PROJECT MANAGEMENT

Project : STRUCTURE BALIWOOD III LOT. 2 - 7


CV Eka Cipta Guna
Komplek Graha Indah Blok F2 No. 13 Location : JL. BABADAN, PERERENAN, KEC. MENGWI
Kota Balikpapan - 76126 Client : BREIG PROPERTY INVESTMENT
Telp. +62 812 8484 8452 Contractor : CV. EKA CIPTA GUNA
Email : cv.ekaciptaguna@gmail.com

No : 1 Day : 5 Date : 02-Mar-24


Location : PERERENAN - BALI Work Hours : 9 Hours

1. Work Performed Today :

Work Status (X) Work Results (X)


No Kinds and Job Descriptions Details
Done Not Yet Good Enough Bad
1 On Progress Baliwood office construction X X Not Yet
2 On Progress finishing install ceramic tiles on front gate door lot 2 X X Finished
3 On Progress rebar fabrication for beam on little villa lot 4 X X Not Yet
4 On Progress install plywood formwork for little villa roof lot 4 X X Finished
5 On Progress finishing wall plester for toilet wall on lot 3 X X Not Yet
6 On Progress plestering left area of lot 5 X X Not Yet
7 On Progress installing sloof rebar on lot 7 X X Not Yet
8 On progress finished installation of 2nd floor bathroom window on lot 2 X X Finished
9 On progress installing ceramic tiles on 2nd floor lot 3 X X Finished
10 On Progress install wooden grill on front area lot 2 X X Finished
11 On Progress cleaning pool area on lot 2 X X Finished
12 On Progress installing MEP equipment on pool area lot 2 X X Finished
13 On Progress steel staircase ironwork X X Not Yet
14 On Progress finishing jacuzzi stair on lot 2 X X Not Yet
15 On Progress installing plumbing equipment on pump room jacuzzi X X Finished
lot 2
2. Total Labor

Workers
Type of Work
Mechanical

Plumbing
Electrical

Exterior
Interior
Painter
No Notes
Steel
Staff

Civil

Skill Level

1 Project Manager 1 1
2 Site Manager -
3 Site Engineering -
4 Supervisor 1 1
5 Surveyor -
6 Engineering Administration -
7 Drafter MEP -
8 Foreman - 1 1
9 Workers - 28 2 2 3 35
- -
-
Total Amount - 2 29 - - 2 - - 2 3 38 Persons

3. Materials Received in The Field 4. Tools Used

Kinds of Materials Quantity Unit Kinds of Tools Quantity Condition

Cement 50 Zak 1 Mixer 2 Good


Gypsum 10 Pcs 2 Cutting Wheel 2 Good
Compound 1 Zak 3 Grinder M0900B 2 Good
Roofing Bolt 12 x 50 Blue 20 Pcs 4 Water Punp Machine 1 Good
Leak Proof Glue 1 Pcs 5 E00119 Electric Katrol HOISTPA-500 1 Good
6 Concrete Vibrator 2 Good

5. Weather
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Sunny PROBLEM & COUNTER :


1
Rain 2
3
Proposed by, Approved by,
CV. EKA CIPTA GUNA BREIG PROPERTY INVESTMENT
Name : Name : Artem Sitnikov
Position : Position : Project Manager
Signature : Signature :
PROJECT MANAGEMENT WORK PROGRESS PHOTOS
Project : BALIWOOD III - PRERENAN No : 5
Location : JL. BABADAN - PERERENAN Monthly : 9
: BADUNG REGENCY - BALI Period : 02-Mar-24
Client : BREIG PROPERTY INVESTMENT
Contractor : CV. EKA CIPTA GUNA

On Progress Baliwood office construction On Progress finishing install ceramic tiles on front gate door lot 2 On Progress install plywood formwork for little villa roof lot 4

On Progress install wooden grill on front area lot 2 On Progress installing MEP equipment on pool area lot 2 On Progress steel staircase ironwork
CV. EKA CIPTA GUNA BREIG PROPERTY INVESTMENT
Proposed by, Approved by,
Nama : Reza Indawan Yulianto Nama : Artem Sitnikov
Tanda Tangan : Tanda Tangan :