Professional Documents
Culture Documents
HAZOP Study Report - Galaxy- CCTG
HAZOP Study Report - Galaxy- CCTG
OF
HAZOP STUDY
FOR
NEBULA PROJECT
Product: CCTG
For
October 2020
By
Client: Author:
Galaxy Surfactants Ltd. Vijay Mandlik
Tarapur, Maharashtra - India Senior Consultant,
AcuTech Consulting Pvt. Ltd.
Ref.: PO No.: 4500110851 Dt. 11.03.2020
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
TABLE OF CONTENTS
APPENDICES
List of Figures
List of Tables
ii
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
EXECUTIVE SUMMARY
This report describes the results of HAZOP Study conducted for Galaxy Surfactants Ltd. (Galaxy)
for Nebula Project being set-up at Tarapur, Maharashtra, India. The HAZOP Study was conducted
by AcuTech Consulting Pvt. Ltd. (ACUTECH) during 10 th August – 3rd October 2020 through
remote meetings with Galaxy Tarapur and Taloja teams. AcuTech Hazop Facilitator had visited
the project site to understand the project layout.
The HAZOP Study systematically reviewed hazard scenarios potentially generated by deviations
from normal operation of the Nebula process. HAZOP is one of the methodologies identified as a
universally acceptable Process Hazard Analysis technique.
This report consists of the results of Hazop Study conducted for CCTG product.
The objective of the HAZOP Study was to identify potential impacts on safety, environment and
health due to deviations during processing of above products. Of most importance were those
hazards that could lead to injury of personnel or members of the community, environmental
damage, or equipment damage resulting in unit downtime. Recommendations were considered to
reduce either the severity or the likelihood of those potential hazards.
Recommendations were identified during the study to reduce the risks associated with the
operations. These recommendations should be resolved as soon as possible and implemented in a
timely manner. Responsibilities to implement the recommendations have been assigned and noted
in the HAZOP worksheet.
The report includes the HAZOP documentation generated from PHA-Pro® 8 software.
Mr. Ajinkya Sajanikar coordinated for this Hazop Study on behalf of Galaxy Surfactants Ltd.
Mr. Vijay Mandlik, Senior Consultant, AcuTech Consulting Group, facilitated the HAZOP
Sessions, with team participation by key personnel from Galaxy.
iii
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
1.0 INTRODUCTION
This report describes the results of HAZOP Study conducted for Galaxy Surfactants Ltd. (Galaxy)
for Nebula Project which is being set-up at Galaxy site, Tarapur, Maharashtra, India. The HAZOP
Study was conducted by AcuTech Consulting Pvt. Ltd. (ACUTECH) during 10 th Aug & 3rd
November 2020 through remote meetings with Galaxy Taloja and Tarapur teams.
The HAZOP Study systematically reviewed hazard scenarios potentially generated by deviations
from normal operation of the Nebula process.
This report consists of the results of Hazop Study conducted for CCTG product.
The objective of the HAZOP Study was to identify potential impacts on safety, environment and
health. Of most importance were those hazards that could lead to injury of personnel or members
of the community, environmental damage, or equipment damage resulting in unit downtime.
Recommendations were considered to reduce either the severity or the likelihood of those potential
hazards.
Section 2.0 describes the objectives and scope of the work. Section 3.0 describes the study
approach and identifies the HAZOP team members. Section 4.0 provides the results and Section
5.0 lists the references used in the study.
Node Descriptions, List of Recommendations, HAZOP Study worksheets and Noded P&IDs for
the CCTG product are provided in Appendices A, B, C and D.
AcuTech has expended its best professional efforts in performing this work. However, it should
be noted that this report describes a joint work effort between AcuTech and Galaxy personnel
using information on the process provided by participants. Consequently, AcuTech can accept no
liability for any use that Galaxy may make of the information contained herein.
1
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
The purpose of this study was to review the design and operation philosophy of the Nebula process
to detect latent faults or hazardous interactions and identify areas where improvements to safety
and operability are necessary.
