Classic Schedule Layout 09-Mar-24 04:53 PM


Activity ID Activity Name Original Start Finish Budgeted Total March 2024
Duration Cost

(New Project) 0.00 $0.00

(New Project) 0.00 $0.00

Tenhical Vocational Training Center 49.00 10-Mar-24 12:00 AM A 06-May-24 08:30 AM $20,600.00

Rough Finishes 26.00 10-Mar-24 12:00 AM A 07-Apr-24 11:30 AM $20,600.00

Brick Works 13.00 10-Mar-24 12:00 AM A 24-Mar-24 09:30 AM $20,600.00 24-Mar-24 09:30 AM
A1000 First Floor Brick Work 8.00 14-Mar-24 02:30 PM 24-Mar-24 09:30 AM $0.00 First Floor Brick Wor
A1010 Ground Floor Brick Work 5.00 10-Mar-24 12:00 AM A 14-Mar-24 02:30 PM $20,600.00 Ground Floor Brick Work
Plaster Works 13.00 24-Mar-24 09:30 AM 07-Apr-24 11:30 AM $0.00
A1030 Cround Floor Plaster Work 5.00 24-Mar-24 09:30 AM 28-Mar-24 04:30 PM $0.00
A1020 First Floor Plaster Work 8.00 28-Mar-24 04:30 PM 07-Apr-24 11:30 AM $0.00
Final Finishes 23.00 07-Apr-24 11:30 AM 06-May-24 08:30 AM $0.00

Tile Work 13.00 07-Apr-24 11:30 AM 21-Apr-24 02:30 PM $0.00


A1050 Ground Floor Tile Work 8.00 07-Apr-24 11:30 AM 15-Apr-24 05:00 PM $0.00
A1040 First Floor Tile Work 5.00 16-Apr-24 12:00 AM 21-Apr-24 02:30 PM $0.00
Paint Works 10.00 21-Apr-24 02:30 PM 06-May-24 08:30 AM $0.00
A1070 G F Paint 5.00 21-Apr-24 02:30 PM 30-Apr-24 11:00 AM $0.00
A1060 F F Paint 5.00 30-Apr-24 11:00 AM 06-May-24 08:30 AM $0.00

Actual Work Critical Remaining W... Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
(New Project)... Classic Schedule Layout 09-Mar-24 04:53 PM
April 2024 May 2024 June 2024 July 2024

06-May-24 08:30 AM, Tenhical Vocational Training Center

07-Apr-24 11:30 AM, Rough Finis hes


24-Mar-24 09:30 AM, Brick Works
First Floor Brick Work

07-Apr-24 11:30 AM, Plaster Works


Cround Floor Plaster Work
First Floor Plaster Work
06-May-24 08:30 AM, Final Finishes
21-Apr-24 02:30 PM, Tile Work
Ground Floor Tile Work
First Floor Tile Work
06-May-24 08:30 AM, Paint Works
G F Paint
F F Paint

Actual Work Critical Remaining W... Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation