1-9 10 11 12 13 Sun 15 16 17 18 19 20 21 22 23 24 25
PROJECT WORK
B BE / DE
Concept Notes for OMC distillation in 2PE
1
column
( Changes in system )
2 OMC distillation - Backup calculation
3 Plant / Equipment Layout
4 PFD for OMC distillation Done
5 P&ID for OMC distillation Done
6 Piping layout
7 BOM for piping modification
8 SOP
9 HAZOP study
10 P&ID discussion
C Procurement
1 High temp circulation pump seal
2 Insulation to required section
3 Piping material
4 Feed SS cartridge filter ( Available)
D Execution
1 Hot water washing of system :-
Distillation column 2
Reciever
All column -2 related piping
SST-I, SST-II, SST-IV,SSR-V
R11 collection tank and its associated piping
R12 collection tank and its associated piping
R13 collection tank and its associated piping
R31 collection tank and its associated piping
R33 collection tank and its associated piping
E Commissioning
1 Actual trial with crude OMC - R11 / R13 stream
26 27 28
Equipements reduired :-
Sr. No Parameter Quantity
1 Column Circulation Pump - Seal 1
2 Piping & Fabrication
3 SS catridge filter 1
4 Product cooler HEX 1
5 Insulation
Project Parivartan Scheduling
1-9 10 11 12 13 Sun 15 16 17 18 19 20 21 22 23 24 25
D Execution
Draining all material through system, piping,
1
vessels, columns
2 Hot water washing of system :-
Distillation Column 2
Reciever
All column -2 related piping
SST-I, SST-II, SST-IV,SSR-V
R11 collection tank and its associated piping
R12 collection tank and its associated piping
R13 collection tank and its associated piping
R31 collection tank and its associated piping
R33 collection tank and its associated piping
E Commissioning
1 Actual trial with crude OMC - R11 / R13 stream
26 27 28