Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

MANU/NL/0327/2024

IN THE NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI


Company Appeal (AT) (Insolvency) Nos. 742 of 2024 and 743 of 2024
Decided On: 08.05.2024
Vikram Babulal Sanghvi and Ors. Vs. State Bank of India
Hon'ble Judges/Coram:
Ashok Bhushan, J. (Chairperson) and Barun Mitra, Member (T)
Counsels:
For Appellant/Petitioner/Plaintiff: Keith Verghese, Advocate
ORDER
Ashok Bhushan, J. (Chairperson)
1 . These two Appeal(s) have been filed by the Personal Guarantors of the Corporate
Debtor, namely - Vikram Babulal Sanghvi and Naresh Babulal Sanghvi, challenging the
order of the Adjudicating Authority dated 27.02.2024, by which order the Applications
filed under Section 95, sub- section (1) of the Insolvency and Bankruptcy Code, 2016
(hereinafter referred to as the "Code") filed by the State Bank of India ("SBI") were
admitted.
2 . In Company Appeal (AT) (Insolvency) No. 742 of 2024, order under challenge is
order dated 27.02.2024 passed in CP(IB) No.100/ NCLT/ AHM/2021 and in Company
Appeal (AT) (Insolvency) No. 743 of 2024 has been filed against the order dated
27.02.2024 passed in CP(IB) No.92/ NCLT/ AHM/2021, by which orders Application filed
by SBI in both the cases, under Section 95, sub-section (1) have been admitted. Both
the Appellant(s) were Personal Guarantors of the Corporate Debtor - Sanghvi Forging &
Engineering Limited and the SBI having filed Applications under Section 95 against both
the Personal Guarantors, it shall be sufficient to refer to the pleading and facts in
Company Appeal (AT) (Insolvency) No. 742 of 2024 for deciding these two Appeal(s).
3. Brief facts of the case are:
(i) A working Capital Term Loan Consortium Agreement was executed between
the Consortium bank consisting of the Respondent with Bank of Baroda and the
Corporate Debtor. An Agreement was also entered into between the Personal
Guarantor with Consortium Bank. Guarantee for repayment of various financial
facilities extended to Sanghvi Forging & Engineering Limited was provided by
the Appellant.
(ii) The Corporate Debtor having defaulted in payment of debt, Section 7
Application was filed by the Financial Creditor, which Application was admitted
by order dated 30.08.2019 passed by Adjudicating Authority.
(iii) On 15.01.2019, recall notice was issued by the Financial Creditor invoking
the Personal Guarantee of the Appellant. On 13.04.2021, Statutory Demand
notice was issued by the SBI to the Appellant after invoking the personal
guarantee.

14-06-2024 (Page 1 of 8) www.manupatra.com Ms. Jyoti Singh


(iv) In Corporate Insolvency Resolution Process ("CIRP") of the Corporate
Debtor, the Adjudicating Authority vide order dated 26.04.2021 approved the
Resolution Plan of one Bharat Forge Ltd.
(v) Applications under Section 95 was filed by the Financial Creditor against the
Personal Guarantors being CP(IB) No.100/ NCLT/ AHM/2021 (in Company
Appeal (AT) (Insolvency) No. 742 of 2024) and CP(IB) No.92/ NCLT/ AHM/2021
(in Company Appeal (AT) (Insolvency) No. 743 of 2024), in which Applications,
RP was appointed. The RP filed its Report recommending the admission of the
Applications. The Personal Guarantors filed affidavit in reply, raising various
objections. The Adjudicating Authority heard the parties and by the impugned
order dated 27.02.2024 admitted the Applications.
(vi) Aggrieved by which order, these Appeals have been filed.
4 . The learned Counsel for the Appellant(s) challenging the order dated 27.02.2024,
admitting Section 95 Applications, contends that Adjudicating Authority committed error
in admitting Section 95 Applications, whereas after approval of the Resolution Plan, the
entire debt of the Corporate Debtor stood assigned to a Special Purpose Vehicle ("SPV")
(M/s BF Industrial Solutions Ltd.) and in view of the assignment of entire debt of the
Corporate Debtor, personal guarantees of the Appellant(s) could not be enforced. It is
submitted that under the Resolution Plan, personal guarantees are retained by the
Financial Creditor, whereas, entire debt of the Corporate Debtor has been assigned to
the SPV, in such circumstances, personal guarantees could not be enforced by the
Financial Creditor. The Appellant in his submission has relied on judgment of Delhi High
Court in Vineet Saraf vs. Rural Electrification Corporation Ltd. - MANU/DE/4669/2023
and judgment of High Court of Australia in Hutchens v. Deauville Investments Pty Ltd. -
MANU/AUSH/0084/1986 : 68 Australian Law Report 367, where it was held that on
assignment of entire debt, the guarantees could not be enforced, which judgment has
not been considered by the Adjudicating Authority.
5. We have considered the submissions of learned Counsel for the Appellant and have
perused the record.
6 . The Company Petition filed under Rule 7(2) of the Insolvency and Bankruptcy
(Application to Adjudicating Authority for Insolvency Resolution Process for Personal
Guarantors to Corporate Debtor) Rules, 2019 has been brought on record by the
Appellant. In Part-III of the Application, particulars of debt has been given. In Column-1
of Part-III, it is clearly contemplated that in the event of successful implementation of
the Resolution Plan approved by the Adjudicating Authority, the claim of Financial
Creditor will be reduced by the amount received from the Resolution Applicant. Part-III,
Column-1 and Column-2 are as follows:

14-06-2024 (Page 2 of 8) www.manupatra.com Ms. Jyoti Singh


7 . From the pleadings in the Appeal, it is clear that in the Appeal itself, the Appellant
quoted the relevant provisions of approved Resolution Plan. Clause 36 of the approved
Resolution Plan as extracted at page-14 of the Appeal is as follows:
"36. paragraph No. 7.1 of Schedule 2 (Implementation Provisions) as contained
in the Resolution Plan is hereby deleted and replaced with the following new
paragraph 7. 1:
7.1 On the Payment Date after completion of Step 6, the dues owed to the
Secured Financial Creditors by the Corporate Debtor (ie the Total Secured Debt)
shall be acquired and purchased by the Acquisition SPV along with all Relation
rights (save and except the Excluded Guarantees) from the Secured Financial
Creditors by paying them their respective portions of the Debt Acquisition

14-06-2024 (Page 3 of 8) www.manupatra.com Ms. Jyoti Singh


Amount. The Secured Financial Creditors shall execute an assignment deed in a
form and manner agreed between the Resolution Applicant and the Secured
Financial Creditors, for the Irrevocable and unconditional assignment of the
Total Secured Debt and Related Rights (save and except the Excluded
Guarantees) in favour of the Acquisition SPV. It is clarified that notwithstanding
anything to the contrary under the Plan, the Excluded Guarantees shall not be
acquired under this Step 7 by the Acquisition SPV and the Secured Financial
Creditors, in whose favour or for whose benefit such Excluded Guarantees have
been issued, shall continue to remain entitled to such Excluded Guarantees
including to invoke and enforce such Excluded Guarantees."
8. It is further submitted that as per the Resolution Plan, assignment agreement dated
28.06.2021 was executed in favour of SPV, i.e. M/s. BF Industrial Solution Ltd. From
the Clause 36 of the Resolution Plan, as extracted by the Appellant, it is clear that
guarantees has been excluded from assignment and that guarantees shall continue to
remain with the Financial Creditor, which can be invoked and enforced. The submission
of the Appellant that since the entire debt has been assigned to SPV, personal
guarantees against the Appellant could not have been invoked, has been considered and
rejected by the Adjudicating Authority by the impugned order. The Adjudicating
Authority in paragraph 13, 14, and 17 observed following:
"13. On perusal of the application and documents annexed with it, it is found
that the Resolution Plan of the CD was approved on 26.04.2021. As per the plan
the entire debt of the CD was acquired by SRA but how much amount received
by the applicant pursuant to approval of the resolution was not mentioned in
the application. Therefore, this Tribunal has listed this matter for clarification
on 24.01.2024. Pursuant to the order of this Tribunal RP filed an Additional
Affidavit clarifying the above points on 01.02.2024. It is stated in the affidavit
that Total Amount of Rs. 46,71,99,997/- has been received by the present
applicant pursuant to approval of resolution plan. Therefore, amount claimed to
be in default will be reduced by Rs. 46,71,99,997/-.
14. It is admitted fact that the Resolution Plan of CD was approved and the
entire debt of the Corporate Debtor has been taken over by Successful
Resolution Applicant but the guarantee given by the promoters has not been
assigned to SRA. The personal guarantor thereby has not been freed of his
guarantee for the debt payable. It is noted under section 128 of Indian Contract
Act, 1872 that when a default is committed the Principal Borrower and Surety
are jointly and severally liable to Creditor and Creditor has the right to recover
its dues from either of them or from both of them simultaneously.
17. The Hon'ble Supreme Court in its judgment in Lalit Kumar Jain V Union of
India & Ors. held that the release or discharge of a principal borrower from the
debt owned by it to creditor by an involuntary process, i.e. by operation of law,
or due to liquidation or insolvency proceedings, does not absolve the surety I
guarantor of his or her liability, which arises out of an independent contract."
9. The judgment of the Hon'ble Supreme Court in Lalit Kumar Jain vs. Union of India &
Ors. - MANU/SC/0352/2021 : 2021:INSC:297 : (2021) 9 SCC 321 has categorically laid
down that approval of Resolution Plan does not ipso facto discharge the liabilities of
Personal Guarantors. In paragraph 126 of the judgment, following has been observed:
"126. For the foregoing reasons, it is held that the impugned notification is

