarking
AO/INT/0064 – V1.1 81
3.1.2 Performance Measures
Setting performance objectives and measuring them against a pre-
determined baseline is an equitable way of managing and measuring a
company’s performance.
86%
84%
82%
80%
78% Target
Actual
76%
74%
72%
Jan Feb March April May June July Aug
There are a multitude of areas within the company that may be considered
and assessed when undertaking an audit of the organisation’s
performance. The type of data collected and aspects of the organisation
measured will very much depend on the nature of the company and the
type of their operations.
82 AO/INT/0064 – V1.1
However, there are a number of key areas that are applicable to many
organisations, including:
Forecasting
Purchasing
Inventory Management
AO/INT/0064 – V1.1 83
What is the ratio of inventories to sales?
Production Operations
There are ranges of indicators that can be used to determine how well
operations and functions within the operation process are being managed.
84 AO/INT/0064 – V1.1
3.1.3 Customer Service Performance Measures
A key area in an audit should be at the customer level. Businesses are in
‘business’ to make a profit and that means satisfying the customers with
the following:
desired products;
expected products;
promised/agreed delivery schedule.
invoices overdue;
late deliveries;
warranty claims;
quality issues.
AO/INT/0064 – V1.1 85
Service According to the Availability of Order of Finished Product
For example, a food company may have given a producing firm 25 orders
for different products.
2 100
100
25
The formula for calculating the customer service level in this instance is
given by:
For example, if a customer orders 250 units, with the consignment having
different order numbers out of these goods only 240 can be supplied; the
stock-out level is therefore 10 (number of goods in an order – number of
goods delivered to the customer).
86 AO/INT/0064 – V1.1
The calculation becomes:
10 100
100
250
Delivery
1 100
100
20
One of the challenges for any business or company is that of reducing the
lead-time between the confirmation and delivery of an order; for example,
Dell strive to meet a 24 hour lead time to its customers.
This is a quantitative measure that, for example, maybe that 98% of all
orders can be delivered within a week.
AO/INT/0064 – V1.1 87
Information Systems
System Malfunction
This is the minimum order size a firm is willing to supply to the customer,
for example, are you prepared to provide service to the smaller clients,
who may only ask for one item on a irregular basis or small, more frequent
orders?
Emergency Orders
Delivery Frequency
88 AO/INT/0064 – V1.1
Delivery Reliability
Task 3.1
Consider the last purchase of a domestic product that you made. Were
you satisfied with the product and level of pre and post sales service
provided?
If no, discuss how the company could have improved its level of goods
and customer service to achieve a more appropriate degree of
satisfaction.
The degree to which an operation fulfils the five performance objectives of:
quality;
speed;
dependability;
flexibility, and
cost
at any point in time, to satisfy the customers.
AO/INT/0064 – V1.1 89
Figure 3.3 The Five Key Elements of Performance and Examples of Their End
Objectives
The market place and individual client needs and expectations for each
performance variable will vary. Therefore, the extent to which an
organisation meets its market’s needs will also vary – the organisation,
possibly with regard to its client’s needs will only meet some of them,
some of the time.
90 AO/INT/0064 – V1.1
The organisation, as the
result of assessing its overall
performance and identifying
the market’s requirements,
may improve the speed at
which orders are produced
and delivered and the relative
cost of the product. However,
as a result its level of flexibility no longer matches and meets the
requirements of the market place and its clients. This is not because it
has, in an absolute sense, deteriorated, but instead because the external
(markets and clients) environment has changed.
If the production cost can be reduced, then for the same sales price,
margins can be increased.
AO/INT/0064 – V1.1 91
Alternatively, lower production costs may allow a reduction in sales price,
which could increase the products (and thus the organisation’s) market
share.
obsolete;
spoilt;
damaged;
stolen;
lost.
During the inventory cycle (the period between one order and the next),
the average inventory is calculated as follows:
This measure can be applied and used whether the customers’ orders are
purchased from outside the manufacturing company or produced within
the company itself.
92 AO/INT/0064 – V1.1
If the orders are undertaken inside the manufacturing company, then the
cost of each unit will also have to give due consideration to the set-up and
other pre-operation preparation costs.
warehousing;
insurance;
theft;
waste;
obsolescence;
etc.
Inventory Turnover
Therefore, the greater the inventory turnover, the more efficient the
operation and the lower the inventory holding costs.
AO/INT/0064 – V1.1 93
Case Study
stock buy-back;
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management.
3rded., Prentice Hall.)
