Professional Documents
Culture Documents
Nebula APG
Nebula APG
Nebula APG
BASIC ENGINEERING
Document Number
P90-AP98-01-001
Galsoft APG, a natural non - ionic surfactant synthesis can be completed with natural and
renewable sources and the compounds are biodegradable , is used in kitchen detergent, body
washing products, cosmetics, plastic and petroleum industry , textile, printing and dyeing, paper
making and other industrial / commercial uses.
• Cosmetics and Toiletries: Hair shampoo, Hair Cleansing, Body Wash, Body Scrub, Shower
Gel, Hand Cleansing, Foundation, Anti-ageing, Beauty Care, Baby Care, etc.
• Face Wash: Face washing foam, Face washing cream, Face washing liquid, Make-up
remover, etc.
• Soap and Other: Facial soap, Liquid Soap, Facial Cleanser, Skin Cleansing, Toothpaste, Bath
soap, Emulsifiers and Dispersing agents, etc.
Aim:
To create the facility to manufacture 600 TPA of Galsoft APG as a product under Project Nebula
at G-59 site in Tarapur.
Background:
• The Pilot batch is conducted at W-67 with a batch size of 90 kg and a batch cycle of 64
hours.
Process
SOP of Process
1. Clean and wash the reactor by steam and dry the reactor.
2. Ensure the reactor is clean by visual testing
3. Apply Steam Jet Ejector vacuum and ensure vacuum in the reactor should be around 10
mm Hg
4. Charge the lauryl alcohol (107 kg) using vacuum
5. Start pump circulation and heat the mass to 40-50°C at 5-7 mm Hg to remove moisture.
6. Break the lumps of dextrose and charge dextrose slowly as free flowing powder (33 kg)
from manhole. Ensure circulation is ON.
7. Stir the reaction mass for ½ h at 50-60°C and at 5-7 mm Hg vacuum to remove the moisture
from the reaction mass
8. Check moisture content of reaction mass. It should be less than 0.1%.
9. After ensuring moisture content is within specifications, charge APG catalyst (151 g) at 60°C
under vacuum from top nozzle and increase the temperature up to 110°C - 112°C under 2-3
mm Hg vacuum.
10. Maintain temperature of reaction mass at 110°C-112oC for 6-6.5 h under 2-3 MM Hg
vacuum.
11. Conduct bottom top mixing 2 times after each 15 min and later after 1h, 2h & 3h to avoid
settling of catalyst & dextrose.
12. After 5-5.5 h, check the conversion of Dextrose by DNSA method as explained below
13. After passing smear test (after 6-6.5h), check % glucose in the reaction mass by DNS
method.
14. After concluding that glucose content is within the lower limit, cool the reaction mass to
around 70°C & add 40 g of caustic lye (48%)
15. Continue the mixing for total ½ h and check pH in 10% IPA: Water 60:40 solution. It should
be around 7-7.5.
16. Increase temperature of reaction mass to 120°C. Parallely, make jacketed cartridge filter
(10 μm) ready by heating it to 120-125°C using steam.
17. Cut off the circulation line and open by pass line to start filtration using nitrogen pressure
to the reactor.
18. Drain the circulation line material and add it to the reactor
19. Initially use lower nitrogen pressure of around 0.5 kg/cm2 for pressure filtration. When rate
of filtration slows down, increase the N2 pressure in the reactor in steps of 0.5 kg/cm2 up to
3kg/cm2.
20. As rate of filtration slows down even at 3kg/cm2, open the filter, clean and wash it and
restart filtration.
21. Collect the filtrate in top open 200kg HDPE drum
22. After completing filtration, drain material in line and wash reactor & cartridge filter.
23. After filtration of entire material, through peristaltic pump it is sent to SPDU Unit. SPDU
unit has steam jacketed body.
24. LA get condensed in internal condenser of SPDU, uncondensed will go to external LA
condenser.
25.Condensed will be collected in a receiver and sent back for next batch.
