Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Name of the work:- Construction Of Concrete Gravity Dam And Spillway

(Superstructure) with its accessories and appurtenant including energy dissipation


arrangement, piers and abutment, head regulator, penstock of powerhouse, construction
sluice, drainage and inspection gallery, all mechanical gate work, electrical work with
power connectivity from existing Sub Station(2x250KVA), watchman cum operator shed,
instrumentation, construction of internal road, beautification of dam site including survey,
planning, design and estimate of all components with operation and maintenance of the
project for a period of five years or five flood seasons whichever is more of Hadua
Irrigation Project across River Hadua near village Kharod of Baramba block in Cuttack
District of State of Odisha. (EPC CONTRACT)

Authority :- GOVERNMENT OF ODISHA DEPARTMENT OF WATER RESOURCES

Name of the Agency:- M/s PES-BEKEM (JV).

Aggrement No:- EPC-01/2022-23, dated 23.12.2022

Scheduled Completion date: 24-06-2025

MONTHLY PROGRESS REPORT -May-2024.


EXECUTIVE SUMMARY
The project is proposed to be implemented on Engineering, Procurement and
Construction (EPC) contract .Scope of work as envisaged include:  a) The main
components of this Gravity Dam & Spillway will be a) Dam & Spillway with it’s
accessories and appurtenant including energy dissipation arrangement, piers and
abutment with guide wall (b) Head regulator, Construction/Under sluices, Penstock
of power house, Drainage gallery, inspection gallery, Audit, drainage arrangement,
ventilation arrangement, curtain grouting & drainage hole in the drainage gallery,
elevator, Construction/ Expansion joint, (c) Mechanical works like mechanical gate
work (radial) for spillway, vertical gate work for head regulator, penstock of the
power house, stop logs, trash rack including hoist and hoist supporting structure,
gantry crane and lifting beam, (d) Afflux bundh guide wall, with protection works and
bank protection work of the river in the upstream up to required length (e) Power
connectivity from the existing 1X250KVA Sub- Station each on each side of proposed
Dam to each component of the dam, allied machineries and facilities for gate
operations and lighting of the sites, backup power arrangement, electrical, electro-
mechanical works, Power connectivity works (f) A double storied building for
watchman & operator shed at the Dam & Spillway site with Ground Floor of 300
SQM & First Floor of 250 SQM built up area with boundary wall ,all sanitary &
sewerage system, Electrification power backup inverter, construction of internal
Road to the Dam & Spillway from the existing road near the dam site, peripheral;
development including land scaping, plantation ,beautification of the toe of non
overflow section, approach road side to the dam & sub Division office campus at
Kharod, and other ancillary works including Survey, investigation, sub-soil foundation
exploration for Planning, fixing alignment , designing and Engineering of Dam &
Spillway as per Technical specification, relevant I.S. Codes, CWC Manuals, Circulars
issued by department from time to time etc

SALIENT FEATURES OF THE WORK.

Employer GOVERNMENT OF ODISHA DEPARTMENT OF WATER


RESOURCES,SUPERINTEDNING ENGINEER,HADUA IRRIGATION
DIVISION,NARASINGHPUR.Cuttack Dist, Odisha
EPC – Contractor PES-BEKEM(JV)
Contract Agreement No. EPC-01/2022-23, dated 23.12.2022
Agreement Cost Part-1 work- 221,43,00,000.00
Part-2 O&M- 3,35,00,000.00
Total Agmt Value- 224,78,00,00.000
River Basin Mahanadi
A. Longitude 85 ͦ-15'-30"
B. Latitude 20 ͦ-27'-50"
Catchment area 170 Sqm
FRL 126.000 M
Live storage( MCM) 32.7318
Capacity at FRL ( MCM) 33.1466
Type of Dam Gravity Concrete Dam
Length of Dam at top 387M
Top width(m 6.00 M
Maximum height above G.L 43.825 M
Deepest Bed level 84.571 M
Type of Spillway Ogee
Type of Energy Dissipation Sky Jump Bucket
Length of Spillway 62 meters
Crest level 118.000
No of gates 5 No’s
Type o Gates Radial Gate
Sluices 1 river Sluices (Construction Sluices) & 1 Irrigation and Powe
combine Sluices
Size of gate (MxM) 11m x 8 m
Design Discharge 2033 Cumec

Progress of Pre-Construction Activities:

The pre-construction activities like Mobilization of plants and equipment’s, construction of


camps, construction of laboratories, erection and commissioning of plants were completed at site.

Survey Works: -

Marking of axis line of dam, checking of, benchmarks are completed.

Source of Material:-

Cement:- JSW Cement, Dlamia- Approved By authority

Steel: SAIL- Approved by authority.

Status of Design & Drawings.

Description Status Remarks


Slno
1 Non Over Flow Section Approved
2 Gallery and Audit Approved
3 Spillway Section Submitted Approval pending at
Ce Deisgns ,
4 Creast Reinforcement Submitted Approval Pending at
CE Designs
5 Bucket Details and Reinforcement Submitted Approval Pending at
CE Designs
6 Intermediate Pier Submitted Approval Pending at
CE Designs
7 End Pier Submitted Approval Pending at
CE Designs
8 Wing wall & Return Wall Submitted Approval Pending at
CE Designs
9 Sum Well Approved
10 Lift Approved
11 Spillway Gate Drawings and Sulices Submitted Approval Pending at
Gated Drawings CE Designs

You might also like