Professional Documents
Culture Documents
shash-qarra-2018-cash-flow-management-of-construction-projects-in-saudi-arabia
shash-qarra-2018-cash-flow-management-of-construction-projects-in-saudi-arabia
shash-qarra-2018-cash-flow-management-of-construction-projects-in-saudi-arabia
Abstract
Cash flow management entails forecasting, monitoring, and controlling practices of the cash inflow and outflow and arrangement
of deficits over a project’s duration. This article reveals, through a questionnaire survey, the techniques and practices that
construction companies in the Eastern Province of Saudi Arabia follow to forecast and manage cash flow at the project level. The
majority of the contractors perform cash flow forecasting for setting a cash flow baseline and determining the proper financing
method. They use credit financing for materials, subcontract a good portion of projects, and use company assets and credit
financing to pay for equipment and labor.
Keywords
cash flow, Saudi Arabia, management, practices, construction, deficit
1 2
Equity Cash Flow Out
Cash Cash
Advanced Payment
Flow Flow Purchase Fixed Asset
Debt In Out Purchase Raw Materials
Cash for Labor Salaries
3
a Project Subcontractors’ Payments
Progress Payments Suppliers’ Payments
Direct Overhead
Compensation
Finished Transformation
Processes Project Processes
the contractor’s expended amount for a completed or partially offered techniques to manage cash flow properly. Unfortu-
completed construction work is a function of the contractor’s nately, the offered techniques concentrated on the development
efficiency and the agreed-upon percentage of retention. of models for forecasting cash flow over the duration of a
The payment amount is reduced by a retainage, a certain construction project, and very little work has been reported
percentage of the payment that has the effect of keeping a on the practices that contractors follow to manage cash flow.
contractor in negative cash flow for a long duration and, in Although the literature is rich in cash flow and cash flow tech-
many cases, for the total duration of the project. High ratio nique studies, the Saudi construction industry’s usage of these
of payment to expenses means excellent recovery of expen- studies and practices in managing cash flow has yet to be
ditures. As a matter of fact, recovering good amounts of investigated. This study is an attempt to reveal the practices
expenditures in terms of cash from progress payments leads that are followed by construction companies in the Eastern
contractors to borrow minimum amounts of money that are Province of Saudi Arabia to forecast and manage cash over the
close to the amount of the retained money and allows them duration of projects. It is hoped that such a study will lead to
to finance ongoing construction operations properly. A con- more advanced treatments of contractors’ cash flow manage-
tractor funds construction costs for a period that may ment and, hence, prevent contractors in Saudi Arabia in
extend to 60 days before recovering such expenditure in particular, and in other countries in general, from facing cash
the form of progress payments from the owner. Contractors flow-related failure.
commonly find themselves in a position where they have to
pay for labor, materials, and suppliers for longer periods
than the scheduled payments dates if there are delays in
Research Objective
receiving the progress payments. The main objective of this study is to reveal and describe the
Contractors follow certain procedures to manage income techniques and practices that construction companies in the
(inflows), expenditures (outflows), and deficits in their proj- Eastern Province of Saudi Arabia employ to forecast and man-
ects. Proper management of these components is essential to age project cash flow.
the survival of construction companies. For years, the unavail-
ability of cash as a result of cash flow problems has been a
major cause of insolvency for many contractors. This was iden- Literature Review
tified in the 1970s and, since then, many researchers have Cash flow is the difference between cash spent and cash
emphasized the importance of cash flow management to the received by a firm during a specific period of time (Tarek &
survival of construction companies, because cash is a crucial Yaqiong, 2014). Cash flow management mandates the applica-
resource to the contractor’s day-to-day activities and a means tion of practices in managing project cash flow against a set
to obtain loans from banks (Odeyinka, Kaka, & Morledge, baseline. Actually, the accurate estimation of cash flow in the
2003). Tarek and Yaqiong (2014) reported that inadequate early stages of a project is considered a vital factor that pro-
control of cash flow caused many construction companies to vides an indication of the project’s financial significance.
