Building_Information_Modelling_Technolog

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Building Information Modelling Technological

Innovations in Industrialised Building Systems Cost


Estimation

Mohamed Murteza Gulamhussein Moledina, Goh Wei Pin, Wallace Imoudu Enegbuma
Department of Civil Engineering, Faculty of Engineering, Computing and Science
Swinburne University of Technology
Kuching, Malaysia
4314077@students.swinburne.edu.my, wenegbuma@swinburne.edu.my, wgoh@swinburne.edu.my

Kherun Nita Ali and Kayode Adenuga


Faculty of Built Environment, Faculty of Computing
Universiti Teknologi Malaysia
Skudai, Malaysia
b-kherun@utm.my, kayodeadenuga@yahoo.ca

Abstract—The paradigm shift in construction cost estimation


is attributed to technological innovations in the spheres of
cost of the project [1]. In Malaysia, many development
building information modelling (BIM) and industrialised projects are under way and many more completed. However,
building systems (IBS). Majority of construction projects during the work progress there are constant modifications and
experience cost overruns which affect project objectives. The delays experienced which are the major drawbacks that
outcome of cost overruns invariably leads to disputes and further increases total cost; causing this to be one of the expensive and
delays. Similarly, cost estimators resistance to overcoming the serious problem in the construction industry in Malaysia.
inertia to leap from traditional estimation methods to advanced Adoption of innovative technology by construction
methods further exacerbates the issues of cost estimation. This professionals is much slower than other sectors [2-4]. Cost
paper aims at comparing cost estimate between traditional cost estimation is a vital activity in any construction project which
estimation and advanced cost estimation. Data was collected via has to be checked at various phases of the construction and it
questionnaire from registered quantity surveying companies with is also a precise process that is made to give the project cost
the Board of Quantity Surveying Malaysia (BQSM). [5]. [6] research found that IBS has been used in Malaysia
Subsequently, real time simulation was carried out on a sample since 1964 and has recently gained more attention due to the
IBS project using Autodesk Revit and Navisworks to compare advancement of the technology. There are 5 diverse types of
cost estimates. The results revealed that BIM is accurate than bill IBS such as pre-cast concrete, steel framing, steel formwork,
of quantity (BOQ) as this difference results in a critical factor for
prefabricated timber framing and block work system. Pre-cast
large construction projects. The study was limited in terms of
cost standard and database in Autodesk Navisworks. Future
concrete and steel structures are mainly used in Malaysia with
research can improve on the quantity coding for BIM in cost playing a key role in IBS use [7].
Malaysia. IBS is a modern construction method that is an alternative
to the conventional construction method in Malaysian
Keywords—building information modelling (BIM); construction industry. This alternative is used in order to bring
industrialised building systems (IBS); cost estimation; Malaysia.
innovation to the construction industry and also to solve
different issues like foreign labour dependency, reduce site
I. INTRODUCTION pollutions, increase site safety and most importantly to reduce
The construction industry plays a major role in both the the overall project cost. However, since IBS was introduced in
developed and developing countries as it is one of the driving 1964, the projects have been facing problem of project cost
forces in the economy. The development of this industry stems overrun. This problem of project cost overrun happens to be a
from both private and public sectors. However, the major issue that is slowing the expansion of the Malaysian
construction industry is always criticized due to the following construction industry [8].
reasons such as over budget of the project cost and slow Cost overrun concerns happened after the ultimate cost or
delivery time of the project. The dominant concern of the spending of the project surpasses the planned, projected or
clients and contractors in construction industry is the overall target price. Hence, it is vital to identify the major factors that
influence the cost over budget, and find out effective technique
to improve the cost estimation for IBS projects in the or procedure is vital apart from good management [13][8].
construction industry to minimise the problem. The Thus, it is of little astonishment that economic cost, being a
complications of cost overruns are actually critical and it standout amongst the most essential decision-making norms
might have a high impact on the contractor and client with for any building construction undertaking, will ordinarily be
extra funds for the project (Goh et al. 2015). In addition, to the considered and investigated at the early phases of the
difficulties that transpired during building, poor project and undertaking [14]. Cost estimation in construction projects is a
cost management can origin disaster to meet the quality and genuine procedure intended to give a reliable forecast of the
suitability of the resources, to develop the envisioned financial costing [15]. The veracity of cost evaluations is
structure, or to function for its projected life. Hence, this paper mostly a function of series of aspects comprising design stage,
aims at comparing cost estimate between traditional cost data availability, quality of the management group’s
estimation and advanced cost estimation. Subsequent sections judgement and construction technique [8][15].
will have a literature review on BIM, IBS and cost estimation,
the methodological approach and results and discussions.
B. Cost Modelling
[16] defined cost models as: “techniques used for
II. LITERATURE REVIEW forecasting the estimated cost of a proposed construction
project”. Moreover, it is used as a term, when denoting to both
A. Cost and Industrialised Building Systems (IBS)
estimating resources cost for contractors and projecting
The Industrialised Building Systems (IBS) is a construction cost for clients. Meanwhile, [8] defined cost
manufacturing process that employs the methods, products, model as: “a procedure developed to reflect, by means of
parts or constructing system which includes prefabricated derived processes, adequately acceptable output for an
parts and on-site establishment. IBS is a substitute way of established series of input data”. In a perfect world, the model
construction that will certainly change the sequence of events ought to be sufficiently straightforward to be useful and
of the current construction industry moving to a systematically comprehended by the client, satisfactorily illustrative of the
way of mass manufacturing of construction materials [9]. IBS total range of effects that it might have, and sufficiently
in Malaysia was first introduced in the early 1960s after the complex to represent the framework precisely.
Local Government and Ministry of Housing of Malaysia
travelled across many European countries and assessed their C. Cost Modelling Types
housing development programs [10]. IBS offers enhanced cash
flow to inventors as the expenses can be claimed from the In the quest for suitable outline for general typology of
clients within two weeks upon assembling of building cost modelling, previous research examined fifty-five papers
components. On the other hand, the conventional method has a relating to cost modeling [17]. It was expected to offer
timeframe ten months to claim the expenses upon casting [11]. structure and give a perspective on which specific research
there is mismatch between IBS focus by the current industry input can be distinguished and strategically placed. Each of the
and government availability to embrace and change to IBS; in cost model looked into was characterized under the
this way, the business should be guided and enhanced their accompanying nine headings: 1. Relevance – whether it relates
preparation on IBS [12]. to a particular design proposal, 2. Units – the units of
measurement, 3. Cost/price – how the model is proposed to be
Cost estimating is an essential activity that is checked at used, 4. Approach – the level at which modelling is practical,
various stages of the structure construction process, that is 5. Time-point – at which point during the design process it is
beginning from the initiation and feasibility study stage of the applied, 6. Model – a general classification of the method, 7.
project to the preliminary and detailed design stages, and Technique – precise classification, 8. Assumption – whether
finally at the project completion stage. several researchers they can be evaluated and 9. Uncertainty – how it is treated.
have accredited that to ensure the construction project is Other types are shown in Table 1.
successful and effective; selecting the right type of cost
estimation method

