shash-qarra-2018-cash-flow-management-of-construction-projects-in-saudi-arabia

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Article

Project Management Journal


Vol. 49(5) 48–63
Cash Flow Management of Construction ª 2018 Project Management Institute, Inc.
Article reuse guidelines:
sagepub.com/journals-permissions
Projects in Saudi Arabia DOI: 10.1177/8756972818787976
journals.sagepub.com/home/pmx

Ali A. Shash1 and Abdulaziz Al Qarra2

Abstract
Cash flow management entails forecasting, monitoring, and controlling practices of the cash inflow and outflow and arrangement
of deficits over a project’s duration. This article reveals, through a questionnaire survey, the techniques and practices that
construction companies in the Eastern Province of Saudi Arabia follow to forecast and manage cash flow at the project level. The
majority of the contractors perform cash flow forecasting for setting a cash flow baseline and determining the proper financing
method. They use credit financing for materials, subcontract a good portion of projects, and use company assets and credit
financing to pay for equipment and labor.

Keywords
cash flow, Saudi Arabia, management, practices, construction, deficit

Introduction in a project. Thus, to ensure a healthy and stable financial


performance for a firm, it is necessary to construct an effective
Cash flow is a term used to describe the pattern of cash move-
cash flow forecasting model (Halpin & Senior, 2009), followed
ment into (income) and out (expenditure) of a business and the
by proper management of cash inflow and outflow.
resulting availability of funds at any given time. Cash flow is
In a construction project, a contractor’s cash flow occurs
considered the main indicator of a business’s financial health.
over the construction contract duration, as shown in Figure 1.
Exercising proper cash flow management is crucial to the sur-
The construction contractor uses cash from equity, advanced
vival of businesses. Cash flow management refers to the prac-
payment, and/or debt to finance initial construction operations
tices that are adopted to balance income and expenses; it entails
and expected overdrafts whenever a contract dictates retention
forecasting (planning), monitoring, and controlling practices of
of a certain percentage of progress payments. The construction
cash inflow and outflow and the arrangement of deficits over
contractor uses available cash to purchase materials and to pay
the life of a business. Construction companies exercise cash
for labor, overhead, subcontractors, suppliers, and vendors. The
flow management at both the company and project levels. The
combination of these resources is transformed into a finished
latter is the concern of this study.
product. This finished product typically takes the form of a
Starting a partial or a complete project subjects a contractor
completed or partially completed construction work. The proj-
to a major risk emerging from the cash flow impact of this new
ect owner values the completed or partially completed con-
work. To ease this risk, according to many researchers, the
struction work, based on an agreed-upon valuation method,
contractor forecasts the cash flow, measures the amount of
and pays a certain amount of cash to compensate the contractor
needed investment before the project produces positive cash
for the finished goods. The ratio of the compensated amount to
flow, and manages the actual cash flow during the construction
process. Forecast analysis aids the contractor in selecting the
proper financial technique that corresponds to the predicted 1
cash flow of project expenses (Gatti, 2008). Proper cash flow Construction Engineering and Management Department, College of
Environmental Design at King Fahd University of Petroleum and Mineral,
management ensures the correspondence of actual cash flow Dhahran, Saudi Arabia
with the set cash flow baseline. Financial success for a firm 2
Dhahran, Saudi Arabia, JLL (Jones Lang LaSalle) MENA, Saudi Arabia
does not depend on the volume of the firm’s capital. Rather, for
a firm to be financially successful, it should have the ability to Corresponding Author:
Ali A. Shash, Construction Engineering and Management Department, College
fulfill its obligations in the various transactions it undertakes. of Environmental Design at King Fahd University of Petroleum and Mineral,
In other words, the firm should manage its cash in a way that Dhahran, Saudi Arabia.
can give it a further view of the different financial transactions Email: aashash@kfupm.edu.sa
Shash and Qarra 49

1 2
Equity Cash Flow Out
Cash Cash
Advanced Payment
Flow Flow Purchase Fixed Asset
Debt In Out Purchase Raw Materials
Cash for Labor Salaries
3
a Project Subcontractors’ Payments
Progress Payments Suppliers’ Payments
Direct Overhead

Compensation
Finished Transformation
Processes Project Processes

Figure 1. Cash flow cycle.

the contractor’s expended amount for a completed or partially offered techniques to manage cash flow properly. Unfortu-
completed construction work is a function of the contractor’s nately, the offered techniques concentrated on the development
efficiency and the agreed-upon percentage of retention. of models for forecasting cash flow over the duration of a
The payment amount is reduced by a retainage, a certain construction project, and very little work has been reported
percentage of the payment that has the effect of keeping a on the practices that contractors follow to manage cash flow.
contractor in negative cash flow for a long duration and, in Although the literature is rich in cash flow and cash flow tech-
many cases, for the total duration of the project. High ratio nique studies, the Saudi construction industry’s usage of these
of payment to expenses means excellent recovery of expen- studies and practices in managing cash flow has yet to be
ditures. As a matter of fact, recovering good amounts of investigated. This study is an attempt to reveal the practices
expenditures in terms of cash from progress payments leads that are followed by construction companies in the Eastern
contractors to borrow minimum amounts of money that are Province of Saudi Arabia to forecast and manage cash over the
close to the amount of the retained money and allows them duration of projects. It is hoped that such a study will lead to
to finance ongoing construction operations properly. A con- more advanced treatments of contractors’ cash flow manage-
tractor funds construction costs for a period that may ment and, hence, prevent contractors in Saudi Arabia in
extend to 60 days before recovering such expenditure in particular, and in other countries in general, from facing cash
the form of progress payments from the owner. Contractors flow-related failure.
commonly find themselves in a position where they have to
pay for labor, materials, and suppliers for longer periods
than the scheduled payments dates if there are delays in
Research Objective
receiving the progress payments. The main objective of this study is to reveal and describe the
Contractors follow certain procedures to manage income techniques and practices that construction companies in the
(inflows), expenditures (outflows), and deficits in their proj- Eastern Province of Saudi Arabia employ to forecast and man-
ects. Proper management of these components is essential to age project cash flow.
the survival of construction companies. For years, the unavail-
ability of cash as a result of cash flow problems has been a
major cause of insolvency for many contractors. This was iden- Literature Review
tified in the 1970s and, since then, many researchers have Cash flow is the difference between cash spent and cash
emphasized the importance of cash flow management to the received by a firm during a specific period of time (Tarek &
survival of construction companies, because cash is a crucial Yaqiong, 2014). Cash flow management mandates the applica-
resource to the contractor’s day-to-day activities and a means tion of practices in managing project cash flow against a set
to obtain loans from banks (Odeyinka, Kaka, & Morledge, baseline. Actually, the accurate estimation of cash flow in the
2003). Tarek and Yaqiong (2014) reported that inadequate early stages of a project is considered a vital factor that pro-
control of cash flow caused many construction companies to vides an indication of the project’s financial significance.
leave the industry. Al-Barrak (1993) found that cash flow man- Cash flow planning is the charting of cash movement into
agement is one of the major financial issues that cause contrac- the production process, then into accounts receivable, and back
tors to go bankrupt in Saudi Arabia. Hence, researchers have into cash. Cash flow planning is a crucial step in making
50 Project Management Journal 49(5)