leave the industry. Al-Barrak (1993) found that cash flow man- Cash flow planning is the charting of cash movement into
agement is one of the major financial issues that cause contrac- the production process, then into accounts receivable, and back
tors to go bankrupt in Saudi Arabia. Hence, researchers have into cash. Cash flow planning is a crucial step in making
50 Project Management Journal 49(5)
significant decisions concerning how to liquidate a project with and corresponding level of risk that may emerge from the use
the cash. Cash flow forecasting guides the contractor to the of the financing technique (Crundwell, 2008). When it comes
amount of cash needed for the project and to how to return this to financing a construction project, the contractor’s goal will be
amount to the account from which it was borrowed (Ross & to finance the negative gap between project expenses and proj-
Williams, 2013). Halpin and Senior (2009) indicated that fore- ect revenues with the aim of achieving the optimum possible
casting cash behavior over a project’s duration is a crucial key amount to finance; thus, the contractor’s loans cost will be the
for controlling project cash effectively. In addition, performing least (Halpin & Senior, 2009). Although the project’s financial
a thorough cash flow analysis for a project is necessary to nature is that an owner pays a contractor periodic (progress)
eliminate or to minimize the possibility of financial failure payments, the contractor may face various financial problems
(Kenley, 2003). along the project’s progress. The owner’s progress payments
Many researchers have developed probabilistic and mostly may be delayed, which will affect the progress of the project,
deterministic models for cash flow forecasting, with some var- unless the contractor has the financial ability to temporarily
iations in their accuracy and detail, the degree of automation in cover this negative cash value. Project expenses that exceed
compiling them, time and money integration methods, and so the cumulative progress payments paid by the owner to the
forth (Mutti & Hughes, 2002). Bromilow (1978), Peer (1982), contractor cause this situation (Hendrickson, 1998). This gap
Isidore and Back (2002), Boussabaine and Elhag (1999), between revenues and expenses is referred to as working cap-
Tucker (1986), Kenley and Wilson (1986), Kaka and Price ital, which is a source of power for a contractor in commencing
(1993), Miskawi (1989), and Boussabaine and Kaka (1998) a project. The term defines the remaining amount of available
developed deterministic models for forecasting and managing cash that the contractor has after deducting the amount of
cash flow at the project level. In contrast, Purnuş and Bodea current liabilities (Steffan, 2008). This working capital is the
(2015) argued that projects are highly dynamic, and a determi- figure that will guide the contractor in the decision to use
nistic analysis does not provide a realistic view of the financial available credit lines or look for new sources of capital by using
efforts that a contractor has to make. They also discussed the corporate finance (Yescombe, 2014).
fact that focusing on the individual project level does not Unfortunately, most of the previous research has suggested
reflect the overall risks at the corporate level, and that the techniques for setting baselines for cash flow, but very few
simple sum of an individual project’s risks can be significantly researchers have addressed the practices that contractors follow
different from the total corporate risks. Some researchers have to manage these cash flows. Odeyinka et al. (2003) surveyed
developed models for forecasting and managing cash flow at United Kingdom contractors on the approaches they use to
the organizational level. Navon (1996) developed a cash flow resolve deficit cash flow, their cash flow monitoring methods,
management system to forecast cash flow at the company level. the frequency of cash flow updating, and the methods they used
Cui, Hastak, and Halpin (2010) developed a system dynamics for forecasting cash flow. They found that contractors resolve
model for project cash flow management. They used a ware- deficit cash flow through different means including, in order of
house project to demonstrate the flexibility of the model in priority, the company’s cash reserves, tender balancing,
incorporating cash flow management strategies and predicting delayed payment to subcontractors, delayed payment to sup-
project cash flows. Purnuş and Bodea (2015) presented a prob- pliers, use of company assets, and borrowed funds. On the other
abilistic cash flow analysis model, which allows integration of hand, many researchers have addressed and reported on cost
risk events and uncertainties such that the model becomes a control against set budgets. Readers interested in cost control
true decision tool that can be applied at the project’s portfolio practices are referred to published work on this subject.