• Dextrose Anhydrous
• Lauryl Alcohol
• Myristyl Alcohol
• Capric Alcohol
• Capryl Alcohol
• Sodium Sulphite
• Magnesium Oxide
• Hydrogen Peroxide-50%
• Sodium Hydroxide
• Catalyst APG
• Product APG
2. Dextrose Anhydrous
a. Procurement of Dextrose Anhydrous is put in separate table. And is to be stored at
25 to 35 ⁰C.
b. To be kept at dry place because it is susceptible to moisture
c. The specification for Dextrose Anhydrous are;
3. Catalyst APG
a. Store the container tightly closed in a dry and well-ventilated place.
b. Packing MOC is PPFRP and Glass Lined.
1. Sodium Sulfite
Magnesium Oxide
• Q and S Components
• Q components;
A. Reaction Step;
NPT/SOP/PBE/005/F01 Rev No. 00 Effective date: 15/11/2017 Page 9 of 34
Project Nebula
1. Moisture recovery- Before reaction it is required to remove the moisture otherwise
it will form polydextrose.
2. Temperature of the reaction should be kept in between 112 to 115 ⁰C. The
reaction will take more time below 112 Degree C (Due to reduced rate of reaction).
And above it will change the degree of polymerization.
2. Vacuum to be kept below 0.5 torr during the reaction, otherwise the rate of
recovery of water will be more which will cause higher BCT.
3. Quality of Dextrose- Should as per specs may hamper overall reaction, such BCT
and colour bodies formation.
4. Quality of LA (C12-14 composition)- composition should be as per our
specifications otherwise product may have different properties such as viscosity and
foaming property and DP.
5. Mixing of Dextrose and LA should be efficient as it is a heterogeneous reaction.
Otherwise the BCT will get increase.
6. Catalyst effect- More catalyst forms more side reactions and lower lading of
catalyst increase BCT also impact on DP of product.
B. Filtration Step;
1. Temperature of Filtration- Filtration to be carried out at 120 degree, below that
temperature it will have an impact on degree of polymerization. Ultimately it will
change the final characteristic of Product (i.e. Product Viscosity and Degree of
polymerization).
D. Dilution Step;
1. Temperature in Dilution- Dilution to be carried out at 60 degrees else the mixing
of INP-APG and water will take more time.
2. Dilution to be carried out at low RPM- Higher RPM contributes to foaming.
(Experiments have been conducted at 10 RPM, similarly some value to be set at
commercial scale.
E. Bleaching Step;
1.
1. Hydrogen Peroxide-
• Storage - Avoid contamination - Contamination could cause decomposition and
generation of oxygen which may result in high pressure and possible container rupture.
• Empty drums should be triple rinsed with water before discarding.
• Isolate post spill area. Keep people away from and upwind of spill/leak. Eliminate all
sources of ignition and remove combustible materials.
• Handling – Avoid contact with skin, eyes and clothing. Wear personal protective
equipment (Safety Goggle, Safety shoes, Mask, Gloves and safety helmet).
2. Sodium Sulphite-
• Handling – Avoid contact with skin, eyes and clothing. Wear personal protective
equipment (Safety Goggle, Safety shoes, Gloves and safety helmet).
3. Magnesium Oxide-
• Handling - Wash hands thoroughly after handling. Minimize dust generation and
accumulation. Avoid contact with eyes, skin, and clothing. Use with adequate
ventilation. Avoid breathing dust and fume.
• Wear personal protective equipment (Safety Goggle, Safety shoes, Mask, Gloves
and safety helmet).
4. Caustic Lye-
• Handling – Use Gloves, Mask, Goggle, Helmet and shoes. Face-shield, Corrosion-proof
suit.
1. MAAG Pump outlet will directly go to a dilution vessel with high shear mixer arrangement.
2. There will be two vessel kept for dilution of equal capacity, one is used for first 24 hours
and other will be used for next day 24 hrs.
3. The amount of material coming out of SPDU in a Day- 40 kg/hr feed rate means in a day
960 kg of water at 80-90 C is kept in Vessel.
4. First vessel material will be sent to Bleaching vessel. Gear pump after dilution to bleaching.
5. Once the first vessel has run for 24 hrs, the SPDU feed will be shifted to 2 nd vessel using
three way valve. And there the process of dilution started .
6. MgO, NaOH and sodium Sulphite will be charged from manhole directly into the bleachng
vessel while H2O2 will be charged using Diaphragm pump directly through carbouys.