1. Identify the response of the plant and equipment to process perturbations and deviations
from normal design conditions;
2. Assess whether the reaction of the system, or equipment will produce effects which are
harmful to the personnel, environment, physical assets and business continuity policy of
the company;
3. Investigate the operability of the process;
4. Identify availability and maintainability issues;
5. Evaluate the adequacy of existing engineering and procedural safeguards;
6. Recommend corrective actions, which will mitigate or eliminate adverse effects; and,
7. Protect the plant, people, environment and assets.
The scope of this HAZOP Study was the Nebula Process which will be operated at Tarapur site.
The HAZOP methodology reviews a process design and operation of the process for deviations
from design conditions. As such, the methodology assumes that the design has been competently
performed and that fabrication has been accomplished according to design. The HAZOP team does
not attempt to perform a detailed design review of engineering assumptions, fabrication, or
installation. However, where the design and/or operation do not appear to be consistent with good
practices, this deviation was discussed. Recommendations for additional reduction of risk are
made as determined by the team.
2
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
The first stage included a review and analysis of the plant related documentation and site visit by
AcuTech consultant. The team sessions included a systematic review of the process using the
HAZOP methodology. Finally, the HAZOP report was developed and processed through a quality
control review to ensure that the study conforms to accepted industry standards.
The Hazop Study process comprised of steps as shown in Figure 1 and is described in the following
section.
Hazard scenarios that resulted from deviation from normal operation were used for this study. The
flowchart in Figure 1 illustrates the typical procedure for a HAZOP.
The guideword HAZOP is based on the premise that hazards and operability problems stem from
deviations from design intent. Guidewords capture the ways in which process parameters can
deviate from design intent. The seven guide words typically used are: No, More, Less, As Well
As, Reverse, Part Of, and Other Than. These guidewords are systematically combined with process
parameters to yield deviations that are then judged for credibility. If credible causes exist, the
deviations are then examined further to determine the potential consequences, assuming the
deviations were to occur. If potential safety, health, property, or environment related consequences
are identified, existing safeguards, if any, are identified. Safeguards are equipment, systems, and/or
human interaction that are intended to detect, prevent, or mitigate the hazard scenario. The
deviations shown in Table 1, HAZOP Deviation Matrix, are reviewed as applicable to each specific
node.
Worksheet Entries
For deviations that the HAZOP team finds both to be credible and to result in potential safety,
health, property, or environment related consequences, the following is recorded in the HAZOP
3
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Guidewords
Guidewords are typically used to describe the ways in which process parameters can deviate from
the design intent. Those commonly used include No, More, Less, As Well As, Reverse, Part Of,
Other Than. These guidewords are systematically combined with relevant process parameters to
develop meaningful deviations. The deviations are then judged to determine whether credible
causes of the deviation exist. If credible causes exist, the deviations are examined further to
determine the consequences, safeguards, and any recommendations. The HAZOP Deviation
Matrix (Table 1) summarizes the guidewords normally used with each typical process parameter.
The team uses other guidewords when they are useful and provide a clearer understanding of the
deviation. Since the guidewords are part of the deviation they are not explicitly assigned a
worksheet column.
Parameters
A parameter is a physical or chemical property associated with the process, for example,
temperature, pressure, level, and flow. Table 1 provides a list of typical process parameters
generally considered. Since the parameters are part of the deviation they are not explicitly assigned
a worksheet column.
Deviation
4
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Causes
Causes are the specific events or failures that result in a deviation from design intent for a process
parameter. For example, "No Flow" may be caused by "pump failure". Detailed root causes (for
example, "pump not turned on due to operator error", or "coupling failure due to excessive
vibration") are sometimes listed if this is necessary to determine the consequences or safeguards.
General types of causes include equipment failure, human error, and external events. Equipment
failures are flaws in the equipment design or fabrication that result in predictable failures, where
the predictability is formed by the history of the equipment in its given service and environment.
