Professional Documents
Culture Documents
Cost Management Slides
Cost Management Slides
Today
Actual
Costs (AC) Planned
Cumulative Value (PV)
Value
Is this project
Earned over/under budget?
Value (EV)
Is it ahead of/behind
schedule?
Time
Cost Management Key Terms
PV - Planned Value, estimated value of the planned work
EV – Earned Value, estimated value of work done
AC – Actual Cost, what you paid
BAC – Budget at Completion, the budget for the total job
EAC –Estimate at Completion, what is the total job
expected to cost?
ETC – Estimate to Complete, forecasted costs to complete job
VAC – Variance at Completion, how much over/under
budget do we expect to be?
Cost Management Process?
Three processes
Estimate Costs
Determine Budget
Control Costs
Control Costs
Estimat Determine
Budget
e
Costs
Types of Cost Estimates
Reserve analysis
Project Cost Management
Cost of quality
Management Plan Plan Updates
• Schedule Mgmt Pln
• Staffing Mgmt Pln
• Risk Register
Estimate Costs
Determine Budget Control Costs
Estimating Methods
Analogous (Top Down) estimating – Managers
use expert judgment or similar project costs [quick,
less accurate]
Bottom-Up estimating – People doing work estimate
based on work base suggestion, rolled up into project
estimate [slow, most accurate]
Parametric estimating – Use mathematical model
[accuracy varies] Two types:
Regression analysis – based on analysis of multiple data
points
Learning Curve – The first unit costs more than the
100th, forecasts efficiency gains
Estimating Methods
Vendor Bid Analysis – Estimating using bids +
allowances for gaps in bid scope [slow, accuracy
depends on gaps]
Reserve Analysis – Adding contingency to each
activity cost estimates as zero duration item [slow,
overstates cost]
Determine Budget
Tools & Techniques
Outputs
Project Scope Statement Cost aggregation Cost Baseline
Work Breakdown Structure Reserve analysis
Parametric estimating Project Funding
WBS Dictionary Requirements
Inputs Funding limit reconciliation
Activity Cost Estimates
Activity Cost Estimates Cost Management
Supporting Detail Plan Updates
Minimal customization
No change in procurement systems
during accounts payable implementation
Cost/Benefit Analysis BSR was broken down into a three-year cash
& Internal Rate of Return (IRR) outlay without depreciation. Costs are
represented in thousands. Capital and
expenses
are combined in this example.
Example: Business Systems Replacement
Project Cash Flow Analysis
FY95 FY96 FY97 3 Year Future Annual
Total Costs/Savings
($000) ($000) ($000) ($000) ($000)
Costs
Oracle/PM Software 992 500 0 1492 0
(List Price)
60% Discount (595) (595)
Oracle Credits (397) 0 (397)
Net Cash for Software 0 500 500
Software Maintenance 0 90 250 340 250
Hardware & Maintenance 0 270 270 540 270
Consulting &Training 205 320 0 525 0
Tax & Acquisition 0 150 80 230 50
Total Purchased Costs 205 1330 600 2135 570
Information Services & 500 1850 1200 3550 0
Technology (IS&T)
Finance/Other Staff 200 990 580 1770
Total Costs 905 4170 2380 7455 570
Savings
Mainframe (101) (483) (584) (597)
Finance/Asset/PM (160) (1160) (1320) (2320)
IS&T Support/Data Entry (88) (384) (472) (800)
Interest 0 (25) (25) (103)
Total Savings (349) (2052) (2401) (3820)
Project Organizational
Process Assets
Management Plan
Updates
Project Management
Plan Updates
Value
Completion
(VAC)
Graph Target
Cost &
Schedule
Planned Schedule
Value Varianc
(PV) (Time)
Earned
Value (EV)
Earned Value Formulas
Project Current
Start Status BAC
PV
EAC
AC ETC
Example: . Earned Value Calculations
for One Activity After First Week
Example: Earned Value Calculations for
a One-Year Project After Five Months
Example Figure:Earned Value
Chart for Project After Five Months