PROJECT NAME: KUSHUMBAGH TOWER .

1. Foundation: Tk . 21388622
2. Ground Floor: Tk 5929005
3. 1st floor: Tk. 8168446.65
4. 2nd floor: Tk 8168446.65
5. 3rd floor: Tk. 8168446.65
6. 4th floor: Tk 8168446.65
7. 5th floor: Tk. 8168446.65
8.6th floor: Tk. 8168446.65
9.7th floor: Tk. 8168446.65
10.8th floor: Tk. 8168446.65
11.9th floor: Tk. 8168446.65
10.Roof Top: Tk. 5036400
TOTAL: Tk. 100833646.9

( Ten core eight lac thirty-three thousand six hundred forty six Taka
only)
FOUNDATION(BELOW GROUND FLOOR)

ADDRESS
PROPOSED BUILDING ON DAG NO-C.S & S.A-1082, R.S-786, DHAKA CITY
JARIP-4401, KHATIAN NO- 5-208, S.A-290, R.S-68, DHAKA CITY JARIP-3298, J.L
NO-C.S-318, S.A-143, R.S-13, DHAKA CITY JARIP-6, MOUZA- DAKHINGAON,
KUSHUMBAGH, SABUJBAGH, DHAKA-1214

No. Item description Quantity Unit Unit rate


(taka)

1 PILE
Concrete
cement 4622 bag 550 2542100
sand 8929 cft 65 580385
stone 17858 cft 210 3750180
MS rod
16mm 32356 kg 90 2912040
10mm 21782 kg 90 1960380

Labor cast
pile 9630 rft 250 2407500
2 PILE-CAP
Concrete
cement 1087 bag 550 597850
sand 2101 cft 65 136565
stone 4202 cft 240 1008480
MS rod
20mm 11000 kg 90 990000
16mm 4000 kg 90 360000

3 SHORT -
COLUMN
Concrete
cement 122 bag 550 67100
sand 265 cft 65 17225
stone 530 cft 240 127200
MS rod
20mm 4000 kg 90 360000
10mm 2000 kg 90 180000
No. Item description Quantity Unit Unit rate
(taka)
4 GREAD BEAM
Concrete
cement 285 bag 550 156750
sand 584 cft 65 37960
stone 1168 cft 240 280320
MS rod
20mm 2704 kg 90 243360
16mm 1148 kg 90 103320
10mm 1860 kg 90 167400
12mm 0 kg 90
5 U.G.W.R
Concrete
cement 190 bag 550 104500
sand 427 cft 65 27755
stone 855 cft 240 205200
MS rod
10mm 4000 kg 90 360000
12mm 2200 kg 90 198000
6 LIFT-CORE
Concrete
cement 27 bag 550 14850
sand 56 cft 65 3640
stone 112 cft 240 26880
MS rod
10mm 125 kg 90 11250
12mm 200 kg 90 18000
7 PARKING
SLAB
Concrete
cement 312 bag 550 171600
sand 779 cft 65 50635
stone 1557 cft 240 373680
MS rod
10mm 5000 kg 90 450000
12mm 0 kg 90
8 LABOR CAST 6935 sft 245 1699075
TOTAL 21388622