TABLE I. THE COST ESTIMATION MODELS THREE MAIN GENERATIONS [13][18]


Traditional Model Non-traditional Model New wave Model
a) Conference a) Statistical/Econometric a) Artificial Intelligence
b) Financial Method b) Model (Regression analysis and Casual Model) b) System (Neural Network and Fuzzy Logic)
c) Functional Unit c) Risk/Simulation Model (Monte Carlo simulation c) Web-Based Tools
d) Superficial and Value management) d) BIM
e) Superficial Perimeter d) Knowledge Based Model e) Other Models (Environmentally and
f) Cube Method e) Resource Based Model Sustainable development)
g) Storey Enclosure Method f) Life Cycle Model
h) Approximate Quantity Method
i) Bill of Quantities Method

D. Bill of Quantity degree of work and this permits the work to be estimated.
Bills of Quantities contain a list of things of work which Moreover, the work incorporated into the thing is
are quickly depicted. The Bills likewise give an amount of characterized in subtle element by the principles of the Method
the of Measurement. The item portrayals are in this way shorthand
to
permit the applicable principles of the Method to be III. METHODOLOGY
distinguished. In addition, the measure might be an individual
item or number, measurement (direct meter or square meter or The research began with an examination of literature in
cubic meter), time (hours or weeks) or weight [19]. The Bills cost estimation, BIM and IBS [26][3][4]. The second stage of
of Quantities can aid several functions such as [19]: (1) A the research is a structured questionnaire survey carried out
breakdown of the tendered cost, with no legally binding status, with the quantity estimators in Malaysia. All members in the
however giving data for the choice from tenderers, (2) A construction industry may have unique views, practices and
forecast quantity of the work at the tendered cost, to be appreciation on the matter of project cost modelling of IBS.
utilized to land at an overhauled contract cost once the real The questionnaire survey examined the demographics of the
amounts of work completed are measured. This is the re- respondents, the present cost modelling that have been
measure type of agreement, (3) A timetable of rates as the generally used, inaccuracy level of cost estimates in both
agreement premise for esteeming varieties in the work and (4) conventional and IBS projects, and subjective variables that
A premise for measure of the estimation of work finished for are speculated to be influencing the IBS project cost. A mail
interim expenditures. survey was used since it is generally cost effective to
administer and the same survey can be sent to a larger number
of people. The survey permits the respondent to fill the
E. Building Information Modelling questionnaire at their own time. The sampling technique used
BIM is an insipid term used to refer to propelled 3D is convenience sampling such that the questionnaire survey
Computer Aided Design (CAD) innovation for modelling and targets the quantity surveyors. The questionnaire survey was
overseeing structures and data associated with them; however, emailed to all the registered quantity surveying companies
which are separated from conventional CAD frameworks in with the Board of Quantity Surveying Malaysia (BQSM); the
that the product objects in a BIM model are logical to specialised organisation that manages the quantity surveyors in
computer programs as demonstrations of true building parts, Malaysia. In addition, of the 354 registered companies, only
dissimilar to the realistic items in a two-dimensional CAD 333 had valid email addresses. As for the remaining
document. A 5D BIM application is brilliantly intended to companies email addresses, 10 of them were repeatedly
relate 3D model segments with time and cost-related data [20]. registered while 11 emails were not in use or the server was
The requirement emphasis for predictable definitions and down or the email address was wrong. The minimum
phraseology to report the significant puzzlement and responses expected are in the range of 15% to 20% of the 333
misconception about BIM in an industry is still developing companies because from the past researches done in Malaysia
with this innovation [21]. One of BIMs acknowledgements is and other South-Asian countries which had a total of 61
to permit the clients to concentrate on the data and choice respondents return rate. The real-life project used was to build
making of the venture, rather than the squandering time on two structures that contain eight classrooms, one science
documentation devices and the real tiring procedure [22-24]. (laboratory) room and six toilets for a school which was
Educational frameworks for BIM training in institutions of proposed by Ministry of Education Malaysia. The following
higher learning still need upgrading to meet industry demand are some of the project details: 6000mm precast concrete piles;
[25]. There are two sorts of amounts to reflect when taking-off elevated above ground by 900mm using the stumps; it has
[23]: (1) The Product/Procurement Quantities (PPQ), which precast concrete slab panel with bondek for both structures
are the quantifiable physical magnitudes resulted, by the except for the toilet side which is reinforced concrete slab; it
design of the venture such as are length, volume and so on and had steel framing with cement boards, steel roof truss system
(2) The Process of Construction Quantities (PCQ), this kind is and steel roof. This project is selected as it is an IBS hybrid
a further detailed breakdown associated to PPQ. The amounts Project for a village school in Kuching, Sarawak, Malaysia.
are influenced by the construction technique, particular Autodesk Revit 2015 mostly utilised by the architects and
situations of the job such as labour hours, areas of formwork, engineers to aid in designing and structuring a project.
scaffolding and so on. Autodesk Navisworks Manage 2015 used for automatically
generating the quantity take-off for the project in the shortest
time and with a high level of accuracy while Microsoft Excel
was used to lay out data, rearrange and reformat data and to do
analysis. Summary of the research method outline is shown in
Fig 2.
Literature Detailed
Review Building Design

Manual
Take-off
Schedule
Analysis
of Rates and
Discussion
Automated
Take-off
Fig. 1. RIBA plan of work and its relationship to cost data

Fig. 2. Research Method Outline


IV. RESULTS AND DISCUSSION have 1-10 years, 33% have above 30 years and 31% have 11-
30 years’ experience. It can be determined that the respondents
A. Respondent work experience working experience in the field is almost balanced such that
As shown in Fig 3 the distribution of working experience in 53% have below 20 years and 47% have above 20 years’
the construction industry of the respondents, whereby 36% experience.