significant decisions concerning how to liquidate a project with and corresponding level of risk that may emerge from the use
the cash. Cash flow forecasting guides the contractor to the of the financing technique (Crundwell, 2008). When it comes
amount of cash needed for the project and to how to return this to financing a construction project, the contractor’s goal will be
amount to the account from which it was borrowed (Ross & to finance the negative gap between project expenses and proj-
Williams, 2013). Halpin and Senior (2009) indicated that fore- ect revenues with the aim of achieving the optimum possible
casting cash behavior over a project’s duration is a crucial key amount to finance; thus, the contractor’s loans cost will be the
for controlling project cash effectively. In addition, performing least (Halpin & Senior, 2009). Although the project’s financial
a thorough cash flow analysis for a project is necessary to nature is that an owner pays a contractor periodic (progress)
eliminate or to minimize the possibility of financial failure payments, the contractor may face various financial problems
(Kenley, 2003). along the project’s progress. The owner’s progress payments
Many researchers have developed probabilistic and mostly may be delayed, which will affect the progress of the project,
deterministic models for cash flow forecasting, with some var- unless the contractor has the financial ability to temporarily
iations in their accuracy and detail, the degree of automation in cover this negative cash value. Project expenses that exceed
compiling them, time and money integration methods, and so the cumulative progress payments paid by the owner to the
forth (Mutti & Hughes, 2002). Bromilow (1978), Peer (1982), contractor cause this situation (Hendrickson, 1998). This gap
Isidore and Back (2002), Boussabaine and Elhag (1999), between revenues and expenses is referred to as working cap-
Tucker (1986), Kenley and Wilson (1986), Kaka and Price ital, which is a source of power for a contractor in commencing
(1993), Miskawi (1989), and Boussabaine and Kaka (1998) a project. The term defines the remaining amount of available
developed deterministic models for forecasting and managing cash that the contractor has after deducting the amount of
cash flow at the project level. In contrast, Purnuş and Bodea current liabilities (Steffan, 2008). This working capital is the
(2015) argued that projects are highly dynamic, and a determi- figure that will guide the contractor in the decision to use
nistic analysis does not provide a realistic view of the financial available credit lines or look for new sources of capital by using
efforts that a contractor has to make. They also discussed the corporate finance (Yescombe, 2014).
fact that focusing on the individual project level does not Unfortunately, most of the previous research has suggested
reflect the overall risks at the corporate level, and that the techniques for setting baselines for cash flow, but very few
simple sum of an individual project’s risks can be significantly researchers have addressed the practices that contractors follow
different from the total corporate risks. Some researchers have to manage these cash flows. Odeyinka et al. (2003) surveyed
developed models for forecasting and managing cash flow at United Kingdom contractors on the approaches they use to
the organizational level. Navon (1996) developed a cash flow resolve deficit cash flow, their cash flow monitoring methods,
management system to forecast cash flow at the company level. the frequency of cash flow updating, and the methods they used
Cui, Hastak, and Halpin (2010) developed a system dynamics for forecasting cash flow. They found that contractors resolve
model for project cash flow management. They used a ware- deficit cash flow through different means including, in order of
house project to demonstrate the flexibility of the model in priority, the company’s cash reserves, tender balancing,
incorporating cash flow management strategies and predicting delayed payment to subcontractors, delayed payment to sup-
project cash flows. Purnuş and Bodea (2015) presented a prob- pliers, use of company assets, and borrowed funds. On the other
abilistic cash flow analysis model, which allows integration of hand, many researchers have addressed and reported on cost
risk events and uncertainties such that the model becomes a control against set budgets. Readers interested in cost control
true decision tool that can be applied at the project’s portfolio practices are referred to published work on this subject.
level. They claim that when contractors apply the proposed
model, they avoid high financial exposures and losses. Further-
more, the modeling of the cumulative behavior of all projects Research Methodology
allows contractors to predict not only when but mostly what This section presents the steps that were followed to achieve
amount of money should be borrowed or obtained from internal the objective of the study, which is to identify and describe the
or external sources and when and what amount of money practices that construction companies in the Eastern Province
should be returned. Ross and Williams (2013) claim, however, of Saudi Arabia follow to manage project cash flow. This study
that many simple cash flow models, other than that presented employed a postal survey, the most popular method used by
above, may not take into account uncertainties and the effects many researchers in descriptive studies (Watson & Noble,
of many factors on project cash flow. 2007), to collect the necessary data from construction contrac-
The internal earnings of a construction company and/or tors. As compared to face-to-face interviews and the Delphi
commercial banks’ financial facilities are two main sources method, the method used here is both cost and time effective.
contractors use to finance the operations of a construction proj- The first step involved reviewing published relevant literature.
ect (Halpin & Senior, 2009). Selecting the financing method The review of pertinent published literature helped us study
depends mainly on the degree of accuracy with which a con- various financial management systems. The literature review
tractor can estimate cash flow during the duration of the project also helped to develop the necessary tool—a structured ques-
(Hendrickson, 1998) and the type of project delivery system tionnaire—for collecting the needed data. The questionnaire
Shash and Qarra 51

consisted of five sections. The first section contained questions where 1 represents very much suitable/very effective/very rea-
related to the company, such as size, location, number of cur- sonable/very low risk and 5 represents not suitable/very expen-
rent projects, age, and so on. The second section contained sive/very high risk.
questions related to respondents’ (the information providers)
characteristics, such as educational background, experience,
position in the organization, and so forth. The third section Data Analysis and Results
contained questions related to financial transactions and cash
flow management. The fourth section consisted of questions on Because the population is small, a structured questionnaire was
current financing techniques. The last section provided space distributed in the last quarter of 2014 via email to the 86 con-
for the respondents to suggest new financial techniques. tractors. The contractors were asked to complete and return the
The second step was collecting the necessary data via the questionnaire to the researchers at their convenience but no more
structured questionnaire from the top management of grades 1, than three weeks later. The questionnaire was followed up with
2, and 3 contractors located in the Eastern Province of Saudi emails and telephone calls to remind and encourage financial
Arabia. The Classifying Directorate of the Ministry of Munici- managers to participate in the study. Twenty-five financial man-
palities and Rural Affair classifies contractors into different agers from different companies completed and returned the
specialties (building, industrial, highway, etc.) and into five questionnaires over 12 weeks. Improving the reliability of the
grades based on qualification criteria for bidding on govern- collected data mandated accepting only questionnaires that had
ment projects. Each graded contractor is given an upper limit at least 80% of their contents duly completed. All the returned
for the projects on which they may bid. Grades 2, 3, 4, and 5 questionnaires satisfied the above restriction and comprised the
building contractors, for example, have upper limits for proj- total number of participants. This means that 29% of the popu-
ects with values of 280, 70, 21, and 7 million Saudi riyal, lation participated in the study, which is considered a typical
respectively. Grade 1 contractors have no upper limit. Other norm of a 20% to 30% response rate in most postal question-
types of contractors are classified in a similar fashion with naires surveying the construction industry (Akintoye & Fitzger-
comparable or different upper limits. The directorate lists 86 ald, 2000). In addition, the 25 participants are greater than the
classified contractors in the Eastern Province. We used the calculated minimum sample size and, therefore, form a reliable,
following statistical formula to determine the minimum suit- acceptable, and representative sample.
able sample size to represent the population. This exercise
revealed a minimum of 20 contractors to comprise a represen- Characteristics of Participants
tative sample of the above population: This section presents the characteristics of the contractors and
pq personnel who completed the questionnaires. Tables 1 and 2
n0 ¼ 2
e summarize the characteristics of the participants and their
n0 employers, respectively.
n¼ n The results indicate that the majority of the participants are
1þ 0
N well educated with college degrees, with about (50%) holding
master’s or doctorate of philosophy degrees. The majority
In the equation, p ¼ 0.5, q ¼ (1-p) ¼ 0.5, e (desired level of
(about 63%) of the respondents’ educational degrees are in
precision) ¼ 10%, and N ¼ population (Lipsey, 1990).
financial management and the remainder are in engineering,
The third step was to analyze the collected data using simple
with extensive experience and training in financial manage-
statistical tools such as frequency, mean, and standard devia-
ment. The majority (54% of the participants) have more than
tion. Simple mathematical techniques, such as percentage and
10 years of experience in the construction industry, and about
average, were used in analyzing the data. However, in addition
54% of these participants have been with their current
to these techniques, importance and severity indices were cal-
employers for more than five years. The results indicate that
culated to reflect the relative severity of the relevant factors
almost one half of the respondents are from the contractors’
over the others. The indices were calculated as follows:
top management positions—that is, general manager, opera-
P5 tions manager, project manager, or director. On the other
1 ai xi
Importance Index ¼ hand, it was found that about one third of the respondents are
5S x i
managers and managers’ assistants in the finance departments
Where: of their organizations.
ai ¼ Constant expressing the weight given to i; xi ¼ variable The results indicate that the participants are employed in
expressing the frequency of the response for i ¼ 1, 2, 3, 4, 5 contracting organizations, which, in the majority of cases
(Likert, 1932). For measuring the level of effect of variables on (67%), have been in existence for more than 10 years. This,
a project financing, a scale of 1 to 5 was used, where 1 repre- of course, ensures that the respondents represent well-
sents a very severe effect and 5 represents no effect. For mea- established firms. The head offices of most of the organizations
suring the suitability, finance effectiveness, cost, and involved are located in the Eastern Province of Saudi Arabia and very
risk in various financing techniques, a scale of 1 to 5 was used, few are located in other cities, such as Riyadh and Jeddah.
52 Project Management Journal 49(5)

