Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)

Contract Package KA-1


Rehabilitating Water Supply and Sewerage in Soba Nagar
Bar Bending Schedule of Raft Foundation

Ref construction drawings

Shop Drawings

Sr# DESCRIPTION STEEL IN KG

SUMMARY FOR STEEL

1 Total Bar # 3 in Kg………………………………………………………………………………………………………… -

2 Total Bar # 4 in Kg…………………………………………………………………………………………………………

3 Total Bar # 5 in Kg…………………………………………………………………………………………………………… -

4 Total Bar # 6 in Kg …………………………………………………………………………………………………………

5 Total Bar # 8 in Kg ………………………………………………………………………………………………………… -

TOTAL STEEL (IN KG) -

SUBMITTED BY: HSAB APPROVED BY: NESPAK

NAME: …………………………………………. NAME: .…………………………………………………..

SIGNATURE: ……………………………….. SIGNATURE: ……………………………………………


DATE: ………………………………………… DATE: ……………………………………………………..
Bar Dia Wt (lbs/ft) Wt (kg/ft)
#3 0.376 0.171
#4 0.668 0.303
#5 1.043 0.473
#6 1.502 0.681
#7 2.044 0.927
#8 2.67 1.211
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar
Water Storage Tanks
Bar Bending Schedule of Slab at FFL (0'-0")

No. of Bars Total


Location Bar Nos of Bar Total Nos Cut Length
Sr. No. in each Bar Length Bar Shape
Top/Bottom Size Member C/C of Bars of each
member (ft.) (ft.)

BOTTOM BAR

8.5" 8.5"
1 B1 #4 1 6" 52 52 30.17 1,568.84 28'-9"

8.5" 8.5"
2 B2 #4 1 6" 52 52 30.17 1,568.84 28'-9"

8"
3 Extra bar #4 1 6" 208 208 9.17 1,907.36 8'-6"

TOP BAR

8.5" 8.5"
1 T1 #4 1 8" 40 40 30.17 1,206.80 28'-9"

8.5" 8.5"
2 T2 #4 1 8" 40 40 30.17 1,206.80 28'-9"

8"
3 Extra bar #4 1 8" 160 160 9.170 1,467.20 8'-6"

Size of Bar #4 Total (kgs)=

Unit Weight 0.302

Total Length 8,925.84 2,695.60

Weight (Kgs) 2,695.60

Page 4 of 40
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar

Water Storage Tanks

Bar Bending Schedule of Beams at EL(14'-0")

No. of
Nos of Bar Bars in Total Nos Cut Length of Total Length
Sr. No. Location Bar Size Bar Shape
Member C/C each of Bars each Bar (ft.) (ft.)
member

Bottom Main Bar B1

17'-9" 13"
1 Bar Mark 1 #8 4 4 16 19.920 318.72 13"

13" 17'-9" 13"


2 Bar Mark 3 #8 4 4 16 19.920 318.72

13" 17'-9" 13"


3 Bar Mark 5 #8 4 4 16 19.920 318.72

4 Bar Mark 8 #4 4 2 8 17.75 142.00 17'-9"

12"
Stirrup
5 #4@4" c/c at #4 8 4" 17 136 5.00 680.00 3" 15"
(L/4)

Bottom Main Bar B2

13" 17'-9" 13"


6 Bar Mark 1 #8 2 3 6 19.920 119.52

13" 17'-9" 13"


7 Bar Mark 3 #8 2 2 4 19.920 79.68

Page 5 of 40
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar

Water Storage Tanks

Bar Bending Schedule of Beams at EL(14'-0")

No. of
Nos of Bar Bars in Total Nos Cut Length of Total Length
Sr. No. Location Bar Size Bar Shape
Member C/C each of Bars each Bar (ft.) (ft.)
member

3'-7.5"
Bar Mark 4
8 #8 4 2 8 4.625 37.00

9"
@ support 13"

6'-0"
Bar Mark 4
9 #8 2 2 4 6.00 24.00
@ Mid span

12"
Stirrup
10 #3@4" c/c at #3 4 4" 11 44 5.00 220.00 3" 15"
(L/4)

12"

Stirrup 3" 15"


11 #3@6" c/c at #3 4 7 28 5.00 140.00
(L/4)

Page 6 of 40
N (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Project Implementation Unit
o
. Contract Package KA-1
o
Rehabilitating Water Supply and Sewerage in Soba Nagar
f
Water Storage Tanks
B
a
Bar Bending Schedule of UGWT Walls
r
s

Nos of Bar i
Sr. No. Location Bar Size Member C/C n Total Nos of Bars Cut Length of each Bar (ft.) Bar Shape

e
Walls of UGWT a
c
h

m
Main Bars e 6'-6"
Walls #6 4 7" ###
m 336 7.50
b
e
r 12"

8"
Main Bars
Walls #4 4 7" ### 336 12.25 11'-7"
11'-7"

2'-1" 27''-4"
Distribution
Inner Face #4 4 5" ### 124 29.41

Distribution 2'-1"
Outer Face #4 4 5" ### 124 30.75 28''-8"

SUMMARY OF STEEL
Size of Bar #6 #4 #3 Total (kgs)
Unit Weight 0.681 0.302 0.171
Total Length #REF! #REF! #REF!
Weight (Kgs) #REF! #REF!
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar
Water Storage Tanks
STEEL SUMMARY OF PLINTH BEAM (Pages 1 & 2)

Size of Bar #6
Unit Weight 0.681
Total Length #VALUE!
Weight (Kgs) #VALUE!