Human errors include errors of both omission and commission. External events include both
naturally occurring events (e.g., weather induced events), and man-made events (e.g.,
transportation related events) that occur outside the process being studied but have an impact on
the process. In general, causes are only considered from within the node under study. All credible
causes are listed for the deviation under consideration. The team then reviews the consequences,
safeguards, and risk ranking for each cause as a separate hazard scenario.
Consequences
Scenario consequences are documented for each of the hazards or operability problems that would
result directly from the Cause, starting with the most immediate and followed by subsequent events
that result from the initial problems to the worst likely outcome. The consequences considered
credible in the study must fall within the defined objectives of the PHA. For example:
Consequences are followed beyond the node under consideration to the furthest reasonable extent
that problems may arise, both upstream and downstream, so that the hazards are fully realized. For
example, if high flow is being considered as a deviation for a hydrocarbon storage tank, the
consequences of "possible overfilling and fire" should be documented. This generally assumes that
all active safeguards (those that require energy to function, e.g. human intervention or a pump
shutdown interlock) fail. Passive safeguards (those that do not require energy to function, e.g.
secondary containment) are assumed to function as designed unless they are affected by the hazard
scenario under review.
Safeguards
All existing measures that detect or warn of a cause of a deviation or consequence, prevent a cause
or consequence, or mitigate the effects of a consequence are entered in this column. This includes
hardware, software, and certain procedural/administrative safeguards. For example, a high level
shutdown interlock, a flammable gas detection system with alarms, or a pressure relief valve are
5
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
all safeguards if they are available and reliable. Safeguards must be fully functional and applicable
to the scenario for which they are credited. Safeguards are included for all scenarios which involve
safety, health, property, or environment related consequences.
Hazard scenarios identified in the study are rated on both the severity of the consequence and the
likelihood of the scenario occurring, using the ranking systems shown in Tables 2 and 3,
respectively. The severity of the consequences is rated independently of the likelihood and, in
general, assuming failure of the safeguards. Consequences have been categorized in following
categories (CAT) in the HAZOP Worksheet:
P: Personnel
C: Community
E: Environmental Impact
F: Facility
The likelihood of the scenario is estimated qualitatively by the team, taking into consideration the
likelihood of the initiating event as well as the likelihood of success or failure of the identified
safeguards.
The risk ranking is an estimate of the risk level taking into consideration estimates of the severity
of the scenario and the likelihood of the scenario occurring. The risk ranking allows scenarios with
differing severity and likelihood to be compared using a common scale. For example, a
catastrophic scenario with a low likelihood of occurrence could have the same risk level as a less
severe scenario with a greater likelihood of occurring.
A Qualitative Risk Ranking Matrix is used to assign a risk level to a hazard scenario where the
severity and likelihood was rated. The Risk Ranking Matrix results in risk levels from (highest
risk) to (lowest risk). The risk levels help the team to determine the need for additional
recommendations and assists in prioritizing any recommendations made. Tables 2 and 3 provide
the Severity and Likelihood Ratings, respectively; the Qualitative Risk Ranking Matrix is provided
in Figure 2.
Recommendations
Recommendations include preliminary design or operating changes that reduce or eliminate causes
and/or consequences. Requests for additional information can also be recommended.
6
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Figure 1
HAZOP Process Flowchart
Begin
Begin Study
Study
Select Node
Define
DefineDesign
Design
Intention
Intention
Select
SelectParameter
Param eter
Select
SelectGuidew
Guideword,
ord,
Develop
Develop Deviation
Deviation
Identify
IdentifyAll
AllCauses
Causes
for
forDeviation
Deviation
Docum
Document
ent
Consequences
Consequencesfor
for
Each Cause
Each Cause
Document
DocumentSafeguards
Protection
for
forEach
Each Cause
Cause
Estimate
Estim ate Severity,
Severity,
Likelihood,
Likelihood,&& Risk
Riskfor
for
Each
Each Cause
Cause
Docum
Document
ent
Recomm
Recommendations/Responsibilities/
endations/Responsibilities/
Questions/Answers/Notes
Questions/Answers/Notes
No
No
Other Nodes?