Table 1. Respondents’ Characteristics

Characteristics Distribution

Educational level Diploma Bachelor’s degree Master’s degree PhD


4% 62.50% 25% 8.50%
Education in finance Yes No
management 63% 37%
Years of experience Less than 5 5 to less than 10 10 to less than 15 15 to less than 20 20 to less than 25 Equal to or more than 25
in current position 50% 25% 12.50% 4% 0 8.50%
Years of experience Less than 5 5 to less than 10 10 to less than 15 15 to less than 20 20 to less than 25 Equal to or more than 25
in current organization 46% 20% 30% 0 0 4%
Years of experience Less than 5 5 to less than 10 10 to less than 15 15 to less than 20 20 to less than 25 Equal to or more than 25
in construction 25% 21% 16.50% 8.50% 12.50% 16.50%
industry

Table 2. Organization Characteristics

Characteristics Distribution

Organization age Less than 5 5 to less than 10 10 to less than 15 15 to less than 20 20 to less than 25
Equal to or
more than 25
20% 16% 16% 20% 8% 20%
Number of employees Less than 50 50 to less than 200 200 to less than 500 500 to less than 700 700 to less than Equal to or
1,000 more than 1,000
20% 20% 20% 4% 4% 32%
Average construction Less than 100 100 to less than 200 200 to less than 500 500 to less than 700 700 to less than Equal to or
contracts executed 1,000 more than 1,000
annually (million SR1) 25% 37.50% 4% 4% 12.50% 17%
Organization capital Less than 1 1 to less than 10 10 to less than 50 50 to less than 100 100 to less than Equal to or
(million SR) 500 more than 500
8% 46% 8% 8% 16.50% 13%
Organization location Dammam Khobar Jubail Dhahran Riyadh Jeddah
32% 28% 0 4% 32% 4%
Types of executed Building Industrial Infrastructure Special construction Utilities
projects 76% 44% 40% 36% 28%
1
Saudi riyal (US$1 equals 3.75 SR)

About 32% of these organizations employ more than 1,000 Cash Flow Management
staff members. The combined extensive experience, rich
Cash flow commences with securing cash to fund project oper-
knowledge in the Saudi construction industry, and the large
ations. Contractors must spend to purchase necessary materials
staff size give these participating contractors the capability to
and equipment, pay laborers and management, and to receive
build large projects (buildings, industrial, highway, utilities,
cash from the owner based on partially or completely finished
and infrastructure) and to generate large annual revenues. The
work. Cui et al. (2010) stated that contractors develop auto-
results indicate that the majority of the participating organiza- mated cash flows with the integrated cost-schedule method,
tions (37.5%) sign yearly contracts with an average amount which involves a detailed project schedule with full costing
between SR100 and SR200 million. The results also show that based on the bill of quantities. The following sections present
a significant portion of the participants (about 29%) signs con- the methods that construction contractors in Saudi Arabia
tracts with an average amount of more than SR700 million implement to forecast and manage their projects’ cash flow.
yearly. This combination of the different sizes of the projects
undertaken by the participating contractors is a good factor,
which improves the quality of the results, as it provides Cash Flow Analysis
research findings representing a wider view of the industry. Cash flow analysis is an important financial activity for a proj-
Collecting the necessary data from personnel of such caliber, ect and entails listing money flows into and out of a project.
with this level of experience in financial issues, lends confi- Cash flow analysis enables a contractor to project future flows
dence regarding the quality of the information, and, hence, the of cash to determine the necessary budget for a project. Cash
results and findings obtained. flow analysis is not concerned with the amount of the cash flow
Shash and Qarra 53

Table 3. Purpose of Cash Flow Forecasting

Number of 5%
Purpose Responses Percentage
5%
5%
Determine the liquidity of the company 1 4
Set cash flow baseline for control purposes 22 85
Determine the financing method 18 70
15%
Determine the amount of money cost to 15 60
include in the bid price
Determine the amount of overdraft 11 45 60%
10%
alone, but also the timing of these cash flows. Most cash flow in
the construction industry is analyzed with monthly time peri-
ods. Cash flow analysis projects the cash balance at the end of
each month.
The results of this study indicate that the majority (76%) of None
Less than 5%
the participating contractors perform cash flow analysis or 5% to less than 10%
forecasting prior to bidding for a project. It was expected that 10% to less than 15%
all contractors would indicate that they perform cash flow 15% to less than 25%
analysis but, surprisingly, 24% of the participating contractors
responded negatively and stated that they do not analyze cash
Figure 2. Percentages of contracts that fail annually because of poor
flow for their projects. It seems that those contractors may cash flow management.
refrain from performing cash flow analysis for reasons related
to time and budget limitations during the pre-bidding stages
This may indicate that some contractors in Saudi Arabia may
and possibly because of previous unsuccessful experience with
apply poor financial practices.
cash flow analysis.
The results indicate that 40% of the participating contractors
The participating contractors delineated several benefits
encounter financial failure in their annual signed contracts,
from performing cash flow analysis. Table 3 presents the pur-
most likely as a consequence of their poor implementation of
poses of conducting cash flow analysis or forecasting, as per-
cash flow analysis and projections. This failure, resulting from
ceived by contractors in Saudi Arabia. Setting a cash flow
poor cash flow management, ranges from less than 5% to more
baseline for control purposes was cited by 85% of the partici-
than 25% of the annual signed contracts. The failure distribu-
pating contractors as one of the benefits they gain from cash
tion is shown in Figure 2. It is alarming to find this large
flow analysis. It seems that contractors are successful in setting
number of contractors facing sizeable project failures in their
cash flow plans, which they monitor and control over the life of
annual contracts because of poor cash flow management. The
a project. Moreover, 70% of the participating contractors
results of the study indicate that the majority of the contractors
reported that they benefit from cash flow forecasting or anal-
who encounter failures in their annual project contracts, attri-
ysis in determining the proper financing method for projects.
butable to poor cash flow management and forecasting, are
Working capital is an important part of a cash flow analysis.
those contractors who do not perform cash flow analysis prior
Computing the amount of working capital gives a contractor a
to submitting bids for projects.
quick evaluation of the liquidity of the project over its con-
Cash flow, as defined previously, is the process in which
struction period. Accordingly, the contractor decides on the
cash inflow and cash outflow are monitored and controlled.
source(s) for funding the working capital. Determining the
Accordingly, to manage the cash flow is to manage its compo-
working capital accurately helps contractors liquidate projects
nents—namely, cash flow out and cash flow in.
with ease and comfort.
Cash flow analysis, as reported by 60% of the participating
contractors, assists them in determining and including the cost
of financing in bid prices. Only 45% of the participating con- Cash Flow Out: Project Expenditures
tractors reported that they forecast cash flow to determine the A contractor expends available cash during the project con-
amount of overdraft. Calculating the overdraft amount plays a structing process. These expenditures are classified as either
vital role in determining a suitable financing method; less than direct or indirect costs. Direct costs consist of materials, equip-
50% of the participating contractors, however, conduct cash ment, labor, subcontractors, suppliers, and job overhead costs
flow analysis to determine the amount of the overdraft. It could that are traced back directly to the project. The direct cost
be inferred that the participating contractors conduct simple signifies the highest percentage of the total cost of a project.
cash flow models, which fail to determine the amount of over- Thus, the direct cost should be managed closely to maintain a
draft and, hence, decide on the suitable financial technique. positive financial status for a project. The indirect cost category
54 Project Management Journal 49(5)