14-06-2024 (Page 4 of 8) www.manupatra.com Ms. Jyoti Singh


legal and valid. It is also held that approval of a resolution plan relating to a
corporate debtor does not operate so as to discharge the liabilities of personal
guarantors (to corporate debtors). The writ petitions, transferred cases and
transfer petitions are accordingly dismissed in the above terms, without order
on costs."
10. We may notice the judgment of this Tribunal in Company Appeal (AT) (Insolvency)
No. 975 of 2022 - UV Asset Reconstruction Company Limited vs. Electrosteel Castings
Limited, where one of the questions arose as to whether by approval of Resolution Plan,
entire debt of the Corporate Debtor stood extinguished and as a result there will be no
default. It was held by this Tribunal that even after approval of Resolution Plan,
recourse against third party can be resorted to and the approval of Resolution Plan,
does not extinguish the right of Financial Creditor to proceed against third party. This
Tribunal while considering the issue, laid down following in paragraph 50, 51 and 56:
"50. Law on extinguishment of claim against personal guarantor and third party
on approval of Resolution Plan has been settled by Hon'ble Supreme Court in its
judgment in Lalit Kumar Jain vs. Union of India and Ors. -
MANU/SC/0352/2021 : 2021:INSC:297 : (2021) 9 SCC 321, where the Hon'ble
Supreme Court held that approval of resolution plan does not ipso facto
discharge a personal guarantor (of a Corporate Debtor) of her or his liabilities
under the contract of guarantee. In paragraph 126 the Hon'ble Supreme Court
held following:
"126. For the foregoing reasons, it is held that the impugned notification is
legal and valid. It is also held that approval of a resolution plan relating to a
corporate debtor does not operate so as to discharge the liabilities of personal
guarantors (to corporate debtors). The writ petitions, transferred cases and
transfer petitions are accordingly dismissed in the above terms, without order
on costs."
51. There cannot be any dispute to the proposition that after the approval of
the Resolution Plan, entire debt of the Corporate Debtor against the Financial
Creditor stand discharged and after approval of Resolution Plan, Financial
Creditor can have no further recourse against the Corporate Debtor. But the
question as to whether debt of personal guarantor or third party which arises
out of different contract shall also automatically extinguished after the approval
of Resolution Plan is a question to be answered in the present case. As noted
above, the law laid down by the Hon'ble Supreme Court is categorical that
approval of a Resolution Plan does not ipso facto discharge a personal
guarantor. We have to look into the Resolution Plan to find out as to whether
approval of Resolution Plan discharge guarantor or third parties or not. The
learned Senior Counsel for the Appellant has relied on Clause 3.2 of the
Resolution Plan, under heading 'Proposal for Workmen and Financial Creditor'.
Sub-clause (ix) of Clause 3.2 has been relied, which clearly mentions that
Company shall stand discharged of any default, but on the same time it has
been mentioned that any rights against any third party shall not be
extinguished. It is relevant to extract following relevant part of sub-clause (ix):
"... Furthermore, the Company shall stand discharged of any default or event of
default under any loan documents or other financing agreements or
arrangements (including any side letter, letter of comfort, letter of undertaking
etc.) and all rights/ remedies of the creditors shall stand permanently