7. As there is heavy foam generates during the reaction, foam breaker type agitator to be
installed.
8. The final stabilized process in sent to Storage tank in Tankfarm for ageing.
Advantages;
1. Very simple option in all, which will ease the operations.
2. In any case the APG does not mix properly with water due to spec change or any
abnormality, this option provides us the flexibility of time of digestion.
Disadvatages;
1. More number of bays are occupying in this option as compared to 2nd and 3rd option.
2. More equipment leads to more piping leads to high initial investment.
3. Inlet pipelines leads to more bends, high chances of dead zones could form, which can
cause solidification of material in longer duration.
4. More residence time at higher temperature leads to color variation.
Option-2- A shear mixer in place of dilution vessel with two Bleaching vessel.
1. MAAG Pump outlet will directly go to an inline High shear mixer with two feed stream
lines, one is hot water (80-90 C) and one is Inp- APG.
2. Inline shear mixer will also be jacketed and insulated.
3. There will be two vessel kept for bleaching of equal capacity, one is used for 24 hours
and other will be used for next day.
4. The amount of material coming out of SPDU in a Day- 40 kg/hr feed rate means 40
kg/hr feed rate of water is to be provided using a flowmeter.
5. MgO, NaOH and sodium Sulphite will be charged from manhole directly into the
bleachng vessel while H2O2 will be charged using Diaphragm pump directly through
carbouys.
6. As there is heavy foam generates during the dilution and bleaching, foam breaker type
agitator to be installed in bleaching vessel.
7. The final stabilized process in sent to Storage tank in Tankfarm for ageing.
Advantages;
1. This option will require 1 bay lesser than option 1.
2. Scaleup will be easier.
Disadvantages
1. There will not be any flexibility of mixing of material if in any case the mixing will not be
proper due to spec change in SPDU.
2. This option needs proper jacketing of shear mixer as well, else solidification of product may
happen. Also Flooding of SPDU can happen.
3. Check the pressure zones- cavity formation- foam generation- check with vendor.
4. Initial investment of this option will be high as compared to 1 and 3.
5. Operational control is more in comparison to both the options.
1. MAAG Pump outlet will directly go to a dilution vessel with high shear mixer
arrangement.
2. Dilution vessel is of bigger size which can accommodate 40 hrs of batch inside it. Once
the 24hrs batch is done. The material upto 60% level will be transferred to bleaching
vessel.
3. The amount of material coming out of SPDU in a Day- 40 kg/hr feed rate means 40
kg/hr feed rate of water is to be provided using a flowmeter.
Advantages
1. There will be only 1 dilution vessel, so saving 1 bay in comparison to option 1.
2. Less initial investment compare to all options.
Disadvantages
1. Mixing of entire mass should be uniform otherwise, solids will be stuck in the strainer of
pump from dilution to bleaching.
2. If due to any specification variation occurs during SPDU which is causing bleach to take
more time. This time flexibility is not there in dilution step due to only 1 dilution vessel. Else
we have to stop the SPDU.
Option 4- Slow stirring dilution vessel with continuous system and Bleaching will be at high
temperature.
1. MAAG Pump outlet will directly go to a dilution vessel with low RPM mixer arrangement.
2. Dilution vessel is of bigger size which can accommodate 40 hrs of batch inside it. Once
the 24hrs batch is done. The material upto 60% level will be transferred to bleaching
vessel.
3. The amount of material coming out of SPDU in a Day- 40 kg/hr feed rate means 40
kg/hr feed rate of water is to be provided using a flowmeter.
4. But rather doing the same we will reduce the flowrate of water by 4 kg’s and mix 36
Advantages
1. System will be easier in operation and easier in understanding.
2. Less initial investment.
Disadvantages
1.
Option 5- Slow stirring in Dilution vessel with continuous system and 2 Bleaching vessel will be
at high temperature.
1. In this process the entire process of dilution is same as above till it is sent to bleaching
vessel.
2. The entire mass will be sent from Dilution vessel to bleaching vessel through Nitrogen.
3. In this option there will be two bleaching vessel, which enable us to keep the capacity
of bleaching for 48 hrs.
4. In this option the same vessel will be used for bleaching (means addition of MgO,
NaOH, H2O2 and sodium sulphite), Foam adjustment through heating and packing.