Other Nodes?
No
7
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Table 1
HAZOP Deviation Matrix
8
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Table 2
Definitions of Severity
RANKING DESCRIPTION
1 PERSONNEL - Fatality or permanently disabling injury; COMMUNITY - One
or more severe injuries; ENVIRONMENT - Significant release with serious
offsite impact and more likely than not to cause immediate or long-term health
effects, >$100,000 remediation fines; FACILITY - Major or total destruction of
process area(s) at an estimated cost greater than $10,000,000 or a significant
loss of production.
2 PERSONNEL - One or more severe injuries; COMMUNITY - One or more
injuries; ENVIRONMENT - Significant release with serious offsite impact, no
long-term impact, $100,000-$10,000 remediation fines; FACILITY - Major
damage to process area(s) at an estimated cost greater than $1,000,000 or some
loss of production.
3 PERSONNEL - Single injury, not severe, possible lost time; COMMUNITY -
Odor or noise annoyance complaint from the public; ENVIRONMENT -
Release that results in agency notification or permit violation, $10,000-$5,000
remediation fines; FACILITY - Some equipment damage at an estimated cost
greater than $100,000 and with minimal loss of production.
4 PERSONNEL - Minor injury, minor lost time; COMMUNITY - No injury,
hazard, or annoyance to public; ENVIRONMENT - Recordable event with no
agency notification or permit violation, $5,000-$1,000 remediation fines;
FACILITY - Minimal equipment damage at an estimated cost less than
$100,000 and with no loss of production.
5 PERSONNEL - No injury, no lost time; COMMUNITY - No injury, hazard, or
annoyance to public; ENVIRONMENT - Internal recordable spill; FACILITY -
Minimal equipment damage at an estimated cost less than $10,000 and with no
loss of production.
Table 3
Definitions of Likelihood
RANKING DESCRIPTION
A Potential of occurring more than once per year
B Potential of occurring once every year
C Potential of occurring once every one - five years
D Potential of occurring once every five-ten years
E Potential of occurring once in facility lifetime
F Practically Impossible
9
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Figure 2
Risk Ranking Matrix
LIKELIHOOD
A B C D E F
S
E 1 1 2 4 7 11 16
V
E
R 3 5 8 12 17 21
2
I
T
Y 6 9 13 18 22 25
3
4 10 14 19 23 26 28
5 15 20 24 27 29 30
NOTE: For this matrix, a Risk Ranking of “1” represents the highest severity and highest likelihood
possible.
10
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
Vijay Mandlik, Sr. Consultant, AcuTech Consulting Group, facilitated the HAZOP Study sessions.
Proceedings of the sessions were recorded on PHA-PRO® 8 Software. Mr. Mandlik is experienced
and trained in facilitating HAZOP Study. Galaxy provided the study team for the review sessions.
The responsibility of the team was to provide the appropriate expertise regarding the operations
conducted in Nebula Project. The personnel participating in the study are listed below:
11
HAZOP Study Report – Nebula Project – CCTG
Galaxy Surfactants Ltd.
Tarapur
4.0 RECOMMENDATIONS
Recommendations identified during a HAZOP Study generally have one of three purposes. They
are:
Recommendations were identified during the Hazop Study to reduce the risks associated with the
processes or operations reviewed.
P&IDs must include all the components installed in the plant (major equipment,
instruments, special items like strainers, gas detectors etc., alarms & interlocks, design data
of major equipment, set points of PSVs and burst pressures of Rupture Disks, etc.
Vendor P&IDs to be embedded in Galaxy P&ID template and issued for conducting Hazop
Studies for future projects.
Alarm & Interlock lists must be prepared consisting of set points, actions to be taken on
activation and final element acted upon by the interlock. Interlock numbers must
correspond to the numbers mentioned in the P&IDs.