14-06-2024 (Page 5 of 8) www.manupatra.com Ms. Jyoti Singh


extinguished except any rights against any third party (including the Existing
Promoter) in relation to any portion of Unsustainable Debt secured or
guaranteed by third parties. Furthermore, it is hereby clarified that upon
approval of the Resolution Plan by the NCLT,...."
56. We, thus, are of the view that in view of Clause 3.2 (ix) of the Resolution
Plan, when read in the light of the CoC Meeting dated 29.03.2018, which throws
considerable light on the meaning and content of Clause 3.2 (ix), the
submission of the Respondent cannot be accepted that after approval of
Resolution Plan, the entire debt stand extinguished and no recourse can be
taken by the Financial Creditor against third party."
11. The learned Counsel for the Appellant(s) has placed reliance on the judgment of the
Hon'ble Delhi High Court in Vineet Saraf vs. Rural Electrification Corporation Ltd. -
MANU/DE/4669/2023. In the said case, a writ petition was filed for quashing the
demand notice dated 09.12.2022 issued by Respondent under Rule 7(1) of the
Insolvency and Bankruptcy (Application to Adjudicating Authority for Insolvency
Resolution Process for Personal Guarantors to Corporate Debtor) Rules, 2019. In
paragraph 1 and 2 of the judgment, facts have been noticed, which are to the following
effect:
"1. The petitioner has filed the instant writ petition seeking quashing of the
impugned Demand Notice dated 09.12.2022 issued by the respondent i.e.,
Rural Electrification Corporation Limited(hereinafter 'REC Ltd.') under Rule 7(1)
of the Insolvency and Bankruptcy (Application to Adjudicating Authority for
Insolvency Resolution Process for Personal Guarantors to Corporate Debtors)
Rules, 2019 (hereinafter 'Rules, 2019') invoking the personal guarantees of the
petitioner for the purported total outstanding debt of Rs. 1211,91,94,259
(hereinafter 'impugned demand notice').
2. As per the facts of the case, the petitioner stood as a personal guarantor for
a loan obtained by one FACOR Power Ltd. (hereinafter 'FPL') for a sum of Rs.
517.90 crores from the respondent i.e, REC Ltd. The loan agreement was dated
22.05.2009 (amended on 29.10.2010, 28.06.2013 and 12.11.2014). The deed
of personal guarantee was executed on 24.08.2009 (amended and restated on
29.10.2010, 21.06.2013 and 22.01.2015)."
12. In the writ petition, the petitioner has prayed for writ of prohibition, preventing the
Respondent from approaching the concerned NCLT under the provisions of the IBC and
the demand notice so issued was prayed to be quashed. In wake of the aforesaid
prayers in the writ petition, the Hon'ble Delhi High Court proceeded to examine various
submissions, including the law with regard to rights of the Guarantors. The Delhi High
Court ultimately took the view that prayers made in the writ petition cannot be granted
and NCLT must carefully examine law on assignment, contract of surety and the
applicability of judgment of Australia High Court in Hutchens. The Delhi High Court
rejected the submission of the Appellant that rights under Article 14 of the Constitution
of India has been violated. Ultimately, Delhi High Court dismissed the writ petition and
laid down following in paragraph 160 to 163:
"160. It is not the case that the reliefs prayed for cannot be granted by the
concerned NCLT. The petitioner's claim of the guarantor getting a right to be
heard at a belated stage, is not sufficient to entertain the present petition. The
legislature, in its wisdom, thought it fit to give the right of hearing at belated