5. In bleaching vessel, all the additions will be done and the batch will be completed in 24
hrs at 50-60 degree temperature and additional 2 hrs will be required for foam settling
at 90 degree. And packing will be done in 8 hrs. So total 34 hrs of batch cycle.
Advantages
1. System will be easier in operation and easier in understanding.
2. Good buffer in bleaching process.
Disadvantages
1. Three bays will be engaged, so less space for future.
Process Parameters
Process - Steps Intermediate Data Value
Name
1. Reaction RxAPG Density
RxAPG Viscosity @
a. Operational Operational temperature( at 112 oC )
temperature = < 400 cP
b. RT RT = Solid
c. Min and Max
(Range)
Ref-APG pH 5-5.4
3. Dilution INP-APG Density 1.07-1.09 g/cm3( 25 oC)
INP-APG Viscosity @ At 25 oC
a. Operational Min = 1000 cP (Note: Considering
temperature C0810 APG)
b. RT Max=25000 cP (Note: Considering of
c. Min and Max Plantcare analysis giving you
(Range) maximum viscosity).
INP-APG pH 4.5-5 (10-10.5 after pH
adjust)
N2 Pressure -
4. Bleaching Final APG Density 1.07-1.09 g/cm3( 25 oC)
Viscosity @
a. Operational At 25 oC
temperature Min = 1000 cP
b. RT Max=25000 cP
c. Min and Max
(Range)
pH During bleaching( 10-10.5) after
bleaching ( 11.5-12.5)
Temperature Range 85-90 oC
Pressure Water vapour pressure at 90 oC
N2 Pressure Need clarification
Tanfarm Philosphy;
Packing
Utility:
1. Steam is required for Reaction vessel, Preheater of SPDU, SPDU, Dilution and bleaching
vessel.
2. Cooling water will be required in water condenser, condenser of SPDU and LA condenser.
3. Oil ring with booster (0.1 torr) and Water ring vacuum pump (50 torr) will be required for
Reaction vessel and SPDU respectively.
4. Nitrogen is required for purging and blanketing.
5. Soft water is required for Dilution and bleaching.
6. Chilling water for vacuum trap.
Effluent;
Mechanical:
8. Piping material;
• All Process pipelines will be in SS316 construction.
• All SS pipes will be in ERW construction and fittings will be seamless.
• All the utility (steam, Chilled water and cooling water) will be in MS.
• Pipes up to 2” will be of Sch 40, 3”-6” will be of Sch 10 and above will be of Sch 5.
• Valve, Nut bolt will be of same or superior make compared to pipes
• NRVs of pipe equivalent MOC will be installed at pump discharge to avoid reverse
flow
• Maintenance platform and space at all required position
• Lifting beam for ease of maintenance.
Civil:
• This will be covered in one single concept notes of entire plant.
Electrical:
• The system will be considered under flameproof area.
• The motors used will be of IE3 class for all the running equipment.
• It will have proper lighting arrangement for proper illumination in night.
• All running equipment’s will have local emergency start stop button with protection.
• All the equipment and structure will have double earthing.
• Further more details will be included in concept notes of electrical.
Instrumentation:
• Inventory to be maintained for Raw material; in which Lauryl Alcohol to be stored in storage
tanks in tank farm area and Dextrose comes in 25Kg bags.
Actual
Raw Material TPM Storage
Lauryl Alcohol 17 35
Safety:
1. The plant should be covered with FH system for handling the emergency.
2. Wherever required the required type fire extinguishers will be in place with clear
identification and easy to access.
3. Safety posters and MSDS to be displayed in all working areas.
4. Internal HAZOP study will be conducted for all process
5. Plant is having safety showers at appropriate locations, easy to access and with effluent
properly routed to effluent pit.
6. Walking and operational areas will be clearly marked with yellow strips.
7. Earthing to individual equipment.
8. Flange guards to be provided in flange joints location.
Laboratory Facilities:
• The laboratory setup is required for performing various analyses for RM and FG.
Statutory Aspects:
Others:
3.0 SIZING
Bleaching Vessel
Dilution to bleaching transfer
pump.
Bleaching to Tank-
farm/Packing pump.
H2O2 Diaphragm Pump