Professional Documents
Culture Documents
Md 521 1500 Cn Cv Mst Mmah 0005_a04 r Mst Road Construction Was
Md 521 1500 Cn Cv Mst Mmah 0005_a04 r Mst Road Construction Was
Number: MD-521-1500-CN-CV-MST-MMAH-0005
Date: 01-FEB-2024
Rev: A04
REVIEW GRADE
Result Code Description
A Accepted
I For Information
REVISION INDEX
Rev Date Description
A01 20-Dec-2023 For Review and Approval
A02 10-Jan-2024 For Review and Approval
TABLE OF CONTENTS
Item no Description Page no
Title: METHOD STATEMENT FOR TEMPORARY AND PERMANENT ROAD
CONSTRUCTION
1 DESCRIPTION OF WORK 4
2 WORK METHODOLOGY 5
3 RESOURCES 6
4 A. SITE KEY PERSONNELS & WORK FORCE 7
5 B. PLANT & EQUIPMENT 8
7 C. MATERIAL & TOOLS 8,9
8 RISK ASSESSMENT 9
Ma’aden Phosphate 3 Phase I
MA’ADEN Phosphate 3 Phase I
Project Phase : Ma’aden Project N° : 18-PME-PH3-PH1-001
METHOD OF STATEMENT Document N°: MD-521-1500-CN-CV-MST-MMAH-
FOR ROAD CONSTRUCTION 0005
Main Title:
Revision: A04
DESCRIPTION OF WORKS
The purpose of the document is to describe the Methodology and Procedure of
temporary/permanent Road Construction to demonstrate the activities to be carried out
in accordance to the contract requirement for WAS . The Scope of these activities shall
consist of Aggregate Sub base & Base Course Construction to be carried out as per
Approved Shop Drawings.
A Setting out survey on high level grade location at the jobsite which required to be cut
and leveled as per drawing. All tests must be carried out by approved 3rd party testing
agency.
Ma’aden Phosphate 3 Phase I
MA’ADEN Phosphate 3 Phase I
Project Phase : Ma’aden Project N° : 18-PME-PH3-PH1-001
METHOD OF STATEMENT Document N°: MD-521-1500-CN-CV-MST-MMAH-
FOR ROAD CONSTRUCTION 0005
Main Title:
Revision: A04
1. WORK METHODOLOGY
ES&H department to check and ensure to have valid driving Iqama’s, TUV for
3 operator, safety passport to all employees. Consequently, to check and ensure
equipment documentations
Before STARRT Meeting, Supervisor must have permit available for area where
4 excavation is to be done in order to identify all hazards related to that specific
excavation. Field Engineer to ensure that permit is available before STARRT
meeting.
5 After meeting employees will sign the STARRT CARD and Supervisor will keep the
STARRT CARD until the end of the day.
Ensure to protect existing utilities with barricades.
6
7 Surveyor shall ensure prior to start survey work the survey equipment is have
calibration certificate and must be approved by WORLY.
8 Conduct setting out survey activities in the jobsite, layout and marked work
location as per design, grade, level and dimension as shown on approved drawings.
Before backfill material, the following shall be observed:
• Areas to receive fill shall be free of roots, trash, or other foreign material.
9
Ensure the site clearing and base and compaction are carried as
10 per the specification and approved quality plan.
11 The source for the Aggregate Sub base & Base course and marl material to be
approved.
12 The approved source material to be sampled and tested by the approved 3rdParty
testing agency.
Road accessories to be procured from approved vendor
13
Road demarcation shall be implemented as per Maaden standard requirements
14
The Aggregate Subbase and Base Course materials are stored properly in assigned
16
Stockpile area
Cut and fill using suitable equipment to be performed as required to achieve the
17
design profile.
No subbase or base course shall be placed on the subgrade until the subgrade has
18
been approved by the WORLY.
19 Loaders start loading trucks the approved material from the stockpiles to the road
areas
20 Graders to spread the materials on the entire route specified and agreed upon
with Worley, as per the approved drawings.
21 Surveyors determine the required level and water tankers flood the specific road
area, roller compactors to start compaction to reach the required result before
the approved 3rd takes samples and make the tests, water specifications to be as per
Maaden requirement.
25 On areas were FDT were failed shall be moisten the surfaced before re-compaction
shall be made before the rescheduled density test.
26 All unsuitable material that has been cut from site to be removed to approved
location.
27 All works carried out as per MA’ADEN standard and SOW.
Ma’aden Phosphate 3 Phase I
MA’ADEN Phosphate 3 Phase I
Project Phase : Ma’aden Project N° : 18-PME-PH3-PH1-001
METHOD OF STATEMENT Document N°: MD-521-1500-CN-CV-MST-MMAH-
FOR ROAD CONSTRUCTION 0005
Main Title:
Revision: A04
Note that all works require mandatory PPE as follows helmet, gloves, safety
glasses, safety boots, vest.
Environmental Controls
WORK TEAM PERMITS PERSONAL PROTECTIVE ISOLATION, TAGGING, (Bunding, Waste Disposal,
PLANT, EQUIPMENT & TOOLS
MEMBERS EQUIPMENT REQUIREMENTS BARRICADES & SIGNS Discharge Prevention, etc)
Cold Work ☐ Hard hat, safety shoe, Grader White and red hard
barricade
Hot Work ☐ High reflective vest Wheel loader Warning signages
Confined Space ☐ Safety Glass Water tanker Heavy equipment
movement signs
Hazardous Work ☐ Leather hand gloves Dumtrucks
Night Work ☐ N 95 Mask, Ear plug Hand tools
Radiography ☐
LockOut Tag Out ☐
Scaffold Permit ☐
Excavation Permit ☐
Crane Permit ☐
Crane Critical Permit ☐
Road Closure ☐
☐
☐