Bill No.

1 PRELIMINARIES
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 1

PRELIMINARIES

Non-Recurring Preliminary Costs (Mobilization)


Incurred at the Commencement of the Works

A Provision of site office for Employer's Representative


and Engineer's site team complete with all facilities,
services, fixtures and fittings as specified on drawings
and specifications. Item

B Provision of 1 no. Project sign board with all related


works, and maintenance of the same complete as per
specification Item

C Closure of Project site fencing, complete with all related


works, and maintenance of the same complete as per
specification Item

D NA

E
NA Item

F Provision and connection of all necessary site power,


lighting, telephone, fax and internet for the site
establishments and the work Item

G Provision and connection of water and sanitation for the


site establishment and the works Item

H Payment of fees to obtaining clearances, permits etc


from Statutory Authorities. Item

J
The Contractor shall allow for all other obligations in
accordance with the contract not listed under this
section of Non-recurring Preliminary Costs at the
Commencement of the Works. The Contractor shall
detail below any such obligations together with the
Contract volume, section and clause reference as
applicable Item
To Collection QR
Recurring Preliminary Costs Incurred During the
Execution of the Works

A
Maintenance of Employer's Representative and
Engineer's site staff office, and all other facilities and
services including all fixtures, furniture and equipments Item

B Provision and maintenance of site office for Contractor's


site team/staff Item

C Provision & maintenance for all associated running


costs of all required site plant and equipment Item

D Provision of Contractor's adequate site management,


administrative and supervisory staff Item

E Maintenance and payment of all necessary site power,


lighting, telephone, fax, internet, water and sanitation for
the site establishments and the work Item

F Provision of all required safety and security during the


progress of the work including watching, safety rails,
barriers and safety signs as required, safety fencing,
protection of existing services, roads and property Item

G Provision of all required progress site reports,


photographs and documentation as required by the
Engineer Item

H Provision of all required Quality Assurance and Quality


Control during the progress of the work, to Employer's
requirements and procedures Item

J Cleaning up and removal off-site of the rubbish during


the progress of the work Item

K
The Contractor shall allow for all other obligations in
accordance with the Contract not listed under this
section of Recurring Preliminary Costs During the
Progress of the Works. The Contractor shall detail
below any such obligations together with the Contract
volume, section and clause reference as applicable Item
To Collection QR
Non-Recurring Preliminary Costs (Demobilization)
Incurred at the Completion of the Works

A Demobilization of all Employer's Representative and


Engineer's site offices and all other facilities and
services including fixtures, furniture, equipments, etc. Item

B Demobilization of all offices, and facilities provided for


Contractor's site team including all services, fixtures,
furniture, equipments, etc. Item

C Demobilization and removal of project sign board,


hoardings and site fences, plants, equipments and
facilities, and making good Item

D
Provision of all required as built drawings, operating
manuals, procedures, information and any other
documentation required in accordance with the Contract
to be handed over to the Employer's Representative Item

E Clearing up and making good of the site establishment


after completion of the work and demobilization Item

F Provision for payment of fees to obtaining clearances,


permits etc from Statutory Authorities Item

G
The Contractor shall allow for all other obligations in
accordance with the Contract not listed under this
section of Non-Recurring Preliminary Costs on
Completion of the Works. The Contractor shall detail
below any such obligations together with the Contract
clause reference as applicable Item
To Collection QR
PRELIMINARIES

QUANTITIES

TOTAL PRICE
(QR)
Bill No. 2 SITE WORKS
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES
ITEM UNIT RATE
ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 2

SITE WORKS

PART A - VILLA TYPE A

SITE PREPARATION

A Allow for clearing the site of all rubbish and debris to the
satisfaction of the Engineer 1 Item

B
Anti-termite application complete as per specifications 1 Item

C RE-ROUTING OF EXISTING SERVICES

Allow for re-routing and/or removal and re-instatement


of existing services above surface or underground
(Contractor to verify all data and information to confirm
any existing services and applicability of this item) 1 Item

EXCAVATION & EARTH WORKS

Excavation, Backfill & Disposal as per specification

Note:
1. Excavation is measured NET without allowance to
working space, Contractor should allow the same on his
rate.
2. Contractor to visit site to determine actual scope of
works of this section.