Percentage of Respondents 50%

40% 44%

30%
30%
20%

10% 13%
9%
0%
4%
Less than 20% to less 30% to less 50% to less Equal to or
20% than 30% than 50% than 70% more than 70%

Figure 3. Materials cost contribution to total project cost.

includes cost items, such as office overhead, which are not comprised less than 20% of the total cost of the projects he had
directly traced back to a particular project. Office overhead constructed. The researchers observed from this contractor’s
includes costs that are generated by management and adminis- profile that he offers services that are limited to industrial
trative activities. Unlike direct costs, indirect cost marks a equipment installation and operation. At the other extreme, two
small percentage of the total cost of a project. Typically, over- contractors (9%) stated that the materials cost represents more
head accounts for less than 5% of the total project cost (Halpin than 70% of the total project cost. It was observed that these
& Senior, 2009). two contractors construct special structures, such as railways
The participating contractors revealed the direct and indirect and precast concrete buildings, where materials have a very
costs (cash flow out) of their undertaken projects. high contribution to the total costs of the project. Material cost
contribution to a project total cost is presented in Figure 3.
The participating contractors indicated that they pay mate-
Direct Cost rials suppliers using a combination of various financing tech-
The participating contractors identified as direct costs the pur- niques. It seems that contractors value the importance of
chased materials and equipment, as well as payments to timely availability of materials and, hence, rely less on limited
laborers, subcontractors, and project management. These are sources to fund this cost item. The majority (56%) of the
the primary sources of cash outflow and are considered and contractors use credit financing for materials. Contractors
accounted for as part of the project direct cost. prefer credit financing because they pay for the delivered
materials after a certain period of the delivery date, which is
typically 30 days. This arrangement gives contractors ample
Materials time until owners pay them against the incurred materials
The constituents of a finished or partially finished product are cost. About 44% and 48%, respectively, of the contractors use
the sources of the material costs. The majority (44%) of the progress payments and advance payments to pay for materi-
participating contractors reported that the material costs als. Few contractors (16% of the participants) pay suppliers
accounted for 30% to 50% of the total costs of projects they from their own accounts.
constructed. Ross and Williams (2013) reported similar find-
ings and stated that the contribution of material costs in con-
struction projects typically ranges from 30% to 50% of the total
Labor
project cost. The results still indicate that about 30% and 13% Labor cost is the sum of all wages paid to laborers, as well as
of the participating contractors reported that materials cost the cost of labor benefits. Contractors in Saudi Arabia pay
comprised 50% to 70% and 20% to 30%, respectively, of the workers monthly and usually at the end of the Gregorian
total costs of the projects they constructed. It seems that the month. The majority (83%) of the participating contractors
participants contract for projects with different scopes of work. reported that the labor cost contributes less than 30% to the
For example, in some contracts, the contractor is responsible total cost of the project. Ross and Williams (2013) reported
for supplying all or most of the project materials, whereas in similar labor cost contributions to total project cost. This per-
other contracts, the owner participates in providing a signifi- centage represents the contractor labor cost contribution and,
cant portion of the materials. This observation was clear from hence, could be marginally higher.
the answers furnished by the remaining participating contrac- Contractors may engage subcontractors to execute parts of a
tors. Interestingly, one contractor indicated that materials cost project. It seems that contractors in certain circumstances
Shash and Qarra 55

Percentage of Respondents 60%

50%
50%
40%

30% 33%

20%

10% 13%
4% 0%
0%
Less than 20% to less 30% to less 50% to less Equal to or
20% than 30% than 50% than 70% more than 70%

Figure 4. Labor cost contribution to total project cost.

prefer to hire subcontractors to provide laborers to execute Table 4. Techniques Used to Pay for Equipment in Construction
elements of the project rather than hire laborers directly. One Projects
contractor reported that the labor cost contribution ranges from
Techniques Number of Responses Percentage
50% to 70% of the total project cost. It seems that this contrac-
tor provides his services to owners who supply most of the Advance payment 4 16
needed materials; thus, the scope of the contractor in these Company assets 15 60
contracts is mainly limited to providing the needed workforce Bank loans 4 16
Progress payments 9 36
for the project. Labor cost contribution to total project cost is
Credit 6 24
presented in Figure 4.

Subcontractors of time. On the other hand, when a contractor needs equipment


for a project for long periods of time, the results indicate that
The majority (78%) of the participating contractors reported 36% of the contractors use periodical payments, which coin-
that subcontracting work typically contributes 20% to 50% of cide with the project progress payments, to pay for the equip-
the total cost of the projects they have constructed. However, ment. It seems that contractors are successful in selecting,
the amount of subcontracted work varies from one project to based on the need duration, suitable and cost-effective financ-
another and from one contractor to another, depending on the ing methods for acquiring needed equipment. Table 4 presents
contractor’s internal policies, resource limitations, and the contractors’ schemes for financing needed equipment.
ongoing projects.

Mobilization
Equipment
The results demonstrated that about 88% of the participating
A high proportion of the participating contractors—almost contractors reported that mobilization costs typically account
83%—reported that the equipment cost (owning and operating) for less than 3% of the total project cost. The majority (80%) of
comprises less than 20% of the total project cost, although the participating contractors pay for mobilization costs using
about 8% stated that their average equipment cost was between the owners’ advance payments, when applicable. About 44% of
50% and 70% of the total project cost. Because the nature of the the participating contractors reported that they use their own
projects undertaken by the different contractors varies, it is cash to liquidate mobilization costs. The other contractors
understandable that there would be such a high variance in showed different financing modes, such as bank loans and lines
equipment cost. Most of the participating contractors construct of credit.
buildings, which are labor intensive rather than equipment
intensive. In addition, some contractors undertake projects that
rely mainly on providing costly types of special equipment.
Overhead
The results indicate that the majority (60% and 24%, respec- The results indicate that about 88% of the participating con-
tively) of the participating contractors use company assets and tractors stated that the project overhead cost was less than 10%
credit financing to pay for the equipment hired for short periods of the total project cost. Similarly, about 80% of the
56 Project Management Journal 49(5)