Record accuracy
For example, the records may show that there is more in stock than there
actually is on the shelves or in the warehouse. As a result, when the
production process requires this ‘inventory’, it is not available in the
quantity necessary. In such situations, the production process may have
to be delayed or halted and ultimately, the customer may experience a
delay in receiving their order(s). Such delays in production may also have
a ‘knock-on’ effect throughout the whole production process and to other
customers, whose goods may be ‘next’ in the production line.
94 AO/INT/0064 – V1.1
3.1.6 Waste Identification
Material lost during the production process is rather like throwing money
down the drain.
Identifying waste is the first step towards eliminating it. Seven types of
waste were identified by a Toyota engineer Taiicho Ohno as part of their
lean manufacturing process and became known by “Muda” which is
Japanese for waste.
AO/INT/0064 – V1.1 95
In simplistic terms, the amount of wastage in a production period can be
determined by the formula:
Task 3.2
design;
manufacture;
market.
the goods and products that are desired by the (its) customers.
96 AO/INT/0064 – V1.1
There are many types of benchmarking.
Task 3.3
AO/INT/0064 – V1.1 97
3.2 Manufacturing Planning and Control Systems
The purpose of planning and control is to ensure that the operating
process operates effectively and efficiently and processes the products
and services as required by the customers.
All operations require plans and require controlling, although the degree of
formality and detail may vary – according to the nature of the industry,
product produced and size of the company.
However, in all instances, the different aspects of planning and control can
be viewed as representing the reconciliation of supply with demand, as
shown in Figure 3.5 below.
(Source: Slack, N., Chambers, S. & Johnston, R., (2001). Operational Management. 3rd
ed. Prentice Hall.)
98 AO/INT/0064 – V1.1
3.2.1 Manufacturing Resource Planning (MRPII)
MRPII is an extension to MRP that links together all other functions such
as production planning, engineering, purchasing, marketing, finance and
human resources into an integrated system. This acts as a decision
support system for the entire business. The MRP extension to MRPII has
to firstly be developed as a closed loop system.
Closed loop MRP means that the various functions in production planning
and control (capacity planning, inventory management and shop floor
control) have all been integrated into a single system.
Priority Planning – urgent jobs can be brought forward and other work
can be held back in time and the raw material flows can be revised and
delivery schedules can be adjusted.
The inclusion of the financial systems into the closed loop MRP creates
MRPII and the advantages are that it is an operational and financial
system that can also be used to perform simulations of production.
AO/INT/0064 – V1.1 99
3.2.2 Master Production Schedule and MRPII
The master production schedule (MPS) drives the production process in
MRPII. Additional inputs are received from the other functions such as
purchasing and engineering. The MRPII system collects data to support
cost accounting, marketing and human resources.
Task 3.4
For example – one machine has five different jobs to process; any of the
five jobs could be processed first and, following that, any one if the
remaining four jobs – and so on.
Where:
Relating this to a real situation, where there may be 100 jobs going
through 30 machines in a route that takes an individual job through five
different machines, it becomes apparent that the scheduling task is
immediately very complicated and complex.
Within this vast number of schedules, there are many acceptable options
as to the appropriate routes and sequences for any set of jobs.
ERP systems facilitate the integration of databases and decisions from all
functions of the business to enable the impact of any changes to be
available to the entire business, in order to improve planning and control
decisions. The consequences of these decisions are followed through the
whole organisation.
In the case of lean or agile supply, the role of the supplier has also been
changed by the need for assured supply. More outsourcing, higher levels
of product complexity and operations such as the use of vendor managed
inventories have all increased the risk that a critical component may not be
available when it is time to make an original equipment manufacturer’s
delivery. If this happens to a major production line, it can lead to an
organisation missing its financial targets for the quarter and a resulting
impact on its annual performance and profitability.
The penalties for failure can be heavy for the supplier, but where the
relationship is strongly interdependent, such penalties cannot be utilised.
Increasingly, purchasing and supply chain management needs to balance
strategies and tactics that simultaneously reduce cost and risk.
Only need to monitor in-process inventory between cells and not for
each activity.
MRP combined with JIT requires the BoM to be divided into common parts
and optional parts. The common parts are of high volume and rate-based
master production scheduling is used to form Kanban requests.
The empty container returning to the supplier will be the signal to produce
more and send them as the system pulls parts through the production line.
The global business will typically source raw materials from more than one
country and it will often have assembly and manufacturing locations
geographically dispersed and will market its products worldwide.
These advances are not without risk and the Production Planner needs to
be aware and plan accordingly and management kept aware and plan
alternatives and backups.