14-06-2024 (Page 6 of 8) www.manupatra.com Ms. Jyoti Singh


stage. Indeed, if in the present case the petition is entertained, it would subvert
the procedure laid down under the IBC. The respondent in turn would be denied
the opportunity to present their case before the concerned NCLT.
1 6 1 . This court is, therefore, of the opinion that the present writ petition
deserves to be dismissed. Ordered accordingly. Pending application also stands
dismissed.
1 6 2 . The concerned NCLT may make a decision upon the submissions
advanced by the petitioner and the respondent on its own merits.
163. All observations on the merits of the case shall be considered as prima
facie and the competent court/Tribunal is at liberty to deal with the issues on
merits."
13. The judgment of the Delhi High Court itself makes it clear that Delhi High Court was
only of prima facie opinion and left it to be dealt with by the concerned Tribunal on
merits. We, thus, are of the view that judgment of the Delhi High Court in Vineet Saraf
does not come to any aid in the present case.
1 4 . The learned Counsel for the Appellant(s) has submitted that the Appellant(s) in
their written submissions have also placed reliance on the judgment of Australian High
Court in Hutchens v. Deauville Investments Pty Ltd. - MANU/AUSH/0084/1986 : 68
Australian Law Report 367, which judgment has not been dealt with by the Adjudicating
Authority. The judgment of High Court of Australia in the above case arose out of action
brought by Respondent for possession of certain land registered under the Transfer of
Land Act 1958. The basis of the action was alleged default by Hutchens as under a
registered mortgage of the land. The facts of the case has been noticed in paragraph-1
of the judgment, which is as follows:
"1. This is an appeal by special leave from a judgment of the Full Court of the
Supreme Court of Victoria affirming the decision of a single judge dismissing an
appeal to him from an order made by a Master. The appellant is Kenneth Ruston
Hutchens ("Hutchens") who was the defendant in the Supreme Court in an
action brought by the respondent, Deauville Investments Pty. Ltd. ("Deauville"),
for possession of certain land registered under the Transfer of Land Act 1958
(Vict.). The basis of the action was alleged default by Hutchens as mortgagor
under a registered mortgage of the land. By his order, the Master gave the
respondent leave summarily to enter final judgment for possession of the land
and thereby precluded the matter going to trial."
15. The High Court of Australia took the view that facts are complicated and evidence is
unsatisfactory and the matter needs to be remitted for further pleading leading trial in
which any outstanding issues of fact may be resolved. In paragraph-2 of the judgment,
following observations were made:
"2. The facts are complicated and the evidence is unsatisfactory. Since, for the
reasons appearing hereunder, we consider that the appeal should be upheld and
that the matter should be remitted to the Supreme Court for further pleading
leading to a trial in which any outstanding issues of fact may be resolved, it is
desirable that we refrain from unnecessary canvassing of the incomplete
evidence at present before the Court. It is, however, necessary to indicate the
essential factual context within which the issues canvassed on the present
appeal arise for consideration. Subject to elucidation and correction by further

14-06-2024 (Page 7 of 8) www.manupatra.com Ms. Jyoti Singh


evidence at the trial, that factual context would appear to be as follows."
16. The High Court of Australia ultimately allowed the prayer, set-aside the judgment
and remitted the matter granting leave to amend the statement of claim. What has been
stated in paragraph-2 as extracted above, clearly indicates that High Court of Australia
left the issue to be considered after further pleadings. The High Court observed that it is
desirable that we refrain from unnecessary canvassing of the incomplete evidence at
present before the Court. The judgment of the High Court of Australia arose out of
action on account of default by mortgagor. We fail to see, how the judgment of
Australian High Court can be helpful to the Appellant(s) in the context of Resolution
Plan approved by the Adjudicating Authority under the IB Code and Regulations. Law
with regard to Resolution Plan and discharge of Personal Guarantors has been settled by
the Hon'ble Supreme Court in Lalit Kumar Jain (supra) and when the Resolution Plan
itself contained a clause retaining the right of invoking the personal guarantees, the
judgment of the High Court of Australia, in no manner help the Appellant(s) in the
present case.
1 7 . The Adjudicating Authority by the impugned order has admitted Section 95
Applications, upholding the initiation of proceeding under Section 95 by the SBI. The
Adjudicating Authority has rightly returned a finding that the Resolution Plan of
Corporate Debtor was approved and the entire debt of the Corporate Debtor has been
taken over by the Successful Resolution Applicant ("SRA"), but the guarantee given by
the Promoters has not been assigned to SRA. The observation of the Adjudicating
Authority has already been extracted above. The Adjudicating Authority also held that
Application was filed within limitation. The date of default mentioned in the Application
was 23.01.2019 and the petition under Section 95 was filed on 22.05.2021.
18. We, thus, do not find any error in the order of the Adjudicating Authority, admitting
Section 95 Applications by the impugned order. There is no merit in any of the
submissions of the learned Counsel for the Appellant(s). Both the Appeal(s) are
dismissed.
© Manupatra Information Solutions Pvt. Ltd.

14-06-2024 (Page 8 of 8) www.manupatra.com Ms. Jyoti Singh

You might also like