D Excavation to the required level as shown

E Backfilling of approved backfill material around


foundations & to make up levels as required and shown
on drawings

F Cart away surplus material to approved site

G Allow compaction of the natural foundation all in


accordance with the drawings and specifications
H All reinstatement works on completion 1 Item

To Collection QR
RKS
S
TOTAL PRICE
(QR)
Bill No. 3 CONCRETE
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 3

CONCRETE

PART A - VILLA

CONCRETE WORKS - SUBSTRUCTURE

Reinforced in-situ concrete; concrete grade as specified


on drawing schedule, including admixtures,
formwork/shuttering and all reinforcing bars, complete
as shown on drawings and as per specifications

A footing

B column

C wall

D ground slab, 100 mm thick


E ground beam
F wall footing

Plain concrete as per specification


G concrete blinding (50 mm thick)
H concrete blinding (100 mm thick)

CONCRETE WORKS - SUPERSTRUCTURE

Reinforced in-situ concrete; concrete grade as specified


on drawing schedule, including admixtures,
formwork/shuttering and all reinforcing bars, complete
as shown on drawings and as per specifications
I columns

J beams, lintels, upstands, downstands and the like

SUNDRIES
K
Allow for structural joints as required

To Collection QR
TE

TOTAL PRICE
(QR)
Bill No. 4 MASONRY
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 4

MASONRY

PART A - VILLA TYPE A

MASONRY BLOCK

Concrete blocks with compressive strength as defined in


the specification, including insulation or extruded
polystyrene at block-structure abutments, horizontal
reinforcing steel mesh, control joint dressing, ties,
complete as per specification

concrete blocks - for external walls

A 100 mm thick blocks + 50mm insulation+ 100mm thick


blocks

B 200 mm thick

C 150 mm thick

D 100 mm thick

concrete blocks - for internal walls

E 100 mm thick blocks + 50mm insulation+ 100mm thick


blocks

F 200 mm thick

G 150 mm thick

H 100 mm thick

J concrete blocks filled with C15 concrete to Ground


Beams

K 200mm parapet walls including upstand, stiffener and


coping

Provide lintels as required for the above block works

L for 200 mm thick block works

M for 150 mm thick block works


N for 100 mm thick block works

To Collection

M
A

M
A

M
A

B
C

C
D

D
To Collection QR

Bill No. 4

COLLECTION

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Page 8
Carried To Summary QR
Y

TOTAL PRICE
(QR)
A
Bill No. 6 WOOD AND PLASTIC
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 6

WOOD AND PLASTIC

PART A - VILLA TYPE A

KITCHEN CABINETS

Supply & installation of 18 mm thick MDF laminated


finish kitchen cabinets comprising of shutters, carcass,
shelves, drawers, hardwares/ironmongery, plinths, 30
mm thick solid surface countertop, mixers, kitchen sink,
all necessary fixing accessories and finish, complete as
shown on drawings and per specification

Kitchen

CABINETS

Supply & installation cabinets comprising of 18 mm thick


white melamine faced MDF with PVC lipping all around,
carcass, shutters, drawers, shelves, hanger rod,
skirting, glazing, frames, ironmongeries, complete as
shown on drawing and as per specification

To Collection QR
WARDROBE

Supply & installation of wardrobe with 18 mm thick MDF


sliding door with glass, internal drawers, shelves,
backpanel , all complete necessary fittings, finishes and
accessories.
To Collection QR
ND PLASTIC

TOTAL PRICE
(QR)
THERMAL & MOISTURE
Bill No. 7
VILLA RENOVATION - AL KHOR PROTECTION
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 7

THERMAL & MOISTURE PROTECTION

ROOFING & ROOF WATERPROOFING

Roof Waterproofing as per details and specification

waterproofing to roof top

A gravel as shown on detail

B water proofing protection

C two layers of water proofing membrane

D slope concrete as specified

E thermal insulation

F vapor barrier

treatment to skirting - 150 mm minimum height

G vapor barrier

H two layers of water proofing membrane

J aluminum flashing system - metal flashing with groove &


mastic sealant

waterproofing to balcony/terrace/window sill

K waterproofing membrane, complete system including


turning up at edges

FLUID APPLIED POLYURETHANE


WATERPROOFING

Fluid applied polyurethane water proofing as per


specification

for wet areas - toilets, kitchens etc.