level. They claim that when contractors apply the proposed
model, they avoid high financial exposures and losses. Further-
more, the modeling of the cumulative behavior of all projects Research Methodology
allows contractors to predict not only when but mostly what This section presents the steps that were followed to achieve
amount of money should be borrowed or obtained from internal the objective of the study, which is to identify and describe the
or external sources and when and what amount of money practices that construction companies in the Eastern Province
should be returned. Ross and Williams (2013) claim, however, of Saudi Arabia follow to manage project cash flow. This study
that many simple cash flow models, other than that presented employed a postal survey, the most popular method used by
above, may not take into account uncertainties and the effects many researchers in descriptive studies (Watson & Noble,
of many factors on project cash flow. 2007), to collect the necessary data from construction contrac-
The internal earnings of a construction company and/or tors. As compared to face-to-face interviews and the Delphi
commercial banks’ financial facilities are two main sources method, the method used here is both cost and time effective.
contractors use to finance the operations of a construction proj- The first step involved reviewing published relevant literature.
ect (Halpin & Senior, 2009). Selecting the financing method The review of pertinent published literature helped us study
depends mainly on the degree of accuracy with which a con- various financial management systems. The literature review
tractor can estimate cash flow during the duration of the project also helped to develop the necessary tool—a structured ques-
(Hendrickson, 1998) and the type of project delivery system tionnaire—for collecting the needed data. The questionnaire
Shash and Qarra 51
consisted of five sections. The first section contained questions where 1 represents very much suitable/very effective/very rea-
related to the company, such as size, location, number of cur- sonable/very low risk and 5 represents not suitable/very expen-
rent projects, age, and so on. The second section contained sive/very high risk.
questions related to respondents’ (the information providers)
characteristics, such as educational background, experience,
position in the organization, and so forth. The third section Data Analysis and Results
contained questions related to financial transactions and cash
flow management. The fourth section consisted of questions on Because the population is small, a structured questionnaire was
current financing techniques. The last section provided space distributed in the last quarter of 2014 via email to the 86 con-
for the respondents to suggest new financial techniques. tractors. The contractors were asked to complete and return the
The second step was collecting the necessary data via the questionnaire to the researchers at their convenience but no more
structured questionnaire from the top management of grades 1, than three weeks later. The questionnaire was followed up with
2, and 3 contractors located in the Eastern Province of Saudi emails and telephone calls to remind and encourage financial
Arabia. The Classifying Directorate of the Ministry of Munici- managers to participate in the study. Twenty-five financial man-
palities and Rural Affair classifies contractors into different agers from different companies completed and returned the
specialties (building, industrial, highway, etc.) and into five questionnaires over 12 weeks. Improving the reliability of the
grades based on qualification criteria for bidding on govern- collected data mandated accepting only questionnaires that had
ment projects. Each graded contractor is given an upper limit at least 80% of their contents duly completed. All the returned
for the projects on which they may bid. Grades 2, 3, 4, and 5 questionnaires satisfied the above restriction and comprised the
building contractors, for example, have upper limits for proj- total number of participants. This means that 29% of the popu-
ects with values of 280, 70, 21, and 7 million Saudi riyal, lation participated in the study, which is considered a typical
respectively. Grade 1 contractors have no upper limit. Other norm of a 20% to 30% response rate in most postal question-
types of contractors are classified in a similar fashion with naires surveying the construction industry (Akintoye & Fitzger-
comparable or different upper limits. The directorate lists 86 ald, 2000). In addition, the 25 participants are greater than the
classified contractors in the Eastern Province. We used the calculated minimum sample size and, therefore, form a reliable,
following statistical formula to determine the minimum suit- acceptable, and representative sample.