Table 5. Cost Items Amounts and Finance Sources Advance Payment


Cost Average Percentage of Major Finance In some construction contracts, an owner agrees to pay the
Category Cost Items Total Project Cost (%) Source contractor an advance payment to finance early activities,
Direct Materials 43% Credit
including mobilization and setting up work. The majority
Cost Equipment 10% Company assets (88%) of the participating contractors reported that they receive
Manpower 15% Company assets advance payments when contracting with some owners. Some
Subcontractor 20% Progress of the participating contractors (41%) indicated that they
payments receive advance payments in 10% to less than 15% of their
Mobilization 2% Advance payment contracts. Interestingly, other contractors (42%) indicated that
Indirect Overhead 10% Company assets they receive the same percentage of advance payment in more
Cost
than 25% of their annual secured contracts. This variance in the
results can be explained by the fact that advance payment is
agreed upon based on the type and size of the project; thus, not
participating contractors indicated that the general overhead all of the executed projects by contractors need this type of
cost was less than 10% of the total project cost. However, other payment in the beginning of the project. Sometimes, the con-
contractors reported that the overhead cost barely reached 30% tractor has the ability to finance the project easily at that stage.
of the total project cost. The results indicate that 50% of the participating contractors
The participating contractors indicated that the direct costs who receive advance payments reported that the average
comprise 88% of the total project cost, whereas the indirect amount of the advance payments they receive is between 5%
costs account for 12% of the total project cost. Table 5 presents and 15% of the contract price. Almost all of the remaining
the approximate contribution of cost items and the major participating contractors who receive advance payments
source of financing as reported by contractors in Saudi Arabia. (46%) reported that the amount of advance payments is
The approximate contribution is calculated as the sum of the between 15% and 25% of the contract price. When asked if
product of the respondents’ ratio and the midpoint of the per- they were content with the amount of advance payment
centage range. received, about 64% of the participating contractors reported
The survey shows that contractors do not rely on banks to that they find the amount of the advance payments insufficient
finance projects. It seems that contractors invest accumulated for them to fulfill their financial requirements at the beginning
profit and cash obtained from other businesses, such as trades, of the project. Contractors regularly utilize advance payments
to finance their project operations. Contractors may believe to pay for their mobilization costs and pay their own advance
that self-financing contributes dearly to their companies’ payments to subcontractors and/or suppliers engaged in a par-
competitiveness by offering cash at lower interest rates than ticular project.
bank rates and, at the same time, they are rewarded directly in The majority (64%) of the contractors stated that owners
their investments. redeem the advance payment by deducting an agreed-upon per-
centage from progress payments. About 32% of the participating
contractors reported that they repay the advance payment by
Cash Inflow Description and Sources
deducting an agreed-upon fixed amount from progress payments.
In construction, partial payments are made to a contractor at
different stages as the work progresses, instead of making
one full payment upon completion. It is common for an
Progress Payments
owner to measure and value the work at designated time The majority (76%) of the participating contractors reported
intervals, mostly monthly, and pay the contractor accord- that they are paid progress payments every month of the project
ingly. At the completion of the project, a final payment is duration. In comparison, about 16% of the participating con-
made covering the value of the last completed work and any tractors stated that they are paid progress payments at set mile-
retentions. In certain contracts, a contractor receives an stones, such as completion of specific work, as designated in
advance payment from the owner at the beginning of the the contract. The remaining 8% of the participating contractors
project. The advance payment, progress payments, and final showed that the owners pay them progress payments at desig-
payment are the main sources of cash inflow. The main cash nated time milestones of the project. These findings signifi-
flow concern of a contractor is to minimize outsourced cantly match the reported studies in the literature. Respecting
financial aids as much as possible, regardless of the cost the agreed-upon conditions in the contract between the con-
of the project. tractor and the owner, a contractor bills the owner for the work
Owner payments take different forms as the work progresses done in the previously agreed-upon period, typically one
and adapt to the different stages of a project. Figure 5 shows month. Subsequently, the owner reviews the invoiced work and
these payments and their occurrences during a hypothetical pays the invoice, once it is certified.
project’s life cycle. The participating contractors described This method of paying construction expenses impacts the
owners’ payment structures and processing methods. way the contractor pays suppliers, subcontractors, and labor. In
Shash and Qarra 57

120%

100%
Percentage of Contract Price

80%

60%

40%

20%

0%

-20%

-40%
Project Project Project Project Project Project
Start Progress Progress Progress Progress Completion

Advance Payment Progress Payment


Retention Advance Payment Deductions

Figure 5. Owners’ payments’ locations and values over a hypothetical project duration.

60%
Progress Payments Delay
Percentage of Respondents

50% 53%

40%

30%

26.70%
20%

10% 13.30%
6.7%
0%
Less than 30 days 30 to less than 60 days 60 to less than 90 days 90 to less than 120 days
beyond their due date beyond their due date beyond their due date beyond their due date

Figure 6. Progress payments delay distribution.

general, the idea behind this credit system is to establish a progress payment delay has major effects on contractors and
system that enables the owner to pay the project expenses in owners. The delay disturbs a contractor’s financial cash flow
a way that supports the contractor effectively while concur- and subjects the contractor to unnecessary stress from credi-
rently securing the owner. tors. The delay may increase the cost of the project through
The participating contractors reported that they are some- additional charged interests on the amount of delayed prog-
what satisfied with the timing of owners’ progress payments. ress payment.
Almost 52% stated that they receive payments on time, The participating contractors indicated that owners delay
whereas the other 48% showed that owners delay payments payments for several reasons. The majority (65%) of the con-
beyond their due dates. Figure 6 presents the delay distribution tractors stated that the approval process for invoiced work in an
in owners’ progress payments as reported by the contractors owner organization is a significant factor in delaying payments.
who receive payments beyond their scheduled times. In fact, It seems that invoices pass through many offices for approval.
58 Project Management Journal 49(5)

Table 6. Reasons for Owners’ Payment Delays and suppliers. This strategy is very harmful to the business of a
contractor. Labor productivity and reputation may suffer dearly
Reasons Number of Responses Percentage
from the application of such a policy. Few contractors (about
Disputes 1 5 7%) of the participants continuously and fiercely follow-up on
Not enough budget 1 5 payment requests with owners and possibly slow down work.
Bureaucracy 6 25 About 27% of the contractors, after exhausting the above
Corruption 0 0 actions, say that they stop work until payments are made. It
Approval process 17 65
is apparent that the contractors incorporate these delayed pay-
ments into their financial model.
Table 7. Actions Toward Owners’ Payment Delays