L to floor including turning up at edges

Warranties & Protection to All Waterproofing Areas


M Allow for water test 1 Item

N Allow for warranties as per specification 1 Item

To Collection QR
To Collection QR
PART E - TOWNHOUSE

WATERPROOFING

waterproofing to planter box including water proofing


membrane, filter fabric, gravel, aluminum flashing,
aluminum u-channel chamfer as shown on Drawing

A to sides of planter box 21 m2

B to bottom of planter box 15 m2


To Collection QR
ROOFING & ROOF WATERPROOFING

Roof Waterproofing as per details and specification

waterproofing to roof top

A gravel as shown on detail 1,000 m2

B water proofing protection 1,000 m2

C two layers of water proofing membrane 1,000 m2

D slope concrete as specified 1,000 m2

E thermal insulation 1,000 m2

F vapor barrier 1,000 m2

treatment to skirting - 150 mm minimum height

G vapor barrier 560 m

H two layers of water proofing membrane 560 m

J aluminum flashing system - metal flashing with groove &


mastic sealant 560 m

waterproofing to balcony/terrace/window sill

K waterproofing membrane, complete system including


turning up at edges 8,660 m2

FLUID APPLIED POLYURETHANE


WATERPROOFING
Fluid applied polyurethane water proofing as per
specification

for wet areas - toilets, kitchens etc.

L to floor including turning up at edges 2,430 m2

Warranties & Protection to All Waterproofing Areas

M Allow for water test 1 Item

N Allow for warranties as per specification 1 Item

To Collection QR
WATERPROOFING

Membrane Water Proofing in complete system as per


specification

to bottom, to sides of footings, column/walls and ground


slab; and top surfaces of footings in contact with ground;
and the like

A rubber base bitumen paint 6,463 m2

B 1000 gauge polythene sheet 8,070 m2

to bottom, to sides of ground beam in contact with


ground; and the like

C protection as shown on details 1,942 m2


To Collection QR
PART F - CLUB HOUSE 1

ROOFING & ROOF WATERPROOFING

Roof Waterproofing as per details and specification

waterproofing to roof top

A gravel as shown on detail 288 m2

B water proofing protection 288 m2

C two layers of water proofing membrane 288 m2

D slope concrete as specified 288 m2

E thermal insulation 288 m2

F vapor barrier 288 m2

treatment to skirting - 150 mm minimum height

G vapor barrier 77 m

H two layers of water proofing membrane 77 m

J aluminum flashing system - metal flashing with groove &


mastic sealant 77 m

waterproofing to balcony/terrace/window sill

K waterproofing membrane, complete system including


turning up at edges 1,479 m2

FLUID APPLIED POLYURETHANE


WATERPROOFING
Fluid applied polyurethane water proofing as per
specification

for wet areas - toilets, kitchens etc.

L to floor including turning up at edges 260 m2

Warranties & Protection to All Waterproofing Areas

M Allow for water test 1 Item

N Allow for warranties as per specification 1 Item

To Collection QR
WATERPROOFING

Membrane Water Proofing in complete system as per


specification

to bottom, to sides of footings, column/walls and ground


slab; and top surfaces of footings in contact with ground;
and the like

A rubber base bitumen paint 817 m2

B 1000 gauge polythene sheet 1,392 m2

to bottom, to sides of ground beam in contact with


ground; and the like

C protection as shown on details 473 m2


To Collection QR
PART G - CLUB HOUSE 2

WATERPROOFING

waterproofing to planter box including water proofing


membrane, filter fabric, gravel, aluminum flashing,
aluminum u-channel chamfer as shown on Drawing