12
APPENDICES
Appendix A - Node Descriptions
Node Descriptions – CCTG
Recommendations (HAZOP)
Risk Risk
Ranking Ranking Responsibility
Place(s) Used Before
After Risk
Risk
Reduction
Reduction
1. Prepare SOP/BMR for unloading of CCA tanker, Consequences: 14 19 Devendra Mhatre
mention PPEs to be used for unloading. 1.1.2.1 14
2. Include periodic cleaning of bucket filter in ITPM Consequences: 14 23 Devendra Mhatre
procedure. 1.1.2.2 14
3. Include in tanker unloading SOP/BMR to monitor Consequences: 14 26 Devendra Mhatre
35P1.G discharge pressure during tanker 1.1.2.2, 1.6.1.1 14
unloading.
20 24
4. Include in SOP/BMR, supervisor check to ensure Consequences: 14 19 Devendra Mhatre
correct tanker has been connected for unloading. 1.3.1.1
5. Include fire in CCA tank farm in Emergency Consequences: 2 16 Yogesh Sankhe
Response Plan and impart training. 1.5.1.1
6. Include in SOP/BMR to check the vent is open Consequences: 9 13 Devendra Mhatre
before unloading is started. 1.4.2.1
7. Provide curbed area with containment for CCA Consequences: 9 18 Nikhil Parit
tanker unloading. 1.4.2.1
8. Develop 'Hose Management System' to maintain Consequences: 9 18 Shrivardhan Nuval & Avinash Shinde
hoses mechanical integrity. (RRF 100) 1.10.1.1
9. Develop SOP for sampling of CCA isotanker - Consequences: 14 19 Devendra Mhatre
include PPEs, tools to be used, method of 1.12.1.1
sampling.
10. Ensure that dyke drain valves are kept blinded, Consequences: 14 26 Nikhil Parit
perform tank farm inspection using a checklist. 2.1.1.1
(RRF 10)
11. Include in SOP/BMR to monitor 35P2.G discharge Consequences: 20 24 Devendra Mhatre
pressure during operation. 2.1.4.1
12. Provide flange guards on all flanges in CCA Consequences: 9 18 Nikhil Parit
unloading line. 1.10.2.1
13. Include piping in ITPM procedure to periodically Consequences: 9 18 Shrivardhan Nuval & Avinash Shinde
check the flanges and condition of gaskets, pipe 2.10.1.1
thickness testing, corrosion monitoring etc.
14. Provide High level switch LSH91.1.G to close KV Consequences: 9 13 Nikhil Parit
91.2.G on CCA line and stop CCA pump 2.7.1.1
15. Ensure Drum color coding, type of drum, drum Consequences: 5 8 Devendra Mhatre
labeling is in place to avoid charging of wrong 3.11.1.1
material.
43. Provide interlock to open KV91.5.G for filtration Consequences: Nikhil Parit
Recommendations (HAZOP)
Risk Risk
Ranking Ranking Responsibility
Place(s) Used Before
After Risk
Risk
Reduction
Reduction
only if 91R1.G temperature is below 50oC 7.7.1.1
44. Provide interlock to prevent opening of KV91.5.G Consequences: 5 17 Nikhil Parit
if 91R1.G temperature TT91.1.G is more than 5.17.1.1
50oC.
45. Perform leak test after maintenance work on Consequences: Devendra Mhatre
sparkler filter. 7.8.1.1
46. Provide line of compatible MOC for 91V3.G. Consequences: 14 19 Nikhil Parit
8.1.1.1
Appendix C - Hazop Worksheets
HAZOP Worksheet - CCTG
Node: 1. CCA Unloading
Drawing: P90-TF35-04-001, Rev. 2
Type: Atm. Storage Tank
Equipment ID: 35T1.G
Design Conditions/Parameters: 35T1.G, SS304, 35 KL
Unloading of CCA from isotanker (20 KL) using centrifugal pump 35P1.G (40m3/Hr.)
