Advanced Data Structures

Seminar Report on
Activity Network
Submitted by :
Aditya Joshi 2SD21CS006
Nagesh Sortur 2SD21CS056
Exercise to Create an Activity Network Diagram

Figure: Activities

Early Start Duration Early Finish


Task Name
Late Start Slack Late Finish

Figure : Activity Node with labels


Figure : Activity Network Diagram with Duration

Forwad Pass

Figure: Completion of Forwad Pass


Backward Pass

Figure : Completion of Backward Pass

Result :
The critical path of this project is B – E – G – I – L – M. It is the longest path.
B – E – G – I – L – M: 2+1+3+4+4+1=15 weeks