CS15 - Method Statement for Boral Impactstop Drywall Installation
CS15 - Method Statement for Boral Impactstop Drywall Installation
CS15 - Method Statement for Boral Impactstop Drywall Installation
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 2 of 12
Revision Record
1. This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.
2. The contractor has the full right to modify, amend or change Method Statement and supporting
documents as required or as deemed necessary. All such documents will be submitted to the
“CONSULTANT” for approval.
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 3 of 12
Contents
1.0 Purpose
2.0 Scope
3.0 References
5.0 Responsibilities
6.0 Materials
9.0 Procedure
10.0 Attachments
1.0 PURPOSE
The purpose of this procedure is to define how the Boral Impactstop Drywall Installation shall be carried out under the controlled condition.
2.0 SCOPE
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 4 of 12
This method statement covers the detailed procedure to be followed for Supply & Installation of Boral Impactstop Drywall as per approved shop drawings
and schedule of finishes for the project. This procedure shall be read in conjunction with contract specification where applicable.
3.0 REFERENCES
Project specifications
Contract drawings
5.0 RESPONSIBILITIES
Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality and safety
procedures. The PM is responsible for the overall implementation of this method statement. The Project Manager shall ensure that the key personnel
are well aware of the specifications and method statement.
Project Engineer shall arrange all materials, equipment, safety related items & manpower & direct the Site Engineers & Foremen to resort appropriate
action for the smooth execution of the works.
Project Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Supervisor to identify potential hazards before
works and advise methods of safe working from new developments.
Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels. Ensuring setting out books are properly maintained
and filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.
Project Engineer shall be responsible for ensuring that execution of works are complying with approved method statement; specifications, approved
shop drawings and ensure ITR are submitted based on ITP requirements.
Project Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting out lines
& levels in concurrence from the Project Manager.
Coordinator / Engineer shall be responsible for proper execution of works involved before, during and after the works.
Project Engineer shall ensure that all materials shall be delivered to site comply with
approved samples and shall be assigned at temporary storage locations at Site according
to its fixing location. The fixing location of each individual stone panel shall be defined
by level no. related identification marking to ensure compliance to the approved shop
drawing and traceability.
Site Supervisor Ensure that all the materials are reached at the site as per the check list.
Site Supervisor responsible for the execution of the job under his control. SS shall be
report to the Project Engineer every end of the day to submit the report of work
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 5 of 12
progress at site. The Site Supervisor shall be carrying the drawing and Method of
Statement to execute job. Site Supervisor also responsible to finish the job within the
time frame given by the Project Engineer. The Site Supervisor responsible and report to
the Project Engineer for any inconvenience at site for execution of Job. Site Supervisor
responsible to inspect the materials is reached as per the check list.
6.0 MATERIALS
The capacity / size of the above equipment shall be judged in accordance with site
conditions, requirements, and availability at the time of execution.
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 6 of 12
Plasterboard should be delivered to site immediately prior to installation to reduce the incident of damage
All material should be kept dry, stored in neat, flat stacks to avoid damage to ends and edge or warping
Plasterboard should be cut by scoring the liner board on the face side or cut with a panel saw. Snap away from the cut face and cut back liner
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS
LOT 3140, BANDAR TAIPING
DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN
Document No: GLSS-JP-MS-CS15
Method Statement for Rev : 00
Boral Impactstop Drywall Installation Date: 27/07/2019
Page 7 of 12
9.2
Installation
Check partition framing to ensure that it is plumb, level and square and in true
alignment before installation of plasterboard sheet
Boral Impactstop sheets are always installed vertically
Boral Impactstop sheets are cut 16mm short, allowing for 10mm deflection to floor
and ceiling
Position temporary plasterboard off cuts between the floor and bottom of sheet prior
to fixing
All gaps are to be sealed using Fire Rated Sealant or Cornice Adhesive
First Side -- Screw fasten Boral Impactstop vertically to studs at edges only,
centering abutting edges on stud flanges. Sheets should be installed by advancing in
the direction opposite to the stud flange direction
Second Side – Cut first sheet of Boral Impactstop wide to stagger joints to first side.
Screw fasten this sheet and all subsequent full width sheets to all studs. Return to
first side and screw fasten Boral Impactstop sheets to previously unattached studs
10.0 ATTACHMENTS
ITP
Checklist
Risk Assessment