Recommendations (HAZOP)
Matrix Matrix
Deviation Causes Consequences CAT Safeguards Matrix
Resp
S L RR S L RR S L RR
No / Less Flow 1. No flow of CCA during 1. Process delay
tanker unloading - due to
malfunctioning of pump -
mechanical failure
2. No flow of CCA during 1. Dry running of pump P 4 B 14 1. None 1. Prepare Devend 4 C 19
tanker unloading - due to 35P1.G - possible damage SOP/BMR for ra
choking of bucket filter of mechanical seal - unloading of Mhatre
35F1.G moderate spill of CCA, CCA tanker,
personnel injury on skin mention PPEs
contact to be used for
unloading.
2. Dry running of pump E 4 B 14 1. Pump is provided 4 C 19 2. Include Devend 4 D 23
35P1.G - possible damage in dyke to prevent periodic ra
of mechanical seal - spread of CCA cleaning of Mhatre
moderate spill of CCA - - spill. bucket filter in
possible carryover of CCA ITPM
to storm water drain - procedure.
environmental hazard - soil 3. Include in Devend 4 E 26
contamination, aqua toxicity tanker ra
unloading Mhatre
SOP/BMR to
monitor
35P1.G
discharge
pressure
during tanker
unloading.
More Flow 1. No credible cause
Misdirected/ Reverse Flow 1. Unloading of wrong material 1. Other materials handled in F 4 B 14 1. None 4. Include in Devend 4 C 19
in CCA Tank - human error isotanker at site are SOP/BMR, ra
compatible with CCA- no supervisor Mhatre
vigorous reaction is check to
expected - impact on ensure correct
product quality due to tanker has
contamination of CCA been
Node: 1. CCA Unloading
Drawing: P90-TF35-04-001, Rev. 2
Type: Atm. Storage Tank
Equipment ID: 35T1.G
Design Conditions/Parameters: 35T1.G, SS304, 35 KL
Unloading of CCA from isotanker (20 KL) using centrifugal pump 35P1.G (40m3/Hr.)
Recommendations (HAZOP)
Matrix Matrix
Deviation Causes Consequences CAT Safeguards Matrix
Resp
S L RR S L RR S L RR
connected for
unloading.
Less Pressure 1. Same as 'Low Flow' in this
node.
2. Low pressure in isotanker if 1. Possible mechanical E 3 B 9 1. None 6. Include in Devend 3 C 13
vent is not provided during damage of isotanker due to SOP/BMR to ra
unloading - human error collapse under vacuum - check the vent Mhatre
possible spillage of CCA - is open before
possible carryover of CCA unloading is
to storm water drain - started.
environmental hazard - soil 7. Provide curbed Nikhil 3 D 18
contamination, aqua toxicity area with Parit
containment
for CCA tanker
unloading.
More Pressure 1. More pressure due to 1. Overpressurisation of tank if P 1 B 2 1. Tank is provided 1 E 11 5. Include fire in Yogesh 1 F 16
external fire around 35T1.G heated above 330oC (B.P.), with open vent (3 CCA tank farm Sankhe
possible tank rupture, in.) without in Emergency
personnel injury, fatality isolation valve. Response Plan
(RRF 1000). and impart
2. Fire-fighting 1 F 16 training.
system is provided
for external cooling
- foam dispenser is
provided for
extinguishing fire
involving CCA.
(RRF 10)
Less Level 1. Low level in isotanker - due 1. Dry running of 35P1.G - F 5 B 20 3. Include in Devend 5 C 24
to isotanker emptying - mechanical damage of seal tanker ra
human error - unloading - downtime unloading Mhatre
operation not monitored SOP/BMR to
monitor
35P1.G
discharge
pressure
during tanker
unloading.
Node: 1. CCA Unloading
Drawing: P90-TF35-04-001, Rev. 2
Type: Atm. Storage Tank
Equipment ID: 35T1.G
Design Conditions/Parameters: 35T1.G, SS304, 35 KL
Unloading of CCA from isotanker (20 KL) using centrifugal pump 35P1.G (40m3/Hr.)