Fig. 3. Respondents' working experience in the Construction Industry

B. Cost Estimation Inaccuracy in Construction Industry presents that there is higher inaccuracy level but lesser then
The Fig 4 shows that there is higher inaccuracy level such conventional project such that 66% say that the inaccuracy
that 49% say that the inaccuracy is less than 5% and other level is less than 5% while 30% say is between 5% to less than
49% say the inaccuracy level is between 5% to less than 10% 10%. Therefore, indicating that use of IBS method of
for a conventional construction project. On the other hand, construction can decrease the project cost overrun.
Figure 22

Fig. 4. Cost estimation inaccuracy comparison

both the past research ranked overall insufficient tendering


C. Inaccuracy of cost forecasting time and insufficient analysis of tender documents as 4th and
The results shown in the Table 2 are different to the past 10th respectively. However, in the current Malaysian
research by [15] and [27] but there is a difference that both construction industry, the results show that insufficient
found that poor tender document is overall ranked 1 but in tendering time and insufficient analysis of tender documents is
case of current Malaysian situation the tender document had a ranked overall 12th and 5th respectively. Hence, showing the
relative importance index of 0.856, severity index of 85.57% difference between different countries construction industry
and COV value of 18.15% and ranked 9th overall. Besides, views.

TABLE II. INACCURATE OF COST FORECASTING RELATED COST FACTORS


Inaccurate of cost forecasting RII SI (%) COV (%) Group Rank Overall Rank
Poor requirement standing 0.754 75.41 26.71 4 21
Poor tender document 0.856 85.57 18.15 2 9
Insufficient tendering time 0.826 82.62 17.94 3 12
Insufficient analysis of tender documents 0.889 88.85 16.19 1 5

D. Quantity Take-off Simulation can be input into the model to generate 5D BIM. The data
BIM permits incorporation of the data delivered by diverse entered into the model by diverse professionals will store and
contributors in the project such as Architect, Landscape turn out to be a valuable tool for construction management.
Architect, Building Services Engineer, Structural Engineer Figures 5 and 6 shows the building design development in
and also Interior Designer, to be in a sole model. Furthermore, Autodesk Revit, simulation in Navisworks and quantity
the project data of structure programme schedules and extraction in excel spreadsheet.
expenses
Fig. 5. Floor plan drawn in Autodesk Revit and 3D Model View in Navisworks

Fig. 6. Display of All Data in Excel and display of Groups Pivot Table –Items in Groups and total quantity

