Daily Report 24 Maret 2023

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

CONTRACTOR

PT. BATARA MEGA KRIDA KENCANA


CLIENT
PT. INDOSAT Tbk
PROJECT IOH EXPERIENCE CENTER
LOKASI NO.PO WAKTU PENGERJAAN TANGGAL LAPORAN HARI KE SISA HARI
LANTAI 1 KPPTI 4800485379 126 Hari Jumat 24 Maret 2023 19 Hari 107 Hari 107
TENAGA KERJA
JUMLAH ORANG
ALAT - ALAT PEKERJAAN HARI INI PEKERJAAN YANG AKAN DATANG
NO STRUKTUR 8.00 - 22.00 19.00 - 06.00 BAHAN MASUK BAHAN KELUAR
14 Hour 11 Hour
1 Project Manager 1 1
2 Site Manager 1 2 A Pekerjaan Bongkaran : A Pekerjaan Bongkaran :
3 Supervisor 3 3 - Pembongkaran void - Pembongkaran void
4 Safety 1 1
5 Tukang Kayu 6 5
6 Tukang Gali 5 2
7 Tukang Batu 13 2
8 Tukang Cat 1 0

Team MEP B Pekerjaan Partisi & Ceiling : B Pekerjaan Partisi & Ceiling :
1 Supervisor ME 1 1 - Pemasangan hebel toilet - Pemasangan hebel toilet
2 Tukang Listrik 5 5 - Rangka partisi backdrop resepsion - Pemasangan gypsum 2 sisi
Tukang Plumbing
3 4 4 - Pemasangan rangka ceiling R meeting - Pemasangan rangka ceiling R meeting
Tukang AC 2 2 - Pemasangan penebalan J2 - Pemasangan penebalan J2
Start pemasangan rangka di area
- - pengecetan ceilling expose
google home
- Pembersihan area

C Buang Sampah / Puing C Buang Sampah / Puing

D Pekerjaan MEP : D Pekerjaan MEP :


- Instalasi penrangan - Pekerjaan Bongkaran existing MEP
- Pabrikasi ducting - Pabrikasi ducting
- Instalasi conduit - Pabrikasi springkler
- cable tray on site - Pekerjaan Cabling
- Cable tray on site

Total 42 27
DOKUMENTASI
INTERIOR FIT OUT

Pemasangan hebel toilet Bongkar Ceiling void Pemasang rangka ceiling ruang meeting

Start pemasangan rangka di area google


Pemasangan rangka partisi backdrop resepsion Pemasangan rangka j2
home
MEP WORKS

Instalasi penerangan Pabrikasi Ducting Instalasi conduit Cable tray on site


OUTSTANDING ITEM

A Outstanding item waiting approval from Indosat, we have not order the material :
1 Double Glass Partition & Door Works at Meeting Room and Waiting Lounge
2 Approval chair at Meeting Room : DONE , 20 March 2023
3 Strech Membran ceiling at Marvelous area
4 Approval Material for Furniture
5 Vynil because increase the volume

B Problem at Site :
1 Based on our survey with Pak Yanuar and Pak Asep this Firday, 17 March 2023 , they show us our new panel installation (1) but we need to demolish the existing panel first.
1. To do the demolition we need to track if that panel is still have electrical load or connected to other area. If no then we can shutdown and demolish it, if there is then it will be another thing.
2. Then we also need to demolish the existing cable (2) as many as we can and make it tidy to make space for our new cable installation. Because refer to the design, we need at least put 53 line installation cable inside panel area.
3. Then regarding the tapping point (3) the existing building don’t have 125A TOB and 160A TOB. For your information usually TOB (4) will take 8-10 weeks purchase. And since there is no TOB in contractor scope, please clarify.

2 Based On site Visit Selasa 21 Maret 2023 :


a Rak server existing bisa di buang

b Ada 1 Panel existing yang masih aktif dan masih terkonek untuk penerangan di area Lobby, IOH akan pastikan dan akan merelokasi panel tersebut.

c Kabel - Kabel existing Yang sudah tidak terpakai akan di potong dan di buang , dan yang masih aktif BMKK diminta untuk merapihkan kabel2 existing

d Kabel Antena & 5G. Akan di rapihkan oleh IOH

e Untuk Produksi ducting & springkler akan di lakukan di area BASEMENT, Lokasi sesuai yang sudah di tunjukan pada site visit 21 maret 2023.
Agar sirkulasi udara dilingkungan area kerja sehat untuk semua pekerja di lapangan

C INFORMATION
1 Gypsum Partition on Meeting room & Waiting Lounge have already instal 2 side , Please info Cisco to install cabling on this area.