Percentages of Retention and Final Payment


S/N Action Respondents The results pointed out that 84% of the participating contrac-
1 Continue work and delay payments to labor, 13.3% tors stated that the retention provision is applied in their con-
management, and suppliers. tracts. The majority (68%) of those contractors reported that the
2 Continue work by borrowing money from a 20% applied retention typically ranges between 5% and 10% of the
bank with intention to claim the interest from contract price, whereas about 23% reported that it ranges
the owner. between 10% and 15% of the contract price. These results
3 Continue work by borrowing money from 40%
match closely what other researchers have discussed and
another ongoing project account.
4 Continue work by borrowing money from 33.3% reported in the literature.
the organization’s available cash with the The participating contractors stated that owners usually pay
intention of claiming an interest from the retained amount at the completion of projects. However, own-
the owner. ers request contractors to submit several documents, as presented
5 Stop work until payments are made. 26.7% in Table 8, before they will release the retained amount.
6 Lower the rate of work and strongly follow up 6.7% The majority (about 73%) of the participating contractors
on the payment.
reported that owners demand a hand-over report (certificate of
completion) and guarantee letters of a facility’s machines and
equipment. About 50% of the participating contractors identi-
Al-Dulaijan (1987) reported that the number of approvals fied the Zakat certificate—a governmental document certifying
needed for a contractor’s invoice might reach 15 in some proj- that the contractor paid the Zakat—and the retention invoice as
ects. He indicated that these approvals might take more than documents demanded by owners before the release of retained
100 days in some projects. Bureaucracy is a major factor caus- amounts. It is interesting that some owners request contractors
ing delays of progress payments, according to 25% of the to show certificates that the salaries of the contractors’ staff and
respondents. The results also indicate that about 5% of the laborers are paid. It seems that those owners want, for huma-
participating contractors find disputes and budget shortages nitarian reasons, to make sure their contractors pay salaries to
as major reasons for delay in owners’ payments. Some contrac- laborers regularly. Some contractors in Saudi Arabia are known
tors mentioned the possibility of corruption inside owners’ to delay the salaries of their staff for several months.
organizations verbally rather than in writing because of the The majority (59%) of the participating contractors stated
sensitivity of this issue. Those contractors declared that corrup- that owners usually release the retained money within 30 days
tion inside some organizations is one significant reason for after the submittal of a retention request. Unfortunately, about
owners’ payments delay. Table 6 presents the reasons for own- 14% and 18% of the participating contractors reported that
ers’ progress payments delay. some owners delay the retention money for more than 60 and
Contractors demonstrated several reactions, as presented in 90 days, respectively.
Table 7, to progress payment delay. Interestingly, the majority The majority (75%) and about 20% of the participating
of the contractors stated that they continue to work during contractors indicated that they usually receive final payments
payment delays and exercise different strategies to compensate within 30 days and 60 days beyond receiving a certificate of
for the delayed payments. About 40% of the contractors borrow completion, respectively.
money from the accounts of other ongoing projects. Under this The results also indicate that owners vary in delaying the
strategy, the contractors expose all of their projects to the risk final payment invoice. About 32% and 34% of the participating
of failure because cash shortages will affect the quality of all contractors reported that owners pay final payment invoices 10
projects. A much more efficient group of contractors, repre- to 30 days and 30 days to 60 days after invoicing, respectively.
senting about 33% of the participants, implement a better strat- Another 24% of the participants indicated that some owners
egy of borrowing money from a bank with the intention to pay final payments in 60 to 90 days.
claim the charged interest from owners. About 13% of the The contractors reported that owners ask them to submit
contractors delay their own payments to labor, management, supporting documents with their requests for final payments.
Shash and Qarra 59

Table 8. Requirements for Releasing Retention and Final Payments

Retention Final Payments

Requirements Respondents Percentage Respondents Percentage

Certificate of payments to firm’s employees 3 13.6 5 24


Zakat/income tax certificate 11 50 10 44
Guarantee letters 16 72.7 16 72.0
Retention/final payment invoice 10 46 11 48
Project hand-over 16 72.7 19 84.0

These requested supporting documents, as presented in Table 9. Deficit Financing


Table 8, are similar to those of the retention requests.
Financing Techniques

Respondents Self-Financing (%) Banking Facilities (%)


Project Deficit Funding
1 20 80
Contractors mainly have two options to generate cash to loosen 2 40 60
the capital lookup (the amount of work done by the contractor 3 50 50
and not yet paid by the owner). Contractors pay either from 4 70 30
their own cash (self-financing) and/or obtain a loan in the form 5 15 85
6 20 80
of cash from a lending organization such as a bank (debt- 7 20 80
financing). The participants were asked to indicate which tech- 8 60 40
niques their organizations apply to finance their projects. 9 25 75
Twenty-two contractors responded to this request. One respon- 10 60 40
dent (about 4.5% of the total respondents) reported that his 11 60 40
company depends fully on banks to finance cash flow deficits. 12 70 30
Six respondents (about 27%) indicated that they do not obtain 13 30 70
14 80 20
loans from banks but rather secure all needed cash for projects 15 70 30
from their companies’ own accounts. The remaining 15 respon-
dents (about 68%) indicated that they depend on self-financing
and bank loans to finance cash flow deficits. The self-financing reasonable/very low risk and 5 represents not suitable/very
ranges from 15% to 80%, with an average of 46%. On the other expensive/very high risk.
hand, the bank loans range from 20% to 85%, with an average The results showed that the participants secure 38%, 35%,
54%. It is believed that the self-financing technique is popular and 27% of the required cash from retained profit, equity, and
among contractors who have trading business and/or real estate trade credit, respectively. The participants rated retained profit
investments in addition to construction contracting. Table 9 and trade credit techniques very much suitable, very much
presents the reported amount of cash, in percentage of deficit, effective, of reasonable cost, and with acceptable risks. On the
which those contractors secure from self-financing and banks. other hand, they rated the equity technique very much suitable,
effective, high in finance rate, and moderate risk. It seems that
all self-financing techniques are equally popular among con-
Self-Financing Techniques tractors in Saudi Arabia because the respondents classified
The results indicate that the contractors who depend on self- their risks as moderate. The participating contractors tend to
financing use three techniques—namely, equity, shareholder utilize the amount of cash that remains after paying the taxes,
investment, and trade credits. Table 10 presents these tech- servicing interest, and shareholder dividends to finance cash
niques with qualification parameters. The table consists of six flow deficits. Ross and Williams (2013) reported that when this
blocks. The first block presents the different self-financing profit is considered relatively large, a contractor could utilize it
techniques and the second block presents the percentage of as working capital to fund the company’s ongoing projects. It
implementation. The third to sixth blocks present the respon- seems that numerous contractors in Saudi Arabia invest part of
dents’ evaluations of these techniques in terms of their suit- their realized profit in financing their projects, and sharehold-
ability, finance effectiveness, cost, and involved risk. The ers enjoy the investment returns. A trade credit technique,
respondents were asked to measure the performance of the where suppliers allow contractors to buy materials and equip-
applied financial techniques in terms of their suitability, ment now and pay later, is also used. Trade credit transaction,
finance effectiveness, cost, and involved risk using a scale 1 as reported in the literature, is commonly used in the construc-
to 5, where 1 represents very much suitable/very effective/very tion industry. Although the trade credit technique is external, it
60 Project Management Journal 49(5)

Table 10. Analysis of Self-Financing Techniques

Suitability Finance Risk


Self-Financing Percentage of Standard Scale Standard Effectiveness Standard Finance Cost Standard Involvement Standard
Techniques Implementation Deviation (1 to 5) Deviation Scale (1 to 5) Deviation Scale (1 to 5) Deviation Scale (1 to 5) Deviation

Retained profit 38% 29.5 High 1.2 High 1.4 High 1.3 Medium 1.6
Equity 35% 30.5 High 1.1 Medium 1.2 Medium 1.1 Medium 1.5
Trade credit 27% 23.3 High 1 High 1.4 High 1.4 Medium 1.4
Total/average 100% - High High High Medium

