PROJECT BALIWOOD DAILY REPORT 29.02.24
PROJECT BALIWOOD DAILY REPORT 29.02.24
2. Total Labor
Workers
Type of Work
Mechanical
Electrical
Plumbing
Exterior
Interior
Painter
No Notes
Steel
Staff
Civil
Skill Level
1 Project Manager 1 1
2 Site Manager -
3 Site Engineering -
4 Supervisor 1 1
5 Surveyor -
6 Engineering Administration 1 1
7 Drafter MEP -
8 Foreman - 1 1
9 Workers - 28 2 4 3 3 40
- -
-
Total Amount - 3 29 - - 2 4 3 - 3 44 Persons
1 Mixer 2 Good
2 Cutting Wheel 2 Good
3 Grinder M0900B 2 Good
4 Water Punp Machine 1 Good
5 E00119 Electric Katrol HOISTPA-500 1 Good
6 Concrete Vibrator 2 Good
5. Weather
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
On Progress install floor tiles in floor area 2, lot 3 On progress Plastering the exterior side walls of lot 4 On Progress steel staircase ironwork
On Progress finishing acian rear openingan on lot 2 On Progress Install ceramic tiles for the 3rd floor table area On Progress install aluminium and glass door on 2nd floor on lot 2