Professional Documents
Culture Documents
Building Construction Method
Building Construction Method
Building Construction Method
INSTRUCTIONAL MATERIALS
for
BUILDING
CONSTRUCTION
METHOD
Construction Methods and Project
Management (CIEN 30293)
Compiled By:
1. Chile
2. Mexico
3. United States
4.Antarctica
5. Russia
6. Japan
7. Philippines
8. Japan
9. New Zealand
10. Papa New Guinea
11.Indonesia
12.Canada
13.Peru
14.Taiwan
15. Gautemala
SCOPE OF WORKS IN BUILDING CONSTRUCTION
A – MOBILIZATION,
B – EARTHWORKS
D – FOUNDATION WORKS
F – CONCRETE WORKS
G – MASONRY WORKS
H – CARPENTRY WORKS
K – ROOFING WORKS
L – FINISHES
M – PAINTING / VARNISHING
N – WATER PROOFING
O – SANITARY WORKS
P – ELECTRICAL WORKS
Q – MECHANICAL WORKS
MOBILIZATION A
Is best described as the deployment of resources at the
project site. This also involves any work that is necessary to
provide access to the site including, but not limited to,
grading, clearing and grubbing.
MANPOWER
MATERIALS
EQUIPMENT
MOBILIZATION A
Application in DPWH Projects
GRAVEL BEDDING
EARTHWORKS B
1 General Requirements
1.1 Earth- Moving Equipment
2 Methodology
2.1 Construction Survey
2.2 Finding Grade Level
2.3 Setting Batterboards
EARTHWORKS B
Construction procedure and lay-out
1. Locate the boundaries of the construction site.
2. Clear the site of any obstructions.
3. Determine the building set back from the road line.
NYLON CHORD
BATTER BOARD
PLUMB BOB
STAKES
or corners at 90 1/2" x 4’ x 8’
PLYWOOD BOARD
degrees.
2” x 3”
BATTER BOARD
5. Verify the measure- 2” x 2”
STAKES
ment in the plan.
a) Center to Center,
b) Center to Outer Side
c) Outer to Outer side
d) Inside to inside.
EARTHWORKS B
Method on Layout and Staking with the Aid of Instrument
EARTHWORKS B
3 Quality Control
*For Clearing and Grubbing, Removal of Structures, Structure
Excavation:
*For Embankment:
Soil poisoning
A process wherein the soil is
treated with chemical solutions to
control and prevent the entry of
termite into the structure
Wood preservation
a process wherein the wood is also
treated with chemical solution and LOWER LOCATION :
SOIL POISONING
are applied directly either external
or internal on wood surfaces.
C
TERMITE CONTROL &
WOOD PRESERVATION
1 General Requirements
1.1 All labor, materials and equipment to be used in
the completion of the job shall be furnished by the
pest control provider.
▪ Cordoning Method
- When there is no visible evidence
of termite infestation
▪Drenching Method
- When the soil shows termite
infestation
Strip foundation
Mat
Foundation
Spread footing
FOUNDATION WORKS D
2 Types of Building Foundation
2.2 DEEP FOUNDATION
Micropiles Bored Piles Pre-cast Piles
FOUNDATION WORKS D
2 Types of Building Foundation
2.3 JET GROUTING
Ground stabilization procedure that
works on plastic granular materials
using the principle of Ultra High
Pressure Injection of Cement Grout
FOUNDATION WORKS D
3 Quality Control
3.1 Pile Integrity Test
1. ) Bar splicing
a. Tension Bar
b. Compression Bar
2. ) Bar Spacing
- shall not be less than the normal diameter of the bars or
40 mm for column, or as specified in the structural design notes.
CONCRETE WORKS F
STEEL REQUIREMENTS
a. Splice location on suspended slab
6.) Bending
1. All reinforcements shall be bent cold, unless otherwise
permitted by the Engineer.
2. Reinforcement partially embedded in concrete shall not be
field-
bent except as shown in the design drawings or as permitted by
the engineer.
CONCRETE WORKS F
CONCRETE
1.) Mixing and Delivery
❖Concrete may be mixed at the site of construction or at the
batching plant.
Mixer Capacity Mixing Time
1.5m3 not less than 60 seconds
Greater than 1.5 m3 not less than 90 seconds
Buckets or Hoppers
Manual or
Motor
Propelled
Buggies
CONCRETE WORKS F
CONCRETE
3.) Conveying / Transporting
Chutes Pipes
CONCRETE WORKS F
CONCRETE
3.) Conveying / Transporting
Conveyor Belt
Concrete Pump
CONCRETE WORKS F
CONCRETE
4.) Depositing of Concrete - Column
Drop
Chute
Maximum
Drop
Height
1.50 meter
or less
PROPER IMPROPER
CONCRETE WORKS F
CONCRETE
4.) Depositing of Concrete - Column
CONCRETE WORKS F
CONCRETE
4.) Depositing of Concrete - Slab
CONCRETE WORKS F
CONCRETE
4.) Depositing of Concrete - Slab
CONCRETE WORKS F
CONCRETE
4.) Depositing of Concrete - Wall
CONCRETE WORKS F
CONCRETE
5.) Compaction of Concrete
Concrete during and immediately after placing shall be
thoroughly compacted. Compaction shall be done by
mechanical vibration. The intensity of vibration shall be such
as to visibly affect a mass of concrete with a 3 cm slump over
a radius of at least 50 cm
CONCRETE WORKS F
CONCRETE
6.) Construction Joints
Construction joints shall be made only as shown in the Plans or as
called for in the pouring schedule, unless otherwise approved by
the Engineer. It shall be thoroughly cleaned of foreign matter and
laitance.
