Project Lcation :

PROPOSED BUILDING ON DAG NO-C.S & S.A-1082, R.S-786, DHAKA CITY JARIP-4401, KHATIAN NO- 5-
208, S.A-290, R.S-68, DHAKA CITY JARIP-3298, J.L NO-C.S-318, S.A-143, R.S-13, DHAKA CITY JARIP-6,
MOUZA- DAKHINGAON, KUSHUMBAGH, SABUJBAGH, DHAKA-1214

FOUNDATION(BELOW GROUND FLOOR)

No. Item description Quantity Unit Unit rate (taka)

1 PILE

Concrete

cement 4622 bag 510 2357220

sand 8929 cft 65 580385

stone 17858 cft 210 3750180

MS rod

16mm 32356 kg 95 3073820

10mm 21782 kg 95 2069290

Labor cast
pile 9630 rft 250 2407500

2 PILE-CAP

Concrete

cement 1087 bag 510 554370

sand 2101 cft 65 136565

stone 4202 cft 240 1008480

MS rod

20mm 11000 kg 95 1045000

16mm 4000 kg 95 380000

3 SHORT -COLUMN

Concrete

cement 122 bag 510 62220

sand 265 cft 65 17225

stone 530 cft 240 127200

MS rod

20mm 4000 kg 95 380000

10mm 2000 kg 95 190000

No. Item description Quantity Unit Unit rate (taka)

4 GREAD BEAM

Concrete

cement 285 bag 510 145350

sand 584 cft 65 37960

stone 1168 cft 240 280320

MS rod
20mm 2704 kg 95 256880

16mm 1148 kg 95 109060

10mm 1860 kg 95 176700

5 U.G.W.R

Concrete

cement 190 bag 510 96900

sand 427 cft 65 27755

stone 855 cft 240 205200

MS rod

10mm 4000 kg 95 380000

12mm 2200 kg 95 209000

6 LIFT-CORE

Concrete

cement 27 bag 510 13770

sand 56 cft 65 3640

stone 112 cft 240 26880

MS rod

10mm 125 kg 95 11875

12mm 200 kg 95 19000

7 PARKING SLAB

Concrete

cement 312 bag 510 159120

sand 779 cft 65 50635

stone 1557 cft 240 373680

MS rod

10mm 5000 kg 95 475000

12mm 0 kg 95 0

8 LABOR CAST 6935 sft 205 1421675

TOTAL= 22619855