The simulation revealed that BIM method is accurate,


laborious task which also has high room for human error. The
reliable, faster and easier to generate the quantity take-off and
time is mostly utilised in taking-off items and tabulating into
bill of quantities; whereas the conventional BOQ method is a
the Excel Sheet, followed by billing the quantities. However,
tedious, laborious and time consuming method for quantity
the knowledge of manual quantification is important as it is
take-off and bill of quantities preparation. In addition, the
done according to the standard used in the place and thus,
difference between the two bill of quantities of 2.067% proved
giving a client to better understand the bill of quantities as all
that BIM is accurate than BOQ. This was derived from
estimators use the same standard. On the other hand, the
dividing the difference between BIM automate cost and
automatic taking-off and producing the bill of quantities was
Manual cost given by 1,424,345.47-1,394903.92/1,424345.47.
found to be simpler than the conventional method as many of
However, it was found that using either BOQ or BIM method
the steps such as taking-off the items, squaring, tabulating and
for quantity take-off for IBS components is easier and faster
others are eliminated; since the quantity take-off is generated
than for the conventional component of the structure.
with just a few clicks. Nevertheless, the disadvantage is that
currently the BIM cannot produce the take-off or bill of
V. CONCLUSION AND RECOMMENDATION quantities with the required standards and therefore, the
The selected project was simulated and the literature knowledge of the manual method and standards is required by
knowledge of cost estimation methods was used to achieve the the estimator to produce the final bill of quantities for
study objective. The BOQ method is a time consuming and submission. In addition, the difference between the two bill of
quantities of 2.067% proved that BIM is accurate than BOQ as
this difference and be a critical factor in larger construction [10] Thanoon, WAM, Peng, LW, Kadir, MRA, Jaafar, MS & Salit, MS 2003,
projects. The experience of drawing the 3D model indicates ‘The Experiences of Malaysia and Other Countries in Industrialised
that the team working on the project needs to be familiar with Building System in Malaysia’, Proceeding of International Conference
Industrialised building systems, Kuala Lumpur, Malaysia.
the software used for the modelling, structural drawings, cost
estimation and others. The relevant parties need to be able to [11] Nawi, M, Nifa, F, Abdullah, S & Yasin, F 2007, ‘A Preliminary Survey
of the Application of Industrialised Building System (IBS) In Kedah and
collaborate and produce great results together and also be able Perlis Malaysian Construction Industry’, Conference on Sustainable
to use the BIM tools well. They require training, equipment to Building South East Asia, 5-7 November 2007, Malaysia, Institute
support the use of the BIM applications and license for the Sultan Iskandar of Urban Habitat & Highrise, Johor, pp. 411-415.
software which can be expensive for small firms. The bright [12] Hamid, ZA, Kamar, KAM, Zain, MZM, Ghani, MK & Rahim, AHA
side of the BIM method is that it can make the process faster 2008, ‘Industrialised Building System (IBS) in Malaysia: The Current
State and R&D Initiatives’, Malaysian Construction Research Journal
and produce accurate project cost. Moreover, it even saves (MCRJ), vol. 2, no. 1, pp. 1‐11.
time for the estimator to focus on more important issues that
[13] Bari, NAA, Yusuff, RM, Ismail, N, Aini, J & Rizan, A 2012, ‘Factors
can achieve the goal of the client of money for value. Finally, influencing the construction cost of Industrialised Building System
it was also found when using both the methods that it is easier (IBS) projects’, Procedia - Social and Behavioral Sciences, vol. 35, pp.
to carry out the quantity take-off and produce bill of quantities 689-696.
for the IBS components which can aid in the Malaysian [14] Gunaydin HM & Dogan, SZ 2004, ‘A Neural Network Approach for
construction industry. The limitations of this study bordered Early Cost Estimation of Structural System of Building’, International
Journal of Project Management, vol. 22, pp. 595-602.
around redrawing the building due to compatibility of higher
[15] Akintoye, A 2000, ‘Analysis of factors influencing project cost
versions of Autodesk Revit and need to export the file into estimating practice’, Construction Management and Economics, vol. 18,
IFC file format and open in Revit 2015 but not all the data was no.1, pp. 77-89.