able sample size to represent the population. This exercise
revealed a minimum of 20 contractors to comprise a represen- Characteristics of Participants
tative sample of the above population: This section presents the characteristics of the contractors and
pq personnel who completed the questionnaires. Tables 1 and 2
n0 ¼ 2
e summarize the characteristics of the participants and their
n0 employers, respectively.
n¼ n The results indicate that the majority of the participants are
1þ 0
N well educated with college degrees, with about (50%) holding
master’s or doctorate of philosophy degrees. The majority
In the equation, p ¼ 0.5, q ¼ (1-p) ¼ 0.5, e (desired level of
(about 63%) of the respondents’ educational degrees are in
precision) ¼ 10%, and N ¼ population (Lipsey, 1990).
financial management and the remainder are in engineering,
The third step was to analyze the collected data using simple
with extensive experience and training in financial manage-
statistical tools such as frequency, mean, and standard devia-
ment. The majority (54% of the participants) have more than
tion. Simple mathematical techniques, such as percentage and
10 years of experience in the construction industry, and about
average, were used in analyzing the data. However, in addition
54% of these participants have been with their current
to these techniques, importance and severity indices were cal-
employers for more than five years. The results indicate that
culated to reflect the relative severity of the relevant factors
almost one half of the respondents are from the contractors’
over the others. The indices were calculated as follows:
top management positions—that is, general manager, opera-
P5 tions manager, project manager, or director. On the other
1 ai xi
Importance Index ¼ hand, it was found that about one third of the respondents are
5S x i
managers and managers’ assistants in the finance departments
Where: of their organizations.
ai ¼ Constant expressing the weight given to i; xi ¼ variable The results indicate that the participants are employed in
expressing the frequency of the response for i ¼ 1, 2, 3, 4, 5 contracting organizations, which, in the majority of cases
(Likert, 1932). For measuring the level of effect of variables on (67%), have been in existence for more than 10 years. This,
a project financing, a scale of 1 to 5 was used, where 1 repre- of course, ensures that the respondents represent well-
sents a very severe effect and 5 represents no effect. For mea- established firms. The head offices of most of the organizations
suring the suitability, finance effectiveness, cost, and involved are located in the Eastern Province of Saudi Arabia and very
risk in various financing techniques, a scale of 1 to 5 was used, few are located in other cities, such as Riyadh and Jeddah.
52 Project Management Journal 49(5)
Characteristics Distribution
Characteristics Distribution
Organization age Less than 5 5 to less than 10 10 to less than 15 15 to less than 20 20 to less than 25
Equal to or
more than 25
20% 16% 16% 20% 8% 20%
Number of employees Less than 50 50 to less than 200 200 to less than 500 500 to less than 700 700 to less than Equal to or
1,000 more than 1,000
20% 20% 20% 4% 4% 32%
Average construction Less than 100 100 to less than 200 200 to less than 500 500 to less than 700 700 to less than Equal to or
contracts executed 1,000 more than 1,000
annually (million SR1) 25% 37.50% 4% 4% 12.50% 17%
Organization capital Less than 1 1 to less than 10 10 to less than 50 50 to less than 100 100 to less than Equal to or
(million SR) 500 more than 500
8% 46% 8% 8% 16.50% 13%
Organization location Dammam Khobar Jubail Dhahran Riyadh Jeddah
32% 28% 0 4% 32% 4%
Types of executed Building Industrial Infrastructure Special construction Utilities
projects 76% 44% 40% 36% 28%
1
Saudi riyal (US$1 equals 3.75 SR)
About 32% of these organizations employ more than 1,000 Cash Flow Management
staff members. The combined extensive experience, rich
Cash flow commences with securing cash to fund project oper-
knowledge in the Saudi construction industry, and the large
ations. Contractors must spend to purchase necessary materials
staff size give these participating contractors the capability to
and equipment, pay laborers and management, and to receive
build large projects (buildings, industrial, highway, utilities,
cash from the owner based on partially or completely finished
and infrastructure) and to generate large annual revenues. The
work. Cui et al. (2010) stated that contractors develop auto-
results indicate that the majority of the participating organiza- mated cash flows with the integrated cost-schedule method,
tions (37.5%) sign yearly contracts with an average amount which involves a detailed project schedule with full costing
between SR100 and SR200 million. The results also show that based on the bill of quantities. The following sections present
a significant portion of the participants (about 29%) signs con- the methods that construction contractors in Saudi Arabia
tracts with an average amount of more than SR700 million implement to forecast and manage their projects’ cash flow.
