Ground Floor

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Project Lcation :

PROPOSED BUILDING ON DAG NO-C.S & S.A-1082, R.S-786, DHAKA CITY JARIP-4401, KHATIAN NO- 5-
208, S.A-290, R.S-68, DHAKA CITY JARIP-3298, J.L NO-C.S-318, S.A-143, R.S-13, DHAKA CITY JARIP-6,
MOUZA- DAKHINGAON, KUSHUMBAGH, SABUJBAGH, DHAKA-1214

GROUND FLOOR

No. Item description Quantity Unit Unit rate (taka) Cost (taka)

1 COLUMN

Concrete

cement 177 bag 510 90270

sand 362 cft 65 23530

stone 724 cft 240 173760

MS rod

20mm 3000 kg 95 285000

12mm 150 kg 95 14250

10mm 1500 kg 95 142500

2 BEAM

Concrete

cement 184 bag 510 93840

sand 377 cft 65 24505

stone 754 cft 240 180960

MS rod

20mm 3500 kg 95 332500

16mm 800 kg 95 76000


10mm 1500 kg 95 142500

3 SLAB

Concrete

cement 402 bag 510 205020

sand 1005 cft 65 65325

Khoa 2010 cft 120 241200

MS rod

12mm 1000 kg 95 95000

10mm 4500 kg 95 427500


BRICK
4
WORK
cement 30 bag 510 15300

sand 130 cft 25 3250

Brick 5000 pic 12 60000

5 PLASTER

cement 270 bag 510 137700

sand 540 cft 25 13500


LINTEL &
6
FALSE SLAB
cement 2 bag 510 1020

sand 12 cft 25 300

Khoa 24 cft 140 3360

MS rod

10mm 200 kg 95 19000

7 TILES

Floor
cement 136 bag 510 69360

sand 272 cft 25 6800

Pavement tiles 6800 sft 95 646000

Toilet(wall)

tiles 150 sft 80 12000

cement 3 bag 510 1530

sand 6 cft 25 150

Kitchen(wall)

tiles 150 sft 80 12000

cement 3 bag 510 1530

sand 6 cft 25 150

8 D00R

door shutter 1 pic 7000 7000

Toilet door 2 pic 4500 9000

9 GRILL

Window grill 75 sft 180 13500

Toilet grill 3 sft 180 540

Stair railing 1 L.S. 12000 12000

10 THAI

Window thai 75 sft 350 26250

Toilet thai 3 sft 350 1050

11 STAIR

Concrete

cement 16 bag 510 8160


sand 45 cft 65 2925

stone 90 cft 240 21600

MS rod

10mm 80 kg 95 7600

12mm 300 kg 95 28500


SANITARY
12
WORK
Toilet 1 pic 12000 12000

Kitchen 1 pic 6000 6000

13 PAINT

Celling paint 5244 sft 9 47196

Wall paint 8300 sft 11 91300

Door /window 200 sft 15 3000

Out-side paint 3030 sft 12 36360


BOUNDARY
14
WALL
cement 90 bag 510 45900

sand 390 cft 25 9750

brick 13600 cft 12 163200

Concrete

cement 180 bag 510 91800

sand 450 cft 65 29250

stone 900 cft 240 216000

MS rod

12mm 300 kg 95 28500

16mm 500 kg 95 47500


10mm 300 kg 95 28500

16 FRONT GATE 100 sft 620 62000

17 LABOR CAST 5244 sft 205 1075020

Sub total= 5981531

ELEC.
18 5% 299076.55
WORK

TOTAL= 6280607.55