Seminar Report on
Activity Network
Submitted by :
Aditya Joshi 2SD21CS006
Nagesh Sortur 2SD21CS056
Exercise to Create an Activity Network Diagram
Figure: Activities
Forwad Pass
Result :
The critical path of this project is B – E – G – I – L – M. It is the longest path.
B – E – G – I – L – M: 2+1+3+4+4+1=15 weeks