yearly. This combination of the different sizes of the projects
undertaken by the participating contractors is a good factor,
which improves the quality of the results, as it provides Cash Flow Analysis
research findings representing a wider view of the industry. Cash flow analysis is an important financial activity for a proj-
Collecting the necessary data from personnel of such caliber, ect and entails listing money flows into and out of a project.
with this level of experience in financial issues, lends confi- Cash flow analysis enables a contractor to project future flows
dence regarding the quality of the information, and, hence, the of cash to determine the necessary budget for a project. Cash
results and findings obtained. flow analysis is not concerned with the amount of the cash flow
Shash and Qarra 53
Number of 5%
Purpose Responses Percentage
5%
5%
Determine the liquidity of the company 1 4
Set cash flow baseline for control purposes 22 85
Determine the financing method 18 70
15%
Determine the amount of money cost to 15 60
include in the bid price
Determine the amount of overdraft 11 45 60%
10%
alone, but also the timing of these cash flows. Most cash flow in
the construction industry is analyzed with monthly time peri-
ods. Cash flow analysis projects the cash balance at the end of
each month.
The results of this study indicate that the majority (76%) of None
Less than 5%
the participating contractors perform cash flow analysis or 5% to less than 10%
forecasting prior to bidding for a project. It was expected that 10% to less than 15%
all contractors would indicate that they perform cash flow 15% to less than 25%
analysis but, surprisingly, 24% of the participating contractors
responded negatively and stated that they do not analyze cash
Figure 2. Percentages of contracts that fail annually because of poor
flow for their projects. It seems that those contractors may cash flow management.
refrain from performing cash flow analysis for reasons related
to time and budget limitations during the pre-bidding stages
This may indicate that some contractors in Saudi Arabia may
and possibly because of previous unsuccessful experience with
apply poor financial practices.
cash flow analysis.
The results indicate that 40% of the participating contractors
The participating contractors delineated several benefits
encounter financial failure in their annual signed contracts,
from performing cash flow analysis. Table 3 presents the pur-
most likely as a consequence of their poor implementation of
poses of conducting cash flow analysis or forecasting, as per-
cash flow analysis and projections. This failure, resulting from
ceived by contractors in Saudi Arabia. Setting a cash flow
poor cash flow management, ranges from less than 5% to more
baseline for control purposes was cited by 85% of the partici-
than 25% of the annual signed contracts. The failure distribu-
pating contractors as one of the benefits they gain from cash
tion is shown in Figure 2. It is alarming to find this large
flow analysis. It seems that contractors are successful in setting
number of contractors facing sizeable project failures in their
cash flow plans, which they monitor and control over the life of
annual contracts because of poor cash flow management. The
a project. Moreover, 70% of the participating contractors
results of the study indicate that the majority of the contractors
reported that they benefit from cash flow forecasting or anal-
who encounter failures in their annual project contracts, attri-
ysis in determining the proper financing method for projects.
butable to poor cash flow management and forecasting, are
Working capital is an important part of a cash flow analysis.
those contractors who do not perform cash flow analysis prior
Computing the amount of working capital gives a contractor a
to submitting bids for projects.
quick evaluation of the liquidity of the project over its con-
Cash flow, as defined previously, is the process in which
struction period. Accordingly, the contractor decides on the
cash inflow and cash outflow are monitored and controlled.
source(s) for funding the working capital. Determining the
Accordingly, to manage the cash flow is to manage its compo-
working capital accurately helps contractors liquidate projects
nents—namely, cash flow out and cash flow in.
with ease and comfort.
