Project: Boracay Hotel and Convention

Subject: Productivity and Manhours Monitoring

Date:
JULY 05 2024

Manhours
Accomplishment
GROUP NAME (SUBCON, QRT OR ADMIN) Regular OT Regular OT Scope of Work Location
Planned (PIC) Actual (Timekeeper) Planned Actual Unit

No. Name of Worker Designation

1 CHRISTOPHER HABINAR Foreman 7 INSTALLATION OF REBAR STP GL 14-15/A-B 37.295 KGS

2 ROY NARCISO STEELMAN 7 INSTALLATION OF REBAR STP GL 14-15/A-B 37.295 KGS

3 ALVIN SONICO STEELMAN 7 INSTALLATION OF REBAR STP GL 14-15/A-B 37.295 KGS

4 KIM DINIGA STEELMAN 7 INSTALLATION OF REBAR STP GL 14-15/A-B 37.295 KGS

10 28 TOTAL 149.18 KGS.

Prepared by: Verified by: Noted by:

Project in-charge Timekeeper Project Manager