Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

Check lists

Table of contents
Sl.No Description
II PEB structures checklist
1 Column
2 Rafter
3 Structure
4 Metal panel
5 Plump
6 Bolt torque
7 Roof sheeting
8 Wall sheeting
9 Insulation
10 Gutter downtake
11 Accessories
STRUCTURAL STEEL - COLUMN

Project: SHOP / STRUCTURE :


Location:
Date:
Drwg No:
SL.NO ITEM DESCRIPTION Yes No
1 Sequence of erection (As per erection plan)

2 Centre line, level and size of foundation anchor bolts/inserts

3 Erection crew and machinery for erection (As per erection plan)

4 Location / orientation of structure

5 Grade, make and size of erection HT Bolts

6 Erection area safety measures (Ref. Pre lift safety permit)

7 Check Nut for Anchor Bolt

8 Arrangement for temporary bracing/Guying


Required Actual
± mm
9 Column base plate level (Allowable )
5 0
± mm
Column Plumb (1/1000mm) (Allowable )
10
11 0

Contractor CMO/ Client


Name
Date
Signature
TRUCTURE :

Remarks

CMO/ Client
STRUCTURAL STEEL ERECTION - RAFTER

Project: SHOP / STRUCTURE :

Location:

Date:

Drwg No:

SL.NO ITEM DESCRIPTION Yes No Remarks

1 Sequence of erection (As per erection plan)

2 Centre line, level and size of foundation anchor bolts/inserts

3 Erection crew and machinery for erection (As per erection plan)

4 Location / orientation of structure

5 Grade, make and size of erection HT Bolts

6 Torque wrench for tightening

7 Erection area safety measures (Ref. Pre lift safety permit)

8 Arrangement for temporary bracing/Guying

Required Actual

9 Torque Value (20 mm bolts) 416

10 Torque Value (24 mm bolts) 719

11 Torque Value ( mm bolts) - -

Contractor CMO/ Client


Name
Date
Signature
STRUCTURAL INSPECTION REPORT

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

SL.NO DESCRIPTION Yes No Remarks

1 Is the roof & wall bracing installed

2 Is the bracing tight

3 Are the flange brace installed at rafters & columns

4 Are all high strength bolts fitted in correct locations

5 Are the washers installed with H.S.B

6 Is the thread projection correct

7 Are the eave strut & purlin clips fitted ( where required)

8 Are the H.S.B's Correctly tightened

9 Are the main frames correctly plumbed & aligned

10 Are the crane beams braced & aligned

11 Are stoppers installed on crane beams

12 Are purlins & girts straight & aligned

Are all machine bolts correctly fitted in secondary


13
framing

14 Has primer paint been touched-up

Contractor CMO/Client
Name
Date
Signature
Metal panel installation

Name of the work : Date :

Contractor : Drawing Ref :

Location : Checklist No:


Sl.No Item Description Yes No Remarks

1 Is Marking done as per the layout

Is Floor track fixed with fasteners and is sturdy and


2
rigid enough to withstand the load of the panels
Is Floor leveling done and floor track fixed to the level
3
after placing the required shims
Are Wall panels installed to the plumb, placed over
4 the floor track and created the step for floor coving
flush with the wall panels.
Are Ceiling supports marked on the floor and
5
transferred to the roof as per layout
6 Is Shaft floor level sealed with fire proof material
Are Anchor fasteners anchored to the roof and
7
supports are hanged
Are Ceiling panels erected and hanged to the
8 supporting system and Locking done with wall panels
by using coving profiles
9 Are Ceiling panels leveled
Are Covings for wall to wall& wall to ceiling erected
10 using corner profiles and Covings fixed using internal
corners& external corners
Are Door frames with hardware erected to the plumb
11 and anchored to the wall panels and is Second glass
fixed after cleaning with disinfectant.
Are Double glazed view panels cleaned internally with
12 the disinfectant before fixing the second glass and are
glasses fixed flush with the wall panels
Are Light fixtures frames are through cut and sealed
13
with the silicon sealant
Are Silicon sealants applied in the panel joints and
14
coving joints

Remarks:

Contractor CMO/Client
Name
Date
Signature
PLUMBNESS AND ELEVATION INSPECTION REPORT OF STRUCTURAL

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

PLUMBNESS - ACTUAL
SL.NO COLUMN & GIRDER HEIGHT RESULT REMARKS
EAST NORTH

10

11

12

13

14

15

Contractor CMO/Client
Name
Date
Signature
BOLT TORQUING INSPECTION REPORT OF STRUCTURAL

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

BOLT TORQUE
SL.NO COLUMN & GIRDER BOLT SIZE RESULT REMARKS
MIN VALUE(N-M) ACTUAL (N-M)

10

11

12

13

14

15

Contractor CMO/Client
Name
Date
Signature
ROOF SHEET INSPECTION REPORT

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

SL.NO DESCRIPTION YES NO NA Remarks

1 Are the sheets correctly lapped at sides & end

2 Is the tail line at eaves straight

3 Has end-lap mastic been installed

4 Have the correct fasteners been used

5 Have the fasteners been fixed in correct location

6 Has the roof been cleaned

Have sheets been crimped at vents or lean-to


7
connection

Have the external foam closures been installed


8
where required

9 Aligning, lapping & Fastening checked

10 Fasters defect check

11 Improper base angle check

12 Field damages

Contractor CMO (Execution) CMO(QA/QC)

Name

Date

Signature
WALL SHEETING INSPECTION REPORT

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

SL.NO DESCRIPTION YES NO NA Remarks

1 Is the base angle securely fastened to concrete

2 Are the sheets fastened in the correct location

Are the sheets fastened with correct length


3
fastener

4 Are the sheets plumbed

5 Are the sheets correctly lapped

6 Are the corner trims correctly fitted & fastened

7 Are the gable trims correctly fitted & fastened

Are the external form closure fitted at eave &


8
gable

9 Are the internal form closes fitted at base angle

10 Aligning, lapping & Fastening checked

11 Fasters defect check

12 Improper base angle check

13 Field damages

Contractor CMO (Execution) CMO(QA/QC)

Name

Date

Signature
INSULATION INSPECTION REPORT

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

SL.NO DESCRIPTION YES NO NA Remarks

1 Is the insulation taut and not sagging

Has the insulation been properly stapled at side


2
tabs

Has the insulation been properly fixed & folded


3
at eaves

Has the insulation been properly fixed at


4
skylight frames

Has the insulation been properly fixed at the


5
base angle

6 Insulation with Lap & Securing

7 Insulation folding

8 Insulation trimming & cutting

9 Sealant installation

10 Has the insulation damages rectified

Contractor CMO (Execution) CMO(QA/QC)

Name

Date

Signature
ACCESSORIES INSPECTION REPORT

PROJECT LOCATION

CONTRACTOR CLIENT

DWG NO DATE

SL.NO DESCRIPTION YES NO NA Remarks

1 Are Personnel doors operating correctly

2 Are locksets, panic devices, closers correctly adjusted

3 Are the sliding door operating smoothly

4 Are the roll - up doors correctly tensioned & operatin

5 Are the windows sliding freely & locking correctly

6 Are ridge vent dampers operating correctly


7 Have ridge vent flashing & clousers been installed

8 Have roof curb or penetrations been installed

10

11
Contractor CMO/Client
Name
Date
Signature

You might also like