Professional Documents
Culture Documents
Initial lateral Load Test Methodology_Joka
Initial lateral Load Test Methodology_Joka
A. Test Procedure:
Preparation of Pile surface at test location:-
The outer side of the pile shaft at Cut-Off level will be cleaned and chipped off the undulation
at Jacking location/ COL. Smooth finishing will be done by 1:3 cement sand mortar for fixing
MS base plate.
Reaction Arrangement:-
Reaction will be taken from reaction pile/ suitable reaction point as per the drawing
attached (Annexure -I). MS plate of 16 mm to 40 mm thick will be placed at the cleaned
and finished surface of test pile and reaction point. Subsequently the Hydraulic Jack will be
placed horizontally in between reaction point and the test pile. The test load will be applied
by means of one no. hydraulic Jack of 400MT capacity.
One no datum bars will be fixed on immovable supports on opposite side of Jacking point of
test pile. The both ends of datum bar will be fixed at a distance of 3d (subject to minimum
of 1.5m.) from the edge of pile where d is the dia of test pile and the level of datum bar will
be 50mm to 100 mm above the COL level. One no. calibrated dial gauges of 0.01mm
sensitivity; will be positioned at COL level of test pile. The tips of the dial gauge shall touch
on the central portion of the square or rectangular glass plate fixed over the finished vertical
surface of the test pile.
B. Physical Data:
1. Test Pile No - “03”
2. Test Pile Size - 1200mm Dia.
3. Location of Pile - Near Joka Tram Depot
[N-2483262.4467, E-633778.3247]
4. Date of Concreting - 11th June, 2011
Page 1 of 4
C. Technical Details:
1. Grade of Concrete - M35
2. Cut-off Level of Pile - (+) 0.850 m
3. Founding Level - (-) 27.150 m
4. Load Applied at - (+) 0.850 m
5. Reinforcement Details - As per drawing no- 3/SE/MISC-0905
Page 2 of 4
E. Load Chart
Theoretical Actual Actual
Theoretical
Sl. Stage of Percentage of Application application application
Application of
No Loading Load of pressure of pressure of Load (MT)
Load (MT)
in Kg/Sq cm in Kg/Sq cm
01 1st Increment 20 % 24.213 4 20 3.304
F. Application of Load :-
Load will be applied through hydraulic Pump arrangement and the load can be
calculated by a pressure gauge. Application and increment of load will be
done as per the load chart shown above,
The horizontal pile load test data essentially accounts for three variables and these
are Load, Horizontal/Lateral Deflection and Time. All these will be recorded
sequentially for the tests under consideration and recorded in a Data Sheet, shown
below,
H. Data Sheet
Page 3 of 4
Elapsed Time in
Pressure in Kg/
Date/ Time
Load in MT
Load in %
Reading of
Sq.cm.
Min.
D1 Remarks
I. Conclusion :-
Ultimate/ Safe capacity of pile will be calculated As per IS 2911 Part-IV.
Page 4 of 4