is considered a self-financing technique because banks are not contractors more than one year to construct, long- and mid-
part of the financing; this occurs between contractors and their term loans satisfy the financial requirements. The participat-
creditors, such as material suppliers. ing contractors believe that loan facilities are very suitable,
The participating contractors appreciated the self- effective, reasonable in finance charges, and moderate in the
financing techniques and stated that they are highly suitable risk involved.
for their businesses, highly effective in financing, and
involved average risk.
Overdraft Accounts
An overdraft allows contractors to borrow money through their
Debt-Financing Techniques bank accounts based on a loan arrangement under which the
Banks furnish various types of facility services to contractors. bank extends credit up to a maximum amount (called the over-
Commonly, once a bank committee approves a contractor’s draft limit) against a current (checking) account through which
request for a banking facility, the contractor has access to cash the contractor can write checks or make withdrawals. It is
in accordance with a loan agreement between the contractor simply an extension of credit from a lending institution when
and the financial institution (bank). This agreement states that an account reaches zero. It is, however, a demand loan; the
the bank finances the contractor with a specific amount of facility can be canceled and the entire outstanding amount may
capital and the contractor, in turn, provides guarantees to repay be called at any time by the lender at its discretion, without any
the lent money with an interest charge. warning or explanation. This type of banking facility is used
Generally, the types of banking facilities can range from only for emergencies or short-term borrowing, and contractors
short- to long-term financing. Short-term financing is usually diligently schedule overdraft payments within a short period.
used to fund changes in a predicted amount of a working capital The participating contractors showed that they understand the
of a project, while long-term financing is applied to fund the risk associated with this type of financing and, hence, only
general operations of the company (Ross & Williams, 2013). utilize it, on the average, at a rate of 4.5% of the different
The first column in Table 11 presents the various banking banking facilities. They believe that overdraft facility is appro-
facilities that banks commonly supply to contractors. Table priate because of its effectiveness, low interest charges, and
11 is similar to Table 10, but shows debt-financing rather than low risk. It seems that when contractors decide to use this type
self-financing techniques. The respondents were also asked to of facility, they use extra caution not to exceed the credit limit
measure the performance of debt-financing techniques in terms and pay the overdraft back on time.
of their suitability, finance effectiveness, cost, and involved
risk using similar measurements as those shown in Table 10.
Invoice Financing
Invoice financing is a form of short-term borrowing often used
Bank Loans to improve a company’s working capital and cash flow posi-
The results indicate that the contractors use all available bank- tion. Invoice financing allows a contractor to draw money
ing facilities to fund their construction operations. The largest against its invoices of progress payments before the owner has
amounts of funds that contractors secure from banks are the actually paid. In order to do this, the contractor borrows a
loan facilities. Loans are typical forms of banking facilities percentage of the value of its invoice from a bank, effectively
and consist of short-term, mid-term, and long-term loans. The using the unpaid sales invoices as collateral for borrowing. The
participating contractors reported that bank loans made up participating contractors indicated that invoice financing com-
44.2% of their banking facilities, with long- and medium- prises about 18% of the amount of cash they borrow to fund
term loans being the most popular, accounting for about their operations. It appears that contractors use invoice financ-
73% of the loans. Short-term loans make up only about 27% ing when owners delay progress payments, which is common.
of the loans used by contractors. The participating contractors believe that invoice financing is a
The nature of construction projects dictates the selection of highly effective and highly suitable technique, despite its high
the loan type. It seems that for projects that take participating risk and high interest charges.
Shash and Qarra 61

Table 11. Analysis of Banking Facilities

Finance Finance Risk


Suitability Effectiveness Cost Involvement
Percentage of Standard Scale Standard Scale Standard Scale Standard Scale Standard
Banking Facilities Implementation Deviation (1 to 5) Deviation (1 to 5) Deviation (1 to 5) Deviation (1 to 5) Deviation

Loans Long term 11.80 18.8 Medium 1.5 Medium 1.5 Medium 1.3 Medium 1.1
Short term 26.20 34.5 Medium 1.4 Medium 1.2 Medium 1.0 Medium 1.0
Term 6.20 14.2 Medium 1.7 Medium 1.5 Medium 1.6 Medium 1.4
Overdraft accounts 4.60 6.0 Medium 1.2 Medium 1.3 Low 1.4 Low 1.2
Invoice financing 18.20 20.4 High 1.0 High 1.3 High 0.9 High 1.6
Bonds Bid 4.70 6.3 Medium 1.2 Medium 1.5 Medium 1.5 Medium 1.5
Advance 6.10 6.6 High 1.2 High 1.0 High 1.0 Medium 1.5
payment
Performance 4.80 5.4 Medium 1.5 Medium 1.2 Medium 1.4 Low 1.4
Retention 3.90 5.2 Medium 1.4 Medium 1.3 Medium 1.2 Medium 1.3
Letters of credit 11.40 13.2 High 0.9 High 0.9 High 0.8 Medium 1.3
Hire purchase/ 2.10 4.3 Medium 1.2 Medium 1.1 Medium 1.0 Medium 1.1
leasing
Total/average 100% – Medium Medium Medium High

Bonds Summary and Conclusion


An owner dictates that contractors furnish several types of This study, to the best knowledge of the authors, is the first to
bonds to protect the owner, mainly from contractor failure. The discuss cash flow management issues in Saudi Arabia.
contractors in this study indicated that bonds constitute about Although contractors in Saudi Arabia are fully aware of cash
20% of their banking facilities. This is not a surprising amount flow into and out of their projects, only 76% of them analyze
of banking finance because of owners’ requirements. Contrac- their cash flows for better financial management. Even those
tors have no option but to apply to a bank for bid bond, advance contractors who analyze cash flow, focus mainly on how to
payment bond, performance bond, and/or a retention bond. temporarily survive rather than have a well-forecasted financial
view. They restrict cash flow analysis for control purposes and
for determining the most suitable financing techniques for the
Letters of Credit prospective project. The majority of contractors in Saudi Ara-
A letter of credit is a document issued by a bank to guarantee bia conduct cash flow forecasting prior to bidding for a project
that a seller will receive payment in full as long as certain aiming mostly to set a cash flow baseline (for control purposes)
delivery conditions are met. In the event that the contractor is and to determine the proper financing method. Unfortunately,
unable to make payment on the purchase, the bank will cover more than half of the contractors surveyed do not benefit from
the outstanding amount. The participating contractors indicated cash flow analysis in determining the amount of deficit and,
that this type of banking facility represents 11.4% of the consequently, deciding on suitable financial techniques and
obtained facilities. The contractors may use letters of credit estimating the cost of deficit financing. The contractors who
to purchase materials and/or equipment for a project. The con- perform no cash flow analysis, and very few of the contractors
tractors find this banking facility highly effective and highly who do so, encounter project failures in their annually signed
suitable despite the medium amount of involved risk and high contract periods because of poor cash flow management and
interest charges. forecasting.
The majority of contractors in Saudi Arabia receive
advance payments in some or all of their undertaken projects,
Hire Purchase Facility with an average value of 15% of the contract price. Owners
Hire purchase is a contract that a purchaser agrees to pay for redeem the advance payment by deducting an agreed-upon
goods in part or a percentage over a number of months. It is percentage from progress payments. Retention is applied in
interesting to notice that some contractors in Saudi Arabia use the majority of construction contracts in Saudi Arabia, with an
this facility to buy goods through making installment payments average of 10% of the contract price. Contractors usually
over time. Under a hire purchase contract, the buyer leases receive retentions and final payments within 30 days after the
goods and does not obtain ownership of them until the full submittal of a retention request accompanied by supporting
amount of the contract has been paid. It seems that contractors documents, including a completion certificate, Zakat certifi-
in Saudi Arabia use the hire purchase facility mostly to buy cate, and certificates showing that the salaries of the contrac-
vehicles. tors’ staff and laborers have been paid. The majority of the
62 Project Management Journal 49(5)