A to sides of planter box 30 m2

B to bottom of planter box 7 m2


To Collection QR
ROOFING & ROOF WATERPROOFING

Roof Waterproofing as per details and specification

waterproofing to roof top

A gravel as shown on detail 46 m2

B water proofing protection 46 m2

C two layers of water proofing membrane 46 m2

D slope concrete as specified 46 m2

E thermal insulation 46 m2

F vapor barrier 46 m2

treatment to skirting - 150 mm minimum height

G vapor barrier 28 m

H two layers of water proofing membrane 28 m

J aluminum flashing system - metal flashing with groove &


mastic sealant 28 m

waterproofing to balcony/terrace/window sill

K waterproofing membrane, complete system including


turning up at edges 303 m2

FLUID APPLIED POLYURETHANE


WATERPROOFING

Fluid applied polyurethane water proofing as per


specification

for wet areas - toilets, kitchens etc.

L to floor including turning up at edges 58 m2


Warranties & Protection to All Waterproofing Areas

M Allow for water test 1 Item

N Allow for warranties as per specification 1 Item

To Collection QR
WATERPROOFING

Membrane Water Proofing in complete system as per


specification

to bottom, to sides of footings, column/walls and ground


slab; and top surfaces of footings in contact with ground;
and the like

A rubber base bitumen paint 284 m2

B 1000 gauge polythene sheet 426 m2

to bottom, to sides of ground beam in contact with


ground; and the like

C protection as shown on details 114 m2


To Collection QR
CONTRACTOR'S ADJUSTMENT

Contractor shall insert in this section any ADDITIONAL


or ADJUSTMENTS on items (or quantities) as
required/shown in the specifications/ drawings and other
tender documents; or as requirements by the
Authorities, relevant Standards and Codes; and such
other items that are required for the satisfactory
completion of this section, or as required by the system
he Contractor is offering but not mentioned else where.
Contractor to list those items here with quantities and its
corresponding all inclusive rates/cost as applicable. Any
such items not listed below shall deemed to be included.

A __________________________________________

B __________________________________________

C __________________________________________

D __________________________________________
To Collection QR

Bill No. 7

COLLECTION

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Page 8

Page 9

Page 10

Page 11

Page 12

Page 13

Page 14

Page 15

Page 16

Page 17

Page 18

Page 19

Page 20

Page 21
Carried To Summary QR
L & MOISTURE
TION
S

TOTAL PRICE
(QR)
TH 3.4 0.3 2.04 10

0.9 0.8 0.72 1.44 14.4


143.2
143.2
CH2
143.2
20.4
Bill No. 8 DOORS & WINDOWS
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES
ITEM UNIT RATE
ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 8

DOORS & WINDOWS

PART A - VILLA TYPE A UPVC/WOOD

DOORS

Supply & installation of doors including door frame


(plywood sub frame, solid wood frame, architraves, door
base, inlay, seals, stoppers) & door shutter (structural
frame, core, decking, skin, lipping, glazing & fire
resistant glass where specified, beadings) and finish
(ironmongery measured separately) as specified,
complete as shown on drawing and as per Specification

A Door Type D1

B Door Type D2

C Door Type D3

D Door Type D4

IRONMONGERY

Supply & installation of doors ironmongery to doors


complete as shown on drawings and as per
specification

ironmongery to doors
To Collection QR
WINDOWS

Supply & install double glazed windows as specified


including coated aluminum frames (where specified),
fixing system and accessories, glass panels - fixed
panels, spandrel panels, awning windows, hinged door
panels, with and including supply and fix of
ironmongeries / hardwares, complete as shown on
drawing and as per specification

glazed windows

A Type AW01

B Type AW02

C Type AW03

D Type AW04

E Type AW05

F Type AW06

G Type AW07

H Type AW08

To Collection QR
& WINDOWS
S
TOTAL PRICE
(QR)
Bill No. 9 FINISHES
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 9