CONCRETE WORKS F
CONCRETE
6.) Construction Joints
CONCRETE WORKS F
CONCRETE
7.) Curing of Concrete
1. Water Method
2. Curing Compound
3. Waterproof Membrane Method
4. Forms-in-Place Method
CONCRETE WORKS F
3 Quality Control
Minimum Test Requirements:
a) CONCRETE:
1. Design Mix
1.a Batching Plant – to be prepared by the Supplier
1.b Jobsite – to be prepared by the contractor
2. Conduct Trial Mix (reference only)
3. Submit Samples for:
3.a Portland Cement
1- Q (Quality Test) for every 2,000 bags or fraction thereof
3.b Fine Aggregates:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.c Coarse Aggregate:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.d Water:
1- Certificate from Project Engineer
MASONRY WORKS G
- is a form of construction work equipped with stone, bricks, concrete, hollow clay
tile, concrete block or tile, or other similar building units or material or a
combination of these materials laid up unit and set in mortar.
Concrete Hollow Blocks
Concrete hollow blocks are classified as load bearing and
non- load bearing blocks.
1 Requirements
A. Strength Requirements
a) Non load bearing concrete masonry units – ASTM C 129
- 100 mm thick
Individual – 3.45 Mpa ( 500 Psi )
Average - 4.14 Mpa ( 600 Psi )
b) Load bearing Concrete masonry units – ASTM C 90
- 150 mm to 200 mm thick
Individual - 5.5 Mpa ( 800 psi )
Average - 6.9 Mpa ( 1000 Psi )
MASONRY WORKS G
2 Methods
Block laying after the
concreting of tied
column
Concreting of column
after block laying of
walls
MASONRY WORKS G
MASONRY WORKS G
MASONRY WORKS G
MASONRY WORKS G
3 Quality Control
Minimum Test Requirements:
a. Drywall Partition
1. Vertical and horizontal alignment
2. Material specification
3. Complete installation of Electro-mechanical rough-ins
4. Rigidly connected to the flooring, walls and at the bottom of the
ceiling frames.
5. Appropriateness of tools to be used.
CARPENTRY &
JOINERY WORKS H
CARPENTRY &
JOINERY WORKS H
Ceiling
1. Dimension and alignment of nailers/metal frames
2. Material specification
3. Complete installation of sanitary/plumbing and electro-
mechanical rough-ins
4. Properly anchored to the carrying metal channel/wood runner.
5. Complete installation of roof framing and roofing
6. Appropriateness of tools to be used.
CARPENTRY &
JOINERY WORKS H
2. Fabrication of steel frames can be done in the field during erection of the
building or at the shop.
3. When punching and drilling steel make sure that the hole drilled or
punched is 1.5 to 3 mm greater than the diameter of the bolt to make it easy in
inserting and bolts through it.
7. If all works are done in accordance with plans and specifications, paint all
metals with metallic paint for rust protection.
ROOF FRAMING WORKS J
ROOF FRAMING WORKS J
ROOF FRAMING WORKS J
LENGTH OF WELD
ROOF FRAMING WORKS J
2 Quality Control
Minimum Test Requirements:
❖Material Requirements
A. Preparatory Works
Preparatory to the installation of the corrugated G.I. roofings, purlins
should have been placed and spaced properly to fit the length of the
roofing sheets. The top of the purlins should be at the same plane.
b) Valleys
Valleys shall lap at least 450 mm each way under the
roofing sheets and shall be secured to the framework
with galvanized nails. The nails are placed below the
roofing sheets. Rivets along the side of the valley shall
be fastened at every second corrugation.
ROOFING WORKS K
c) Flashing
Flashing, of gauge 26 plain G.I. sheets, unless otherwise specified, shall be
installed along intersections of roofs and concrete or masonry walls.
Flashing running parallel to sheet corrugations must have its edge turned
down. Flashing across sheet corrugations or at an angle thereto, shall lap at
least 250 mm and the edge of flashing turned down at each corrugation.
d) Gutters
Gutters, of gauge 24 plain G.I. sheets, shall be fabricated to the shape and
dimensions indicated in the Plans. Gutter joints shall be flat seam folded in
the direction of flow and soldered evenly. Gutter shall be attached to fascia
board with appropriate nails or screws spaced of not more than 900 mm on
centers. As additional support, gutters shall have plain G.I. strap hangers 25
mm wide fastened to the roof nailers and shall be spaced at not more than
900 mm on centers.
The gutter shall be installed with a pitch of 1 in 100 sloped toward the
downspout.
ROOFING WORKS K
2 Methods
a. Lay-outing
In laying out the placement for the J-
Bolts, make sure that it will be aligned
near enough to the lip of the purlin
avoiding it to be drilled when making
holes. A guide chord may be stretched
out from end to end of the purlin to
establish alignment.
ROOFING WORKS K
2 Methods
b. Drilling
❖Material Requirements
a. Glazed Tiles and Trims
b. Unglazed Tiles
c. Trims
d. Accessories
e. Cement
f. Sand
g. Lime
FINISHES L
❖Construction Requirements
A. Surface Preparation
D. Cleaning
4. Trowel finish
FINISHES L
3 Quality Control
Minimum Test Requirements:
Surface
preparation for Surface preparation
Boards for Concrete &
Masonry Surface
PAINTING &
VARNISHING WORKS M
Safety Concerns