SUMMARY OF STEEL
Size of Bar #4
Unit Weight 0.302
Total Length 355.72
Weight (Kgs) 107.43

SUMMARY OF STEEL
Size of Bar #3
Unit Weight 0.170
Total Length #VALUE!
Weight (Kgs) #VALUE!
orporation (KW&SC)

Total (kgs)=

#VALUE!

Total (kgs)=

107.4300

Total (kgs)=

#VALUE!
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar
Water Storage Tanks
Bar Bending Schedule of Slab at FFL (0'-0")

No. of Bars Total


Location Bar Nos of Bar Total Nos Cut Length
Sr. No. in each Bar Length Bar Shape
Top/Bottom Size Member C/C of Bars of each
member (ft.) (ft.)

BOTTOM BAR

8.5" 8.5"
1 B1 #4 1 6" 52 52 30.17 1,568.84 28'-9"

8.5" 8.5"
2 B2 #4 1 6" 52 52 30.17 1,568.84 28'-9"

8"
3 Extra bar #4 1 6" 208 208 9.17 1,907.36 8'-6"

TOP BAR

8.5" 8.5"
1 T1 #4 1 8" 40 40 30.17 1,206.80 28'-9"

8.5" 8.5"
2 T2 #4 1 8" 40 40 30.17 1,206.80 28'-9"

8"
3 Extra bar #4 1 8" 160 160 9.170 1,467.20 8'-6"

Size of Bar #4 Total (kgs)=

Unit Weight 0.302

Total Length 8,925.84 2,695.60

Weight (Kgs) 2,695.60

Page 34 of 40
Project Implementation Unit (PIU) KWSSIP, Karachi Water and Sewerage Corporation (KW&SC)
Contract Package KA-1
Rehabilitating Water Supply and Sewerage in Soba Nagar
Water Storage Tanks
Bar Bending Schedule of Plinth beam 1 ( 0.00)

No. of Cut Total


Nos of Bar Bars in Total Nos Length of
Sr. No. Location Bar Size Length
Member C/C each of Bars each Bar
(ft.)
member (ft.)

PB1 (1'x1'-3") on P1 GRID A-C/1-3 & 1,3/A-C (4 NOS)

PB1 Top bar #6 4 2 8 30.25 242.00


9"

Bottom
PB1 #6 4 4 16 30.25 484.00
bar 9"

PB1 Mid bar #4 4 2 8 29.42 235.36

Top
extra bar
at
PB1 #6 12 2 24 3.25 78.00
Support
(C2) at
L/3

Top
extra bar
PB1 at Mid #6 8 2 16 6.17 98.72
Support
(P1)
Top
extra bar
PB1 at Mid #6 4 2 8 5.00 40.00
Support
(C1)

Stirrup
at
PB1 Support #3 4 4" 36 144 4.00 576.00
#3@4"
c/c

Stirrup at
Mid
PB1 #3 4 6" 18 72 4.00 288.00
#3@6"
c/c
PB1 (1'x1'-3") on C1 B-C/1-3 & 2/A-B (2 NOS)

PB1 Top bar #6 2 2 4 30.25 121.00


9"

Bottom
PB1 #6 2 4 8 30.25 242.00
bar
9"

PB1 Mid bar #4 2 2 4 29.42 117.68

Top
extra bar
PB1 at #6 4 2 8 3.25 26.00
Support
(C2)
Top
extra bar
PB1 at Mid #6 4 2 8 5.17 41.36
Support
(L/R C1)

Top
extra bar
at Mid
PB1 #6 2 2 4 6.00 24.00
Support
(Centre
C1)

Stirrup
at
PB1 Support #3 2 4 36 72 4.000 288.00
#3@4"
c/c

Stirrup
at Mid
PB1 #3 2 4 22 44 4.000 176.00
#3@6"
c/c
rage Corporation (KW&SC)

a Nagar

0.00)

Bar Shape

9" 28'-9" 9"

9" 28'-9" 9"

28'-9"
4"

4"

2'-6"
9"

6'-2"
5'

9"

3" 12"

9"

3" 12"

9" 28'-9" 9"

9" 9"

28'-9"

28'-9"
4"

4"

2'-6"
9"
9"

5'2"

6'

9"

3" 12"

9"

3" 12"