FINISHES

PART A - VILLA TYPE A

GENERAL

A
plaster to external walls&Internal walls to receive paint

PLASTER

Cement-sand plaster/render on specified thickness as


per specification

to receive paint as per manufacturer's recommendation

B to walls & columns - internal (CPP)

C to ceiling, soffits/sloping soffits of staircase (CPP)


To Collection QR
CERAMIC TILES/Marbles

Supply & installation of ceramic tiles including


necessary base screed/cement-sand mortar, adhesives,
grouts, sealants, stainless steel fixing to walls, and other
fixing accessories, all as shown on drawings and
specifications

to floors

A ceramic tiles (CM1)

B ceramic tiles

C to landing, tread and riser (CM3)

D ceramic 80 mm skirting (SK1)

E ceramic 110 mm skirting (SK2)

to walls

F ceramic tiles 450mm x 250 mm (CM4)

G ceramic copings to balustrade, planter box

PAINTING

Supply & apply painting, including necessary surface


preparation, sealer, primer, paint at number of coats as
specified, waterproofing & anti-slip application where
applicable, etc. (plaster/screed measured separately
unless mentioned otherwise) complete as per
Specification

Paint on plaster

H
to external walls, to walls with groove, rendered plaster

J to internal walls

K to ceilings
To Collection QR
S

TOTAL PRICE
(QR)
BILL NO. 15B PLUMBING
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES
UNIT
ITEM
ITEM DESCRIPTION QUANTITY UNIT RATE
REF.
(QR)

BILL NO. 15B

PLUMBING

COLD WATER SYSTEM INSTALLATION

Supply, installation, testing, commissioning handing over and


guarantee the following works

All PPR pipes shall be manufactured from approved raw


materials in accordance with standard, for cold water inside
wall. The material is a polypropylene random improved
temperature resistance and including gate valves, check
valves, automatic reducing valve and all accessories
according to drawing and specification.

A 15 mm Ø ( Quantity as per site requirements ) LOT M

B 20 mm Ø " " LOT M

C 25 mm Ø " " LOT M

D 32 mm Ø " " LOT M

E 40 mm Ø " " LOT M

F 50 mm Ø " " LOT M

HOT WATER SYSTEM INSTALLATION

Supply, installation, testing, commissioning handing over and


guarantee the following works
All PPR-CT pipes shall be manufactured from approved raw
materials in accordance with standard, for hot and return hot
water inside wall. The material is a polypropylene random
improved temperature resistance and including gate valves,
solenoid valves, strainers, check valves, automatic reducing
valve and all accessories according to drawing and
specification.

G 15 mm Ø ( Quantity as per site requirements ) LOT M

H 20 mm Ø " " LOT M

I 25 mm Ø " " LOT M

Supply Water Tanks and Pumps:

Supply, installation, testing, commissioning handing over and


guarantee the following works:

Clyindrical Ground water- tank capacity of 2000L 2 nos


complete with all components c/w,float valves, balancing and
K over flow connections, all necessary accessories as required 2 No
by the drawings, standard and specifications

Pressure pump for domestic supply with pressure valve as


L per drawings, complete with all accessories 2 NR

WATER HEATER SYSTEM:

Individual Water Heaters for Bathrooms & Kitchen complete


M 10 NR
with all accessories

N Fixing all the Bathroom & Kitchen fittings with necessary LOT
accessories

Note : Bathroom & Kitchen fittings supplied by the client.

Lumpsum Amount for Plumbing Work


A

D
Carried To Mechanical Installations Collection QR
PLUMBING

QUANTITIES

TOTAL PRICE
(QR)
56,450.00
Bill No. 15C DRAINAGE INSTALLATION
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES
UNIT
ITEM
ITEM DESCRIPTION QUANTITY UNIT RATE
REF.
(QR)

Bill No. 15C

DRAINAGE INSTALLATION

RAIN WATER ISTALLATION:

Supply, installation, testing, commissioning handing over and


guarantee the following works:

110mm Ø UPVC Pipes class 4 and fittings as specified and


A LOT M
drawn

Half Circle Roof Drain 110 mm Ø installed complete as


B LOT NR
specified and drawn

SEWERAGE SYSTEM INSTALLATION

Supply, installation, testing, commissioning handing over and


guarantee the following works

UPVC pipes including fitting and supports embedded in


concrete or floor screed complete as specified jointing to
pipeworks.

