DEVELOPMENT OF NOOR CITY- CONSTRUCTION OF 207 RESIDENTIAL VILLAS

WEEKLY MEETING PRESENTATION (08-07-2024)


Table of Contents:

1- 207 Residential Villas shop drawings


and materials Status.
------------------------------------------------------
1.1- Materials Status.
1.2- Shop drawings Status :
1.2.1- Structural shop drawings Status.
1.2.2- Infrastructure and Roads shop drawings Status.
1.3- RFA & RFP and Sketch .
1.4- RFIs
1.1- Materials Status.
Received
No Submittal Ref. REV. Description Remarks
Date
Earth Spike (TYPE T01-SP.1+TYPE T02-SP.2), 10Watt, 3000K,
Earth Spike (TYPE T01-SP.1), 10Watt, 3000K, Ip65, Beam
Angle 12 (Adjustable), Code:5001-20-G2-TR-JB-S + tridonic 24-06-2024
01 SUB-MAT-EL-0554 01 driver + JUNCTION BOX 3WAYS (EW-M2068S) IP68 + Surge (Pending)
protection 10K From "EGYLUX" For NOOR VILLAS
LANDSCAPE".
1.2.1- Structural shop drawings Status.
No Submittal Ref. REV Description TYPE Received Date Remarks

Concrete Dimension For First Floor Slab & 04-03-2024


01 SUB-SDW-ST-0345 01
Beams For Builder Work
TV
(Pending)

1.2.2- Infrastructure and Roads shop drawings Status.


No Submittal Ref. REV Description Received Date Remarks

Spot Elevations Low Points &Setting Out Of Road


05-05-2024
01 SUB-SDW-SUR-0555 00 (V3-Rd 04-Part 02 From Stn 0+260 To
0+491.11&Roundabout Ra-03) (Pending)

Spot Elevations & Setting Out & Typical Cross


Section Of Road (V3-Rd 04-Part 03) 05-05-2024
02 SUB-SDW-SUR-0556 00
Profile Of Road (V3-Rd 04-Part 03) (Pending)
CIVIL 3D FILE
1.3- RFA & RFP and Sketch :
No Submittal Ref. REV Description Received Date Remarks
Infrastructure
Request For Alternative -
Infrastructure
Pressure & Gravity Networks
03-06-2024
01 SUB-RFA-PD-0512 01 Materials : Bitumenus Protective External Coating
Manufactuer: Kemia For Building Products (Pending)
Applied For: External Surfaces of Concrete
Manholes and Chambers for all networks

Architecture
Request For Proposed Change Roof Freon Sleeve 28-05-2024
02 SUB-RFP-AR-0579 00 Details All Types
(Pending)
Request for proposed change walkways around all 24-06-2024
03 SUB-RFP-AR-0602 00 type of villas to increase the grean area
(Pending)
1.4- RFIs
No Submittal Ref. Description Received Date Remarks

19-05-2024
01 RFI-EL-0042 Distribution Boxes Architectural Locations
(Pending)

25-06-2024
02 RFI-EL-0043 Location of landscape lighting panels.
(Pending)

You might also like