Site Test Form For (Line Diff.

Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
GENRAL INFORMATION:

RELAY ANSI NO. 87L-1 RATED CURRENT 1.0 A

RELAY FUNCTION Line Differential protection RATED VOLTAGE 100-120 V AC

RELAY MAKE AREVA AUX SUPPLY 48-250 V DC

MODEL / STYLE MICPMP543…………….. REF. DRAWING


S. NO. S/W REF MICOM_S1

Scope of functions checked


NO FUNCTIONS Checked NO FUNCTIONS Checked
1 Physical /Visual Inspection
2 Electrical check:
3 Measurements
4 Differential protection:
5 Distance protection:
6 DEF

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 1 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
1. PHYSICAL /VISUAL INSPECTION: (Tick if verified)

Item Description Checked

1 Inspect for physical damage / defects O.K

2 Check Name Plate information for correctness O.K

3 Check for proper installation and mounting O.K

4 Verify tightness of external wiring O.K

2. ELECTRICAL CHECKS: (Tick if verified)

Item Description Checked

1 Wiring check (Type-Cross Section – Colour – Label) as per Ref (approved) Drawing O.K

2 Auxiliary power supply checked for rating and polarity O.K

3 Casing Earthing checked O.K

4 Test Switch checked for correct function O.K

5 LED's operation checked O.K

6 BI’s Binary Inputs checked O.K

7 BO's Binary Outputs checked O.K

3- MEASUREMENTS:

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 2 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
- C.T Ratio 800/1 A

- V.T Ratio: 690000/115 V

- Frequency: 60 HZ

Injected Values Expected Values Measured Values


PARAMETER
SECONDARY PRIMARY SECONDARY PRIMARY SECONDARY PRIMARY
U1 66.39 V 39.84KV 66.39 V 39.84KV 65.79 V 39.34 KV
U2 66.39 V 39.84KV 66.39 V 39.84K 65.73 V 39.36 KV
V
U3 66.39 V 39.84KV 66.39 V 39.84K 65.42 V 39.33 KV
V
U1-U2 115 V 69.00 KV - 69.00 - 68.21 KV
KV
U2-U3 115 V 69.00 KV - 69.00 - 68.19 KV
KV
U1-U3 115 V 69.00 KV - 69.00 - 68.20 KV
KV
IA 1.00 A 800 A 1.0 A 800 A 0.983 A 788.9 A
IB 1.00 A 800 A 1.0 A 800 A 0.986 A 787.6 A
IC 1.00 A 800 A 1.0 A 800 A 0.982 A 788.2 A
Im n/a n/a --- --- --- ---
In n/a n/a --- --- --- ---

Accuracy

 The measurement accuracy of the relay is ± 1 %

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 3 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1

4-DIFFERENTIAL PROTECTION FUNCTION:

I- Current Differential operation

1-OPERATION MEASURED VALUE FOR DIFF.

Measured current
Phase (A)
Inj.
Current (A) PH DIFF BIAS
Exp. Meas. Exp. Meas. Exp. Meas.
A 1.0 1.0 1.0 0.5
B 1.0
C 1.0

Where
 ‫׀‬IDiff‫׀ = ׀‬Ia+Ib+Ic‫׀‬
 ‫׀‬IBias0.5 = ‫׀ ( ׀‬Ia‫ ׀‬+ ‫׀‬Ib‫׀‬+ ‫׀‬Ic‫)׀‬

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 4 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1

2-pick up & time

1. Disabled all the other relay protection functions


2. also set the relay to Loopback moel to isolate it from the remote end
3. Phase A:
4. Phase B:
5. Phase C:

Meas. time @ 2 Meas. time


PHASE Setting Pick - Up Drop Off Is @ 4 Is
(ms) (ms)
A 0.2
B 0.2
C 0.2

Accuracy:

 With IDMT/Definite time delay the expecting operating time is typically with in ± 5%
 For instantaneous fault Measured Time ≤ 35 ms for 60 Hz

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 5 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
II- Current Differential Bias Characteristic

1. Disabled all the other relay protection functions


2. also set the relay to Loopback moel to isolate it from the remote end
3. Ibias = Ia , Idiff= Ib & Ia> Ib

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 6 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 7 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
I-Lower Slope

 Assign three different led to give phase segregated trip information TripA,B&C
 Assumption Is1= 0.2pu, K1=30% , Is2= 2.0 pu & ensure Ibias < IS2
 Make sure that the relay is on loopback mode by

1. Setting cell (0f12 Test loopback) to External and applying either loopback fiber on the
relay or loopback is selected on the P590
2. Alternatively setting cell (0f12 Test loopback) to External

 Give bias current Ia = 1.0 p.u (according to relay rated current ) thus the relay will trip with
phase A
 When Current in A is established slowly increase the current in the B phase from zero until
phase B trips
 Record the phase B current value and check that is corresponds to the

Bias Current
Differential Current
Phase Magnitude Phase Magnitude
A 1 PU B 0.25PU± 10%

The formula below can be used:


 B phase operate current is 0.5{ Is1+ (IBAIS ×K1)}PU ± 10%

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 8 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1
II-Upper Slope

 Repeat the above test with Bias current set in the A phase to be 3 PU
 Give bias current Ia = 3.0 p.u (according to relay rated current ) thus the relay will trip with
phase A
 When Current in A is established slowly increase the current in the B phase from zero until
phase B trips
 Record the phase B current value and check that is corresponds to the

Bias Current
Differential Current
Phase Magnitude Phase K2 Magnitude
A 3 PU B 150% 1.15 PU± 10%
100% 0.9 PU± 10%

The formula below can be used:


 B phase operate current is 0.5{ (IBAIS ×K2) - {(K2- K1) × Is2} + IS1 }PU ± 20%

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 9 of 1
Site Test Form For (Line Diff. Relay MICOMP543)
Customer SEC-ERB Contract #
Project IBN KHLADOON BSP Job # I-
Location DAMMAM Equipment Tag
LINE#1 SET#1

I Bias I DIFF
Slope Remarks
PU EXP MEASURED
Lower 1 PU
Upper 3 PU

III- LOOPBACK Test:

Depend on the Communication type


1. Direct Fiber optic Cable

 Set cell ( 0F12 test loopback ) to External


 Using A length of fiber optic cable with ST connector at each end
 Connect the channel 1 transmit(Tx) and Channel 1 receive (Rx) ports on the rear
of the relay together
 The relay respond as if it is connected to remote relay with current at the remote
end equal to and in phase with current injected at the local end
 Loop back alarm will be active
 Check channel status ,propagation delays and communication statistics in
(measurement4)

2. Communication using P591 interface unit


3. Communication using P592 interface unit
4. Communication using P593 interface unit
5. Communication using P594 interface unit

Remarks Relay Tested Based on Default Setting & Default Configurations


Eqpt FREJA300 Eqpt FLUKE
Test Inst. Used ID#: B90-E050 F ID#: B90-E490F
Name: ADEL IBRAHIM Name:
Tested By Date: Witnessed By Date:
Signature: Signature:
Page 10 of 1