Method Statement

Ceramic Works
INDEX

1.0 SCOPE

2.0 PURPOSE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITY

6.0 GENERAL REQUIREMENTS

6.1 MATERIAL

6.2 MANPOWER

6.3 EQUIPMENT

7.0 CONSTRUCTION PROGRAMME

8.0 PROCEDURE

8.1 WALL FINISHES

8.1.1 PREPARATORY WORKS

8.1.2 WORKMANSHIP

8.2 FLOOR FINISHES

8.2.1 PREPARATORY WORKS

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 1 of 7
8.2.2 WORKMANSHIP

9.0 HOUSE KEEPING

10.0 SAFETY

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 2 of 7
1.0 SCOPE
This method statement covers the detailed procedure to be followed for laying of
Ceramic/Porcelain Tiles on floors and walls.
This procedure shall be read in conjunction with contract specification wherever
applicable.

2.0 PURPOSE
The purpose of this procedure is to define how tiling shall be carried out under
controlled condition.

3.0 REFERENCES
Contract specification
Contract Drawings
Project Quality Plan

4.0 DEFINITIONS
QA/QC- Quality Assurance and Quality Control.
ITP-Inspection and Test Plan.
IR-Inspection Request.
Engineer- Architectural & Engineering Consultants Representative.

5.0 RESPONSIBILITY
Project Manager:
➢ The Project Manager is responsible for the implementation of Method
Statement.
➢ The Project Manager is responsible to carry out the work as per the Method
Statement, Specification and Approved Drawings.
➢ The Project Manager shall ensure that the key personnel are well aware of the
Specification and Method Statement.
➢ The Project Manager shall ensure that all resources like Manpower, Material and
Equipment are available to carry out the work as planned and without any delay
or confusions.
➢ The Project Manager shall ensure that the resources are available to carry out
the works as scheduled.

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 3 of 7
➢ The Project Manager shall ensure the implementation of ITP and Method
Statements etc.
➢ The Project Manager shall ensure that all the activities are proceeding by the
submission and approval of IR and Check list.
➢ The Project Manager shall ensure that all the approvals are available for the safe
movements of works.
➢ The Project Manager is responsible for the effective implementation of safety
procedures.
➢ The Project Manager shall ensure that all safety precaution is in place and
personnel on site are using the required protective equipment.

6.0 GENERAL REQUIREMENTS

6.1 MATERIAL
As per the Material Submittals.
6.2 MANPOWER
Manpower requirements such as Project Manager, Foreman, skilled labor
and helper shall be available depend upon the site requirements.
6.3 EQUIPMENT
➢ Wooden Hammer
➢ Straight Edge
➢ Leveling Instruments
➢ Cutting Tool
➢ Measuring tape
➢ Spirit level
➢ Wire brush
➢ Sponge, Cloth, Brush and Trowel

7.0 CONSTRUCTION PROGRAMME


The works shall be carried out as per the approved sequence of program.

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 4 of 7
8.0 PROCEDURE

8.1 WALL FINISHES

8.1.1 PREPARATORY WORKS


 The surface to which tiles are to be fixed shall be thoroughly dry before
fixing commences and free from all defects.
 The areas to be tiled shall be brushed clean and all traces of grease, oil,
loose particle etc must be removed.
 Cordon off the working area to prevent unauthorized entry.
 Ensure that the laying of tiles shall be as per the direction and pattern
agreed with the Engineer.
 Before laying the tiles shall be thoroughly soaked in clean water and
drained so that no free moisture remains on the back of the tiles.
8.1.2 WORKMANSHIP
 Tiles shall be fixed to wall surfaces by bedding in the approved cement
sand mix or an approved adhesive.
 The tiles must be firmly placed into the mix/adhesive bed ensuring good
contact with a twisting motion.
 Tiles shall be laid with required spacing and spacers shall be used as per
the requirements.
 Excessive mix/adhesive shall be removed with a damp cloth before the
material has set.
 The vertical joints shall be maintained plumb for the entire true level and
plane by uniformly applied pressure.
 The external and internal angles and side edges of glazed wall tiling shall
be formed with angle beads.
 Joints in glazed wall tiles and fittings, after edges of tiles have been
thoroughly wet, shall be grouted with a plastic mix of neat white or
colored cement/approved grout.
 Grout/plastic mix of neat white or colored cement shall be applied to the
spaces between the tiles using a sponge or a small piece of the soft cloth.
 Work the mixture into the joints and around the edges.
 Surplus material shall be removed with a dry cloth.
 Movement joints shall be located as required and be carried through
backing to the structural wall, partially fill with strip and finish flush with
sealant to the manufacturer’s recommendations.
 Tiling shall be protected from heat and inclement weather until jointing
has completely set.

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 5 of 7
8.2 FLOOR FINISHES
8.2.1 PREPARATORY WORKS
 Ensure that cement screed has been provided and approved.
 Ensure that relevant approvals are in place.
 The areas of substrate to be tiled shall be brushed clean and the finished
floor level shall be established by means of dots.
 All traces of grease, oil and loose particles etc must be removed.
 Cordon off the working area to prevent unauthorized entry.
 Ensure that the laying of tiles shall be as per the direction and pattern
agreed with the Engineer.
 Before laying the tiles shall be thoroughly soaked in clean water and
drained so that no free moisture remains on the back of the tiles.
8.2.2 WORKMANSHIP
 The mortar for bedding the tiles shall be of approved thickness of 20 mm
and shall consists of 1 parts of cement to 3 parts of sand by volume
,mixed semi dry with only sufficient water added to give proper
consistency to spreading and compaction.
 The mix shall be spread to a thickness approximately 10 mm greater than
that actually required for the bed and shall be compacted by tamping and
drawing off to the required level.
 Slurry of cement sand shall be poured over the mix and dry tiles shall then
be laid on the slurry and beaten firmly into position with a wooden
hammer to ensure a true surface and contact between the tiles and
bedding is completed.
 Tiles shall be laid level or enough falls in wet areas as may be required.
 Particular care shall be taken in wet areas to prevent low spot and
pooling of water.
 When the installation has hardened sufficiently a thick grout of cement
mixed with a minimum amount of water/approved grout shall be
prepared and brushed over the floor until all the joints are thoroughly
filled.
 Surplus material shall be removed with a dry cloth.
 Movement joints shall be located as required and be carried through
backing to the structural wall, partially fill with strip and finish flush with
sealant to the manufacturer’s recommendations.
 The completed tile floor should be kept traffic avoided in the area.

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 6 of 7
9.0 HOUSE KEEPING
All work places will be cleaned from waste materials and ensuring clean and healthy
work environment as well as maintain free access and egress in the event of
emergency.

10.0 SAFETY
All works shall be controlled as per the Safety procedures. Safety equipment will be
worn at all times.
Safety procedures are to be considered before, through and after the completion of
the work to avoid any possibility of danger to humans or the construction.
Movement of vehicles should be controlled to avoid any confusion with any other
casual traffic.

MS- Tile Works Rev-00 Four O Two Interior Design


Implementation Works L.L.C Page 7 of 7