contractors receive monthly progress payments, with delays  Monitor and control subcontracts and ensure on-time
attributed to owners’ approval processes for invoiced work progress payments.
and bureaucracy.  Restrict the available cash in a project account to its
The contractors depend on self-financing techniques, construction activities only and refrain from moving
including retained profit, equity, and trade credit, rather than cash from one project to another.
bank loans to finance construction projects. The contractors
also use all kinds of banking services, especially those required Owners are advised to be prompt in paying contractors’ prog-
by contracts, in running their businesses. These self-financing ress payments and to reconsider the implementation of reten-
and banking services are used to pay for material costs and tions in projects, especially in projects where performance and
labor salaries, equipment, subcontractors, overhead, and mobi- payments bonds are applied.
lization costs. Materials, subcontractors, and labor costs com-
prise the highest portion of a project’s total cost. A significant Declaration of Conflicting Interests
percentage of contractors in Saudi Arabia (40%) undergo a The author(s) declared no potential conflicts of interest with respect to
financial failure as a result of poor cash flow management in the research, authorship, and/or publication of this article.
at least one of their annual contracts. Delays in advance payment
and/or progress payments and project delays have very severe Funding
effects on cash flow over the duration of a project. The author(s) received no financial support for the research, author-
In conclusion, projects in Saudi Arabia are executed ship, and/or publication of this article.
according to the well-established cash flow baseline forecast
of cash inflow and outflow, used for control purposes. Some References
owners make advance payments to help contractors start proj- Akintoye, A., & Fitzgerald, E. (2000). A survey of current cost esti-
ects, pay progress payments to contractors on time, and pay mating practices in the UK. Construction Management and Eco-
final payments, including retentions, on time. Contractors nomics, 18(2), 161–172.
apply certain practices to manage their cash outflows and Al-Barrak, A. (1993). Causes of contractors’ failures in Saudi Arabia,
deficits. They tie their payments to suppliers and subcontrac- Arabia (M.Sc. thesis). King Fahd University of Petroleum and
tors to owners’ progress payments and make use of deficits Minerals, Dhahran.
from either their own accounts and/or from banks. Unfortu- Al-Dulaijan, S. U. (1987). Construction financing in Saudi Arabia
nately, some contractors, apply poor practices that subject (M.Sc. thesis). King Fahd University of Petroleum and Minerals,
their companies to bankruptcy situations. Some contractors Dhahran.
use cash from other ongoing projects to finance the activities Boussabaine, A. H., & Elhag, T. (1999). Applying fuzzy techniques to
of a project with a deficit. cash flow analysis. Construction Management and Economics,
The contractors are advised to improve current cash flow 17(7), 745–755.
management practices by implementing detailed forecasting Boussabaine, A. H., & Kaka, A. P. (1998). A neural networks
prior to the bidding stage, and monitoring and updating the approach for cost-flow forecasting. Construction Management and
forecasted model continuously over the stages of the project’s Economics, 16(4), 471–479.
execution. Following are suggestions that may improve the Bromilow, F. J. (1978, March). Multi-project planning and control in
cash flow process for contractors: construction authorities. Building Economist, 208–213.
Crundwell, F. (2008). Finance for engineers: Evaluation and funding
 Study the characteristics of projects under bid and of capital projects. London, England: Springer-Verlag.
the contract conditions very thoroughly and ensure Cui, Q., Hastak, M., & Halpin, D. (2010, April). System analysis of
that they are adequate for the contractor’s financial project cash flow management strategies. Construction Manage-
status. ment and Economics, 28, 361–376.
 Benefit from cash flow analysis in determining the Gatti, S. (2008). Project finance in theory and practice. San Diego,
amount of deficit to decide on the proper financing tech- CA: Academic Press.
nique and, thus, estimate the cost of financing. Halpin, D. W., & Senior, B. (2009). Financial management and
 Consider contingency factors while preparing a cash accounting fundamentals for construction. Hoboken, NJ: John
flow forecasting model. An owner’s payment delay, Wiley & Sons.
project delay, and absences of certain financing sources Hendrickson, C. (1998). Project management for construction. Pitts-
should all be accounted for in the forecasting process. In burgh, PA: Prentice-Hall.
other words, more “what if” models should be applied Isidore, L. J., & Back, W. E. (2002). Multiple simulation analysis
prior to considering the final shape of the cash flow for probabilistic cost and schedule integration. ASCE Journal of
forecast. Construction Engineering and Management, 128(3), 211–219.
 Control project materials cost, ensure a good relation- Kaka, A., & Price, A. D. (1991). Net cash flow models: Are they
ship with project suppliers, and effectively utilize con- reliable? Construction Management and Economics, 9(3),
tractor credit with them. 291–308.
Shash and Qarra 63

Kaka, A., & Price, A. D. (1993). Modeling standard cost commitment Ross, A., & Williams, P. (2013). Financial management in construc-
curves for contractors. Construction Management and Economics, tion contracting. Oxford, England: John Wiley & Sons.
11(4), 271–283. Steffan, B. B. (2008). Essential management accounting: How
Kenley, R. (2003). Financing construction. London, England: Spon to maximise profit and boost financial performance. London,
Press. England & Philadelphia, PA: Kogan Page.
Kenley, R., & Wilson, O. D. (1986). A construction project cash flow Tarek, Z., & Yaqiong, L. (2014). Cash flow modeling for construction
model—An idiographic approach. Construction Management and projects. Engineering, Construction and Architectural Manage-
Economics, 4(3), 213–232. ment, 21(2), 170–189.
Likert, R. (1932). A technique for the measurement of attitudes. Tucker, S. N. (1986). Formulating construction cash flow curves using
Archives of Psychology, 140, 1–55. a reliability theory analogy. Construction Management and Eco-
Lipsey, M. (1990). Design sensitivity: Statistical power for experi- nomics, 4(3), 179–188.
mental research. Thousand Oaks, CA: Sage Publications. Watson, T., & Noble, P. (2007). Evaluating public relations: A best
Miskawi, A. (1989). An S-curve equation for project control. Con- practice guide to public relations planning, research and evalua-
struction Management and Economics, 7(2), 115–124. tion (2nd ed.). London, England & Philadelphia, PA: Kogan Page.
Mutti, C. D. N., & Hughes, W. (2002, September 2–4). Cash flow Yescombe, E. R. (2014). Principles of project finance (2nd ed.).
management in construction firms. In D. J. Greenwood (Ed.), 18th Kidlington, England: Elsevier Science.
annual ARCOM conference: Association of Research in Construc-
tion Management (Vol. 1, pp. 23–32). Northumbria, UK: Univer-
sity of Northumbria. Author Biographies
Navon, R. (1996). Company level cash-flow management. Journal of
Dr. Ali A. Shash is a Professor in the Construction Engineering
Construction Engineering and Management, 122(1), 22–29.
and Management Department of the College of Environmental
Odeyinka, H. A., Kaka, A., & Morledge, R. (2003, September 3–5). An
Design at King Fahd University of Petroleum and Minerals
evaluation of construction cash flow management approaches in
(KFUPM), Dhahran, Saudi Arabia. He is also the director of
contracting organizations. In D. J. Greenwood (Ed.), 19th annual
the Construction Industry Institute at KFUPM. He can be con-
ARCOM conference: Association of Researchers in Construction
tacted at aashash@kfupm.edu.sa or aashash854@gmail.com
Management (Vol. 1, pp. 33–41). Brighton, England: University of
Brighton. Abdulaziz Al Qarra is a graduate student at the Construction
Peer, S. (1982). Application of cost flow forecasting models. Journal Engineering and Management Program, King Fahd University
of Construction Division, AACE, 108(2), 226–232. of Petroleum and Minerals (KFUPM), Dhahran, Saudi Arabia.
Purnuş, A., & Bodea, C. (2015). Financial management of the con- He is also a Project Manager in the Project and Development
struction projects: A proposed cash flow analysis model at project Services Department, JLL (Jones Lang LaSalle)—MENA,
portfolio level. Organization, Technology and Management in Saudi Arabia. He can be contacted at asqarra@gmail.com or
Construction International Journal, 7(1) 1217–1227. Abdulaziz.AlQarra@eu.jll.com

You might also like