FIT OUT WORKS FOR 2B+ G + 3 FLOORS MAIN BUILDING, PARKING AREA,EXTERNAL LIGHTING,SERVICE BUILDING

SPECIFICATION 01 – GENERAL

When a failure of work covered by a guarantee has been rectified, the guarantee shall be
reinstated to operate for a period of time equal to that of the original guarantee to take
effect from the date of the acceptance of the rectified work.

The Contractor shall ensure that he obtains, for the benefit of the Employer, a 10 year
guarantee in respect of the performance of the roof waterproofing.

1.59 SPARE PARTS AND TOOLS

The Sub-Contractor shall provide as part of this Contract, all special tools required for
equipment maintenance and sufficient spare parts for each item of equipment to provide
maintenance for 400 days, all in accordance with there commendations of the
manufacturers of the equipment.

Note:

Completion certificate will not be issued before proving that adequate spare parts for
equipment installed are available with the services sub-contractor.

15 - SPARE PARTS AND TOOLS - A/C INSTALLATION

Spares for the A/C installation as included in the contract shall be delivered by the
Contractor before the Practical Completion Certificate is issued.

The following spare parts and tools shall be provided.


A DX SPLIT UNITS
1 Air Filter Element (One complete replacement)
2 Condenser Fan Motor (One No. of each size)
3 Evaporator Fan Motor (One No. of each size)
4 Evap. and Cond. Fan Bearing (One set of each size of fan)
5 Contactor for Comp. Motor (Four Nos)
6 Auxiliary Relay (Two No. of each type)
7 Overload relay for Comp, Motor (Two No. of each type)
8 Capacitor (One complete replacement if applicable)
9 Fuses (One complete replacement)
10 Remote control switch and Thermostat - for ceiling mounted units if any (One
No.)
11 Evap. Fan Belt (One complete replacement)
12 Expansion Valve, if any (One No.)
13 HP/LP Cutout (One No.)

B AIR HANDLING UNITS


1 Air Filter (One complete replacement)
2 Fan Bearing (One set for each size of AHU)
3 Fan Motor (One Motor of each size)
4 V. Belts (One set or each AHU)
5 Three way valve with modutrol motor and linkage if any (One No. of each size)
6 Modulating Thermostat (Three Nos)
7 Smoke Detectors (Three Nos)
8 Thermostat (R/A) (Three Nos)
9 Manometer (One No.)
10 Humidistat if installed in Plant (One No.)

30
FIT OUT WORKS FOR 2B+ G + 3 FLOORS MAIN BUILDING, PARKING AREA,EXTERNAL LIGHTING,SERVICE BUILDING

SPECIFICATION 01 – GENERAL

C CONTROL PANEL
1 Ammeter (One complete replacement)
2 Selector Switch (One complete replacement)
3 Indication Lamps (One complete replacement)
4 Power Fuses (One complete replacement)

D SPECIAL TOOLS
1 Pulley Puller (One No.)
2 Bearing Puller (One No.)
3 Comp. Stator Puller (One No.)

E HANDY TOOLS

The Contractor shall provide a complete set of handy tools for use of the routine
maintenance of the plants. Tools shall be provided in a tool box. Tools will
include:

Screw drivers, spanners, hammers, pliers, etc. as needed for the opening of
panels, tightening of bolts, etc.

F PUMPS

1 Pump Motor (One No.)


2 Pump Gland Packing where applicable, or mechanical seal (One complete
replacement for each pump)
3 Shaft Coupling (One of each size)
4 - Coupling Bushes (One set per pump)
- Pump Bearings (One set per pump)
- Pump Motor Bearings (One set per pump)

G GENERAL

Note: Quantities listed apply to the quantities listed in the Bill of Quantities.

1 Pipe flexible conns. (Two of each size)


2 Pressure gauges (Water) (One complete replacement)
3 Water Thermostat (One complete replacement)
4. Fuses for Fire Damper (One complete replacement)
5 Water strainer element (One complete replacement)
6 Test Probe with Pressure gauges for self (Two Nos.)
7 Self sealing (One complete replacement)

1.60 WORKMANSHIP

1.61 GENERALLY

The whole of the works shall be executed with only the best workmanship practices being
used throughout in accordance with the code of practice of each trade.