C 50 mm Ø LOT M

D 75 mm Ø LOT M

E 110 mm Ø LOT M

F 150 mm Ø LOT M

Vent Pipes UPVC class 3 and fittings as specified with solvent


welded joints for floor drain ; allow for insulation and vapor
sealing as necessary

G 50 mm Ø LOT M

Instllation of Floor Drain complete as specified and drawn

H 50mm Ø LOT NR
Roof vent caps installed complete as specified and drawn

I 50mm Ø LOT NR

J 75mm Ø LOT NR

K 110mm Ø LOT NR

Clean Outs installed complete as specified and drawn

L 75 mm Ø LOT NR

M 110 mm Ø LOT NR

N New Manholes (800x800mm) with 6" sleeve 11 NR

150 mm Ø UPVC pipes including fitting and supports


O embedded in concrete or floor screed complete as specified LOT NR
jointing to pipeworks between manholes

P New Gully Chamber (400x400mm) with 4" sleeve 7 NR

110 mm Ø UPVC pipes including fitting and supports


Q embedded in concrete or floor screed complete as specified LOT NR
jointing to pipeworks between Gully & manholes

Lumpsum Amount for Drainage Work


INAGE INSTALLATION

QUANTITIES

TOTAL PRICE
(QR)
32,650.00
BILL NO. 15D FIRE FIGHTING
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES
ITEM UNIT RATE
ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

BILL NO. 15D

FIRE FIGHTING

Portable fire extinguishers ABC type complete as


specified in the drawings and specs. including supports
and fixing brackets as necessary and wall mounted.

A 6 kg dry chemical powder extinguisher;


2 NR

Portable fire extinguishers for kitchen complete as


specified in the drawings and specs. including supports
and fixing brackets as necessary and wall mounted.

B 6 kg wet chemical powder extinguisher; ref. PFE-2 1 NR

C Fire blanket complete as specified in the drawings and 1 NR


specs

CARRIED TO COLLECTION
FIRE FIGHTING

QUANTITIES
TOTAL PRICE
(QR)

950.00
Bill No. 16 ELECTRICAL INSTALLATIONS
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 16

ELECTRICAL INSTALLATIONS

ELECTRICAL & LOW CURRENT INSTALLATIONS

Supply and installation as described in the specification


and shown on the drawings to give a complete system
that is acceptabe to the Engineer and all local
authorities and under the following sections.

A Contractor is full responsibility is to coordination


Item

Supply, install,test and commission of the limited items


of the following, all as per the specification . Main
distribution boards including all necessary circuit
breakers,cables,conduits,ducts and trays from incoming
supply and all terminations as per drawings and
specifications and as per Kahramaa regulation

POWER

Supply install, testing and commissioning complete


Wiring devices with cover plates and outlet boxes
including conduits, wiring and all terminations

Removing Existing Electrical System Item

Power Outlets

A 13 A single switched socket LOT

B 13 A twin switched socket LOT

C 13 A single switched socket (weather proof) LOT

D shaver socket (dual voltage type) LOT

E 45A Cooker Unit + 45A Flex Outlet LOT


F 20A DP+E switch all split unit with 45A flex outlet LOT

G 16A power socket for equipments (weather proof) LOT

H power Isolators for AC Units (weather proof) LOT

I 20A Isolators for Water Pumps (weather proof) 2 No

J Modification of existing DB LOT

K Prepairing ASBUILT drawing for Electrical Services Item

Lighting fixtures delivered by the client

Note : Light fixtures, Swittches & Sockets


supplied by the Client

Supply, install, testing and commissioning complete


Light fittings including cabling, wiring, conduits and
switches in connections to permanent wiring system.

