SCHEDULE PROCESS Project start: 1-Jul-24

PROYEK RSUPT MAKASSAR Display week: 1


PENGERJAAN LANTAI 2 , 3 , 4 DAN 11

Jul 1, 2024 Jul 8, 2024 Jul 15, 2024 Jul 22, 2024 Jul 29, 2024 Aug 5, 2024 Aug 12, 2024 Aug 19, 2024

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PROCESS PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Terima approval shopdrawing dan spek material 0% 1-Jul-24 3-Jul-24

Pengadaan Material 0% 2-Jul-24 11-Jul-24

Pembuatan gambar produksi dan BOM 0% 6-Jul-24 11-Jul-24

BOM / Standard turun ke produksi 0% 8-Jul-24 13-Jul-24

Proses Produksi 0% 9-Jul-24 27-Jul-24

Pengiriman (2 kali) 0% 26-Jul-24 7-Aug-24

Perakitan 0% 2-Aug-24 16-Aug-24

Target Selesai 0% 16-Aug-24 17-Aug-24