Task No. Task No. of Days Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
A. General Works
1 Site Inspection 1
2 Transporting of Necessary Equipments & Workers 4
B. Earthworks
3 Demolition & Clearing of Land 5
4 Staking Out 1
5 Excavation Process for Footings 15
7 Backfilling & Compacting of Footings 4
C. Concrete Works
6.1 Formation of Rebars for Footings 7
6.2 Installation of Rebar Works & Formworks for Footings 12
6.3 Concreting of Footings 14
8.1 Formation of Rebars for Columns 9
8.2 Installation of Rebar Works & Formworks for Columns 10
8.3 Concreting of Columns 12
9.1 Formation of Rebars for Slab 3
9.2 Installation of Rebar Works & Formworks for Slab 14
9.3 Concreting of Slab 14
10.1 Formation of Rebars for Beams 12
10.2 Installation of Rebar Works & Formworks for Beams 15
10.3 Concreting of Beams 13
11.1 Formation of Rebars for Stairs 3
11.2 Installation of Rebar Works & Formworks for Stairs 6
11.3 Concreting of Stairs 7
D. Other Works
12 Masonry Works 23
13 Roofing Works 14
14 Electrical Works 4
15 Plumbing Works 4
16 Painting 6
17 Installation of Fixtures and Appliances 3
18 Cleaning & Clearing of Unecessary Equipments 2
19 Final Inspection 1