Method Statement

Screed Topping Works

INDEX

1.0 SCOPE

2.0 PURPOSE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITY

6.0 GENERAL REQUIREMENTS

6.1 MATERIAL

6.2 MANPOWER

6.3 EQUIPMENT

7.0 CONSTRUCTION PROGRAMME

8.0 PROCEDURE

8.1 GENERAL

8.2 WORKMANSHIP

8.3 CURING

9.0 HOUSE KEEPING

10.0 SAFETY

MS- Plaster Rendering Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 1 of 5
1.0 SCOPE
This method statement covers the detailed procedure to be followed for
screeds/topping operation.
This procedure shall be read in conjunction with contract specification wherever
applicable.

2.0 PURPOSE
The purpose of this procedure is to define how screeds/toppings shall be carried out
under controlled condition.

3.0 REFERENCES
Contract specification
Contract Drawings
Project Quality Plan

4.0 DEFINITIONS
QA/QC- Quality Assurance and Quality Control
ITP-Inspection and Test Plan
IR-Inspection Request
Engineer-Architectural and Engineering Consultants Representative

5.0 RESPONSIBILITY
Project Manager:
➢ The Project Manager is responsible for the implementation of Method
Statement.
➢ The Project Manager is responsible to carry out the work as per the Method
Statement, Specification and Approved Drawings.
➢ The Project Manager shall ensure that the key personnel are well aware of
the Specification and Method Statement.
➢ The Project Manager shall ensure that all resources like Manpower, Material
and Equipment are available to carry out the work as planned and without
any delay or confusions.
➢ The Project Manager shall ensure that the resources are available to carry out
the works as scheduled.
➢ The Project Manager shall ensure the implementation of ITP and Method
Statements etc.

MS- Plaster Rendering Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 2 of 5
➢ The Project Manager shall ensure that all the activities are proceeding by the
submission and approval of IR and Check list.
➢ The Project Manager shall ensure that all the approvals are available for the
safe movements of works.
➢ The Project Manager is responsible for the effective implementation of safety
procedures.
➢ The Project Manager shall ensure that all safety precaution is in place and
personnel on site are using the required protective equipment.

6.0GENERAL REQUIREMENTS

6.1 MATERIAL
As per Material submittals
6.2 MANPOWER
Manpower requirements such as Project manager, Foreman, skilled labor and
helper will be available depend upon the site requirements.
6.3 EQUIPMENT
➢ Air compressor
➢ Shovel
➢ Wire brush
➢ Concrete Pump
➢ Trowel
➢ Hand float, skip float or power float

7.0 CONSTRUCTION PROGRAMME


The works shall be carried out as per the approved sequence of program.

MS- Plaster Rendering Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 3 of 5
8.0 PROCEDURE

8.1 GENERAL
➢ All the related documents such as method statements, material approvals
etc. must be approved and available upon request.
➢ The surface of the sub-floor shall be thoroughly cleaned and prepared to
ensure a good bond.
➢ Ensure that the design mix has been approved by the Engineer.
➢ Free water shall be removed and cement slurry/bonding agent shall be
applied prior to screed.

8.2 WORKMANSHIP
➢ Pipes and conduits which are to be cast into screed/topping shall be
overlaid with a 450mm wide strip of steel fabric.
➢ Mix materials thoroughly to a uniform consistency and use while
sufficiently plastic for full compaction.
➢ Dense screeds and toppings shall be fully compacted by vibrating beam,
pan vibrator or hand as per the site condition.
➢ Joints shall be provided as per the ratio of length to breadth not more than
3:2.
➢ In screeds over expansion joints in base, the joints shall be filled with
bitumen impregnated board joint filler placed to full depth and finished
flush with surface.
➢ After completion of casting, enough number of workers must be available
for the finishing works, cleaning and protection.

8.3 CURING
➢ As soon as the screeds/toppings have set it shall be covered with polythene
sheeting and keep in position for required number of days as suggested by
the Engineer.
➢ Surface hardener and sealer shall be applied if needed as per the
manufacturer’s recommendations.

MS- Plaster Rendering Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 4 of 5
10.0 HOUSE KEEPING
All work places will be cleaned from waste materials and ensuring clean and healthy
work environment as well as maintain free access and egress in the event of
emergency.

11.0 SAFETY
All works shall be controlled as per the Safety procedures. Safety equipment will be
worn at all times.
Safety procedures are to be considered before, through and after the completion of
the work to avoid any possibility of danger to humans or the construction.

MS- Plaster Rendering Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 5 of 5