received which is the issue with the export option to IFC file. [16] Ashworth, A 1999, ‘In Building in Value’, in R Best and G De Valence,
Autodesk Navisworks Manage 2015 also has limited resources Cost Modelling, Arnold, London.
available which limited the use of the software and only the [17] Newton, S 1991, ‘An Agenda for Cost Modelling Research’,
quantification was carried out and data exported to excel. Construction Management and Economics, vol. 9, pp. 97-112.
Future studies can improve on the quantity coding for BIM in [18] Ashworth, A 1995, Cost Studies of Building, 2nd edn, Longman
Malaysia and ways to further enhance construction industry Scientific and Technical, Harlow.
stakeholders to use BIM and IBS. [19] Atkinson, D 2000, ‘Bill of Quantity’, Bills of Quantity Atkinson,
December, viewed 13 April 2016,
<http://fidic.org/sites/default/files/Bills%20of%20Quantity%20Atkinson
REFERENCES .pdf>.
[1] Baloi, P, & Price, A 2003, Modelling Global Risk Factors Affecting [20] Sacks, R, Eastman, CM, Lee, G & Orndorff, D 2005, ‘A Target
Construction Cost Performance, International Journal of Project Benchmark of the Impact of Three-Dimensional Parametric Modelling
Management, Vol. 21, No.4, pp. 262-269. in Precast Construction’, PCI Journal, viewed 5 May 2016,
<http://www.pci.org/uploadedFiles/Siteroot/Publications/PCI_Journal/2
[2] Enegbuma, W.I, Aliagha, U.G & Ali, K.N 2015, ‘Effects of Perceptions 005/DOI_Articles/JL-05-JULY-AUGUST-6.pdf>.
on BIM Adoption in Malaysian Construction Industry’, Jurnal
Teknologi, vol. 77, pp. 15. [21] Goucher, D & Thurairajah, N 2013, ‘Advantages & Challenges of Using
BIM – A Cost Consultant’s Perspective’, 49th ASC Annual International
[3] Enegbuma, W.I. (2016). Factors Affecting Building Information Conference Proceedings, Associated Schools of Construction, United
Modelling Adoption by Malaysian Consultants and Contractors. PhD Kingdom.
Thesis, Universiti Teknologi Malaysia.
[22] Popov, V, Juocevicius, V, Migilinskas, D, Ustinovichius, L &
[4] Ojoko, E. O., Tanko, B. L., Jibrin, M., Ojoko, O. and Enegbuma, W. I. Mikalauskas, S 2009, ‘The use of a virtual building design and
(2016a). Project Delay Causes and Effects in the Construction Industry. construction model for developing an effective project concept in 5D
6th International Graduate Conference on Engineering, Science and environment’, Automation in Construction, vol. 19, no. 3, pp. 357-367.
Humanities (IGCESH). 15th - 17th August, Johor, Malaysia.
[23] Al-Mashta, S & Alkass, S 2010, ‘Integrated Cost Budgeting &
[5] Akintoye, A & Fitzgerald, E 2000, ‘A survey of current cost estimating
Estimating Model for Building Projects’, AACE International Annual
practices in the UK’, Construction Management and Economics, vol. 18,
Meeting: “TCM: Cost Engineering on my Mind”, viewed 30 April 2016,
no. 1, pp. 161-172.
<
[6] Ismail, N 2014, ‘Implementation of Industrialised Building System http://www.aaceimontreal.org/pdf/BIM.02%20%20Integrated%20Cost%
(IBS) in Malaysia Construction Industry’, Honours thesis, Universiti 20Estimating%20Model%20for%20Bldg%20projects.pdf>.
Malaysia Pahang, Pahang.
[24] Eastman, C, Teicholz, P, Sacks, R & Liston, K 2011, ‘BIM handbook: A
[7] Ojoko, E. O., Osman, M. H., Rahman, A. B., Omar, W. S. and guide to building information modeling for owners, managers, designers,
Enegbuma, W. I. (2016b). Stakeholders Perception of Project Success engineers and contractors’, 2nd edn, John Wiley & Sons, New Jersey.
Criteria for Industrialised Building System in Nigerian Mass Housing [25] Ali, K.N, Mustaffa, N.E, Keat, Q.J & Enegbuma, W.I 2016, ‘Building
Development. 2nd International Conference on Science, Engineering, Information Modelling (BIM) Educational Framework for Quantity
and the Social Sciences (ICSESS), May 29th – June 1st, Skudai, Surveying Students: The Malaysian Perspective’, Journal of Information
Malaysia. Technology in Construction (ITcon), vol. 21, no. 1, pp. 140-151.
[8] Goh, K.C, Yap, A.B.K, Seow, T.W, Masrom, M.A.N, Goh, H.H & Tey, [26] Hair, J. F., Black, W.C., Babin, B. J. and Anderson, R. E. 2010.
J.S 2015, ‘Strategies in Dealing with Cost Overrun Issues: Perspective Multivariate Data Analysis (7th ed.). New Jersey: Pearson Prentice Hall.
of Construction Stakeholders’, Springer, Singapore.
[27] Cong, J, Mbachu, J & Domingo, N 2014, ‘Factors influencing the
[9] Bari, NAA, Kadir MRA, Ismail, N & Yusuff, RM 2009,‘The incidence- accuracy of pre-contract stage estimation of final contract price in New
in-use of cost estimation model for Industrialised Building Systems Zealand’, International Journal of Construction Supply Chain
(IBS) projects’, Department of Civil Engineering, Universiti Putra Management, vol. 4, no. 2, pp. 51-64.
Malaysia, Selangor, Malaysia.

You might also like