Iceland Volcano – shut down airspace over Western Europe for weeks.
The challenge for global companies is how to achieve the cost advantage
of standardisation while still catering for the local demand for variety. The
aim is to standardise on parts, components and modules, and then
through flexible manufacture and local assembly, provide the specific
variants demanded by each market.
Some people say that this is unfair exploitation and also corrupt. The
pressure to lower production costs and the need to compete for global
market share far outweighs these concerns for some large corporate
organisations and, therefore, they have invested in production facilities
around the world.
The issue for production planning is the demand for global distribution
channels and the potential to collect and deliver to any global location.
Task 3.6
customer satisfaction;
growth;
maximised profit;
product leadership;
survival.
Internet;
Intranets;
Extranets;
RF (Radio Frequency);
Satellite Communications;
Robotics;
Mobile Communications.
purchasing;
inventory management;
stores management;
operations planning and control;
management of physical distribution.
Task 3.7
reduce lead time by reducing set up times, queue lengths and lot size;
JIT goes beyond the technical aspects of scheduling and ordering and
involves high levels of worker cooperation and motivation.
JIT is making what the customer needs, when it is needed and in the
quantity required by the customer with no waste and using the minimum
resources of people, material and machinery.
flexibility in production;
the smoothing of the master production schedule to give the correct mix
of products.
cost;
quality;
delivery;
safety; and
morale.
overproduction;
waiting;
transportation;
inappropriate processing;
excess inventory;
unnecessary motion;
Set up time can be reduced in different ways, for example, cutting out the
time to search for tools, prior preparation of tasks that delay change over
times, creating procedures to minimise delays and waste.
The activity and tasks are part of the changeover routine (internal set up
work) and converted so as to be performed before the changeover. This
is referred to as the transfer of internal set up work to external work.
3.4.6 Kaizen
Kaizen, or continuous improvement, is implied in all lean production
activities and means that every process and operation is continuously
evaluated and improved.
Factors such as time required, resources used and the quality of the
finished goods are measured and improved by small work groups in cross-
functional teams or quality circles. They are encouraged to think
creatively and take pride in making a small improvement every day.
Just in time;
FMEA, Failure modes effects analysis;
SPC, Statistical Process Control;
six sigma quality;
production control;
pull systems;
load levelling;
one-piece production flow;
continuous flow;
kanban systems;
materials flow;
TPM ,Total Production Maintenance;
workplace management;
visual controls;
brainstorming;
pareto analysis;
sampling;
presentation skills.
improved quality;
3.5 Summary
Having completed this element you should now have a clear
understanding of:
Waste minimisation;
Quality;
JIT;
MRP;
ERP;
APS;
CRM;
Kanban;
Kaizen;
Benchmarking
Lean production.
Task 3.9
For a specific production process of your choice, discuss how you would
evaluate, design and implement and appropriate information system that
will support, enhance and improve the production process.
d) the customers.
Competitive advantage;
Performance measuring systems;
Financial performance;
Resource productivity.
Is it going to continue?
financial performance;
competitive advantage;
quality of service;
flexibility;
innovation;
resource utilisation.
human resources;
facilities management.
labour turnover;
staff morale.
fault analysis;
The waste that can be further worked or processed to form raw material
for other production processes.
Some waste is considered dangerous and hazardous to health and the
environment such that this type of waste requires proper handling and
safe disposal.
Waste is defined in JIT (just in time) as any activity that does not add
value. Identifying waste is very important and different types of waste
include:
over production;
waiting time;
transport;
process;
inventory;
motion;
defective goods.
Quality is not necessarily the best or highest quality available but that
which conforms and meets the customer requirements.
Quality means delivering the right product to the right place at the right
time in the right quality at the right price. When these requirements are
met then there is quality.
Case Study
Process technologies with equipment that does the work have taller
organisation structures and include university-trained graduates. The
proportion of the workforce in actual production is low.
Logistics and operations Director positions are more common within the
organisational structure nowadays.
planning;
control;
coordination;
motivation;
decision making;
accountability;
Task 4.2
How can the use and application of such measures help the
organisation ensure that their product and planning system meets
customer expectation?
4.2 Summary
Having completed this element you should now have a clear
understanding of:
Journals/Magazines
Transport and Logistics Focus
Business Horizon
www.productionplanning.com
www.sap.com/uk/
www.preactor.com
www:businesscasestudies.co.uk/nissan/planning-for-quality-and-
productivity/production
www.slideshare.net/hazman/toyota-production-system-bussiness-case-
studies-plan