Chandliers, Spotlights, LED Tubes Various Light fittings


installation with necessory supports LOT

Switches

The rate of switches, isolating switches, switches,


panelboard shall include: Supply and installation of
switches Box in wall, support, wires and conduits from
switch to lighting point, and all necessary accessories
Labor, tools, transport, testing, one year guarantee, all
overhead expenses and profit.

A 20A 1 Gang 1 Way switches LOT No.

B 20A 2 Gang 1 Way switches LOT No.

C 20A 3 Gang 1 Way switches LOT No.

D 20A 1 Gang 2 Way switches LOT No.

Lumpsum Amount for Electrical Work QR


To Collection

QR
Carried To Summary

QR
RICAL INSTALLATIONS

QUANTITIES

TOTAL PRICE
(QR)
97,500.00
Bill No. 17C NETWORKING & CCTV
VILLA RENOVATION - AL KHOR
BILL OF QUANTITIES

ITEM UNIT RATE


ITEM DESCRIPTION QUANTITY UNIT
REF. (QR)

Bill No. 17C

NETWORKING & CCTV

1 camera

MP bullet camera 30 fps Resolution (Default camera


resolution is set to 5MP. ) 9 NO
2.8 mm Fixed Lens
Maximum IR Length 30 m (98 ft) with Smart IR
IP67 Ingress Protection

5 MP at 20 fps Resolution (Default dome camera


resolution is set to 5 MP. )
2.8 mm Fixed Lens 1 NO
Maximum IR Length 30 m (98 ft) with Smart IR

2 Storage

4K HDCVI DVR
DVR 16 Channel Penta-brid Recorder
Support for 16 Channels
Smart H.265+ and Smart H.264+ Dual Codec
4K at 7 fps Recording Resolution on all HDCVI
Channels P2P 1 Item
Automatically Detects HDCVI, AHD, TVI, and CVBS
Inputs
64 Mbps Incoming Bandwidthwith 4 TB HD

3 Monitor

40” Monitor with Video Wall Solution 1 Item

4 workstation

Intel Core i5 COMPUTER with min.4GB RAM,500 GB


HDD and Windows 7 Pro 64 Bit for the VMS and CMS 1 Item
Software Support with graphics Card

5 Data Points - for Telephone & Internet 10 No


24 Port POE Switch 1 Item

24 Port Patch Panel 1 Item

Cable Organizer 1 Item

6U Network Cabinet 1 Item

Cable Pulling and counduting with all meterials inclusing


fiber cable and meterials LS

Camera fixing and tuning LS

To Collection QR
MOI drawing preparation and approval LS

To Collection QR
CONTRACTOR'S ADJUSTMENT
Carried To Summary QR
TWORKING & CCTV

UANTITIES

TOTAL PRICE
(QR)
22,500.00
AL KHOR VILLA

SUMMARY
BILL NO. DESCRIPTION AMOUNT
Bill No. 1 PRELIMINARIES 7000.00 QAR
Bill No. 2 SITE WORKS 12500.00 QAR

Bill No. 3 CONCRETE 7000.00 QAR


Bill No. 4 MASONRY 85000.00 QAR
Bill No. 5 WOOD & PLASTICS 0.00
Bill No. 6 THERMAL & MOISTURE PROTECTION 63000.00 QAR

Bill No. 7 DOORS & WINDOWS 66000.00 QAR


Bill No. 8 FINISHES 172000.00 QAR
Bill No. 9 MECHANICAL (PLUMBING) 56450.00 QAR
Bill No. 10 MECHANICAL (DRAINAGE) 32650.00 QAR
Bill No. 11 MECHANICAL (FIRE FIGHTING) 950.00 QAR
Bill No. 12 ELECTRICAL 97500.00 QAR
Bill No. 13 CCTV 22500.00 QAR
Bill No. 14 PROVISIONAL SUM 25000 QAR
Bill No. 15 SCHEDULE OF DAY WORKS
GRAND TOTAL: QR
647550 QAR

Amount in Words:
(Carried to Form of Six hundred fourty seven thousand five hundred and fifty Qatari Riyals
Tender)