Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Project Time Table (w/ 6 Days of Work a Week)

Task No. Task No. of Days Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
A. General Works
1 Site Inspection 1
2 Transporting of Necessary Equipments & Workers 4
B. Earthworks
3 Demolition & Clearing of Land 5
4 Staking Out 1
5 Excavation Process for Footings 15
7 Backfilling & Compacting of Footings 4
C. Concrete Works
6.1 Formation of Rebars for Footings 7
6.2 Installation of Rebar Works & Formworks for Footings 12
6.3 Concreting of Footings 14
8.1 Formation of Rebars for Columns 9
8.2 Installation of Rebar Works & Formworks for Columns 10
8.3 Concreting of Columns 12
9.1 Formation of Rebars for Slab 3
9.2 Installation of Rebar Works & Formworks for Slab 14
9.3 Concreting of Slab 14
10.1 Formation of Rebars for Beams 12
10.2 Installation of Rebar Works & Formworks for Beams 15
10.3 Concreting of Beams 13
11.1 Formation of Rebars for Stairs 3
11.2 Installation of Rebar Works & Formworks for Stairs 6
11.3 Concreting of Stairs 7
D. Other Works
12 Masonry Works 23
13 Roofing Works 14
14 Electrical Works 4
15 Plumbing Works 4
16 Painting 6
17 Installation of Fixtures and Appliances 3
18 Cleaning & Clearing of Unecessary Equipments 2
19 Final Inspection 1
Project Time Table (w/ 6 Days of Work a Week)
Task No. Task No. of Days Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
A. General Works
1 Site Inspection 1
2 Transporting of Necessary Equipments & Workers 4
B. Earthworks
3 Demolition & Clearing of Land 5
4 Staking Out 1
5 Excavation Process for Footings 15
7 Backfilling & Compacting of Footings 4
C. Concrete Works
6.1 Formation of Rebars for Footings 7
6.2 Installation of Rebar Works & Formworks for Footings 12
6.3 Concreting of Footings 14
8.1 Formation of Rebars for Columns 9
8.2 Installation of Rebar Works & Formworks for Columns 10
8.3 Concreting of Columns 12
9.1 Formation of Rebars for Slab 3
9.2 Installation of Rebar Works & Formworks for Slab 14
9.3 Concreting of Slab 14
10.1 Formation of Rebars for Beams 12
10.2 Installation of Rebar Works & Formworks for Beams 15
10.3 Concreting of Beams 13
11.1 Formation of Rebars for Stairs 3
11.2 Installation of Rebar Works & Formworks for Stairs 6
11.3 Concreting of Stairs 7
D. Other Works
12 Masonry Works 23
13 Roofing Works 14
14 Electrical Works 4
15 Plumbing Works 4
16 Painting 6
17 Installation of Fixtures and Appliances 3
18 Cleaning & Clearing of Unecessary Equipments 2
19 Final Inspection 1
Project Time Table (w/ 6 Days of Work a Week)
Task No. Task No. of Days Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
A. General Works
1 Site Inspection 1
2 Transporting of Necessary Equipments & Workers 4
B. Earthworks
3 Demolition & Clearing of Land 5
4 Staking Out 1
5 Excavation Process for Footings 15
7 Backfilling & Compacting of Footings 4
C. Concrete Works
6.1 Formation of Rebars for Footings 7
6.2 Installation of Rebar Works & Formworks for Footings 12
6.3 Concreting of Footings 14
8.1 Formation of Rebars for Columns 9
8.2 Installation of Rebar Works & Formworks for Columns 10
8.3 Concreting of Columns 12
9.1 Formation of Rebars for Slab 3
9.2 Installation of Rebar Works & Formworks for Slab 14
9.3 Concreting of Slab 14
10.1 Formation of Rebars for Beams 12
10.2 Installation of Rebar Works & Formworks for Beams 15
10.3 Concreting of Beams 13
11.1 Formation of Rebars for Stairs 3
11.2 Installation of Rebar Works & Formworks for Stairs 6
11.3 Concreting of Stairs 7
D. Other Works
12 Masonry Works 23
13 Roofing Works 14
14 Electrical Works 4
15 Plumbing Works 4
16 Painting 6
17 Installation of Fixtures and Appliances 3
18 Cleaning & Clearing of Unecessary Equipments 2
19 Final Inspection 1
Project Time Table (w/ 6 Days of Work a Week)
Task No. Task No. of Days
Week 31 Week 32 Week 33 Week 34 Week 35 Week 36 Week 37 Week 38 Week 39 Week 40
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
A. General Works
1 Site Inspection 1
2 Transporting of 4Necessary Equipments & Workers
B. Earthworks
3 Demolition & Clearing
5 of Land
4 Staking Out 1
5 Excavation Process
# for Footings
7 Backfilling & Compacting
4 of Footings
C. Concrete Works
6.1 Formation of Rebars
7 for Footings
6.2 Installation of Rebar
# Works & Formworks for Footings
6.3 Concreting of Footings
#
8.1 Formation of Rebars
9 for Columns
8.2 Installation of Rebar
# Works & Formworks for Columns
8.3 Concreting of Columns
#
9.1 Formation of Rebars
3 for Slab
9.2 Installation of Rebar
# Works & Formworks for Slab
9.3 Concreting of Slab
#
10.1 Formation of Rebars
# for Beams
10.2 Installation of Rebar
# Works & Formworks for Beams
10.3 Concreting of Beams
#
11.1 Formation of Rebars
3 for Stairs
11.2 Installation of Rebar
6 Works & Formworks for Stairs
11.3 Concreting of Stairs
7
D. Other Works
12 Masonry Works#
13 Roofing Works #
14 Electrical Works4
15 Plumbing Works4
16 Painting 6
17 Installation of Fixtures
3 and Appliances
18 Cleaning & Clearing
2 of Unecessary Equipments
19 Final Inspection1

You might also like