Recommendations (HAZOP)
Matrix Matrix
Deviation Causes Consequences CAT Safeguards Matrix
Resp
S L RR S L RR S L RR
More Level 1. Excess unloading of 1. Overfilling of tank, spillage P 3 B 9 1. High level switch 3 C 13
isotanker in 35T1.G - human of CCA through high vent - LS 35.1.G with an
error personnel injury due to skin inter lock to stop
contact 35P1.G on high
level.
2. LT35.1.G is 3 D 18
provided with high
level interlock to
stop 35P1.G.
3. Occupancy around 3 E 22
tank is low.
Less Temperature 1. No credible cause
More Temperature 1. Discussed in 'High pressure'
scenario
Leakage 1. Hose / flange leak during 1. CCA spill, personnel injury P 3 B 9 1. None 8. Develop 'Hose Shrivar 3 D 18
tanker unloading on skin contact, medical Management dhan
treatment System' to Nuval &
maintain hoses Avinash
mechanical Shinde
integrity. (RRF
100)
2. Flange leak due to gasket 1. CCA spill, personnel injury P 3 B 9 1. None 12. Provide Nikhil 3 D 18
failure on skin contact, medical flange guards Parit
treatment on all flanges
in CCA
unloading
line.
Previous Accident 1. Taloja site - Incident related 1. Personnel exposure to P 5 B 20 1. Tanker auditing 5 C 24
to leakage of tanker isolation DMAPA, no injury had has been
master valve had taken occurred incorporated to
place, cause moderate spill ensure supply in
of DMAPA appropriate
tankers with no
leaks.
Sampling 1. Sampling will be done from 1. Possible exposure to CCA, P 4 B 14 1. None 9. Develop SOP Devend 4 C 19
isotanker before unloading personnel injury for sampling of ra
Node: 1. CCA Unloading
Drawing: P90-TF35-04-001, Rev. 2
Type: Atm. Storage Tank
Equipment ID: 35T1.G
Design Conditions/Parameters: 35T1.G, SS304, 35 KL
Unloading of CCA from isotanker (20 KL) using centrifugal pump 35P1.G (40m3/Hr.)
Recommendations (HAZOP)
Matrix Matrix
Deviation Causes Consequences CAT Safeguards Matrix
Resp
S L RR S L RR S L RR
CCA isotanker Mhatre
- include
PPEs, tools to
be used,
method of
sampling.
Misdirected/ Reverse Flow 1. Reverse flow of water from 1. Process delay, impact on
vacuum pump - due to quality
sudden stoppage of pump in
Node: 3. Glycerine Charging
Drawing: P90-CG91-04-001, Rev. 3
Type: Drum charging
Equipment ID: 91R1.G, 84WV.2G
Design Conditions/Parameters: 91R1.G, SS304, 7 KL
Glycerine (752 Kg.) drum unloading under vacuum using water ring vacuum pump
Recommendations (HAZOP)
Matrix Matrix
Deviation Causes Consequences CAT Safeguards Matrix
Resp
S L RR S L RR S L RR
case of power failure
Less Pressure 1. No credible cause -
equipment is designed for
full vacuum
More Pressure 1. No credible cause
Less Level 1. No consequence
More Level 1. No new scenario -
Discussed in 'Node 2'
Less Temperature 1. No credible cause
More Temperature 1. No credible cause
Wrong Composition 1. Charging of wrong material 1. Impact on process safety P 2 B 5 1. 15. Ensure Drum Devend 2 C 8
instead of drum color coding, ra
type of drum, Mhatre
drum labeling
is in place to
avoid
charging of
wrong
material.
Misdirected/ Reverse Flow 1. Charging of wrong material - 1. Impact on quality F 4 B 14 1. 42. Ensure bags Devend 4 C 19
human error labeling is in ra
place to avoid Mhatre
charging of
wrong
material.