Cash flow analysis, as reported by 60% of the participating
contractors, assists them in determining and including the cost
of financing in bid prices. Only 45% of the participating con- Cash Flow Out: Project Expenditures
tractors reported that they forecast cash flow to determine the A contractor expends available cash during the project con-
amount of overdraft. Calculating the overdraft amount plays a structing process. These expenditures are classified as either
vital role in determining a suitable financing method; less than direct or indirect costs. Direct costs consist of materials, equip-
50% of the participating contractors, however, conduct cash ment, labor, subcontractors, suppliers, and job overhead costs
flow analysis to determine the amount of the overdraft. It could that are traced back directly to the project. The direct cost
be inferred that the participating contractors conduct simple signifies the highest percentage of the total cost of a project.
cash flow models, which fail to determine the amount of over- Thus, the direct cost should be managed closely to maintain a
draft and, hence, decide on the suitable financial technique. positive financial status for a project. The indirect cost category
54 Project Management Journal 49(5)
40% 44%
30%
30%
20%
10% 13%
9%
0%
4%
Less than 20% to less 30% to less 50% to less Equal to or
20% than 30% than 50% than 70% more than 70%
includes cost items, such as office overhead, which are not comprised less than 20% of the total cost of the projects he had
directly traced back to a particular project. Office overhead constructed. The researchers observed from this contractor’s
includes costs that are generated by management and adminis- profile that he offers services that are limited to industrial
trative activities. Unlike direct costs, indirect cost marks a equipment installation and operation. At the other extreme, two
small percentage of the total cost of a project. Typically, over- contractors (9%) stated that the materials cost represents more
head accounts for less than 5% of the total project cost (Halpin than 70% of the total project cost. It was observed that these
& Senior, 2009). two contractors construct special structures, such as railways
The participating contractors revealed the direct and indirect and precast concrete buildings, where materials have a very
costs (cash flow out) of their undertaken projects. high contribution to the total costs of the project. Material cost
contribution to a project total cost is presented in Figure 3.
The participating contractors indicated that they pay mate-
Direct Cost rials suppliers using a combination of various financing tech-
The participating contractors identified as direct costs the pur- niques. It seems that contractors value the importance of
chased materials and equipment, as well as payments to timely availability of materials and, hence, rely less on limited
laborers, subcontractors, and project management. These are sources to fund this cost item. The majority (56%) of the
the primary sources of cash outflow and are considered and contractors use credit financing for materials. Contractors
accounted for as part of the project direct cost. prefer credit financing because they pay for the delivered
materials after a certain period of the delivery date, which is
typically 30 days. This arrangement gives contractors ample
Materials time until owners pay them against the incurred materials
The constituents of a finished or partially finished product are cost. About 44% and 48%, respectively, of the contractors use
the sources of the material costs. The majority (44%) of the progress payments and advance payments to pay for materi-
participating contractors reported that the material costs als. Few contractors (16% of the participants) pay suppliers
accounted for 30% to 50% of the total costs of projects they from their own accounts.
constructed. Ross and Williams (2013) reported similar find-
ings and stated that the contribution of material costs in con-
struction projects typically ranges from 30% to 50% of the total
Labor
project cost. The results still indicate that about 30% and 13% Labor cost is the sum of all wages paid to laborers, as well as
of the participating contractors reported that materials cost the cost of labor benefits. Contractors in Saudi Arabia pay
comprised 50% to 70% and 20% to 30%, respectively, of the workers monthly and usually at the end of the Gregorian
total costs of the projects they constructed. It seems that the month. The majority (83%) of the participating contractors
participants contract for projects with different scopes of work. reported that the labor cost contributes less than 30% to the
For example, in some contracts, the contractor is responsible total cost of the project. Ross and Williams (2013) reported
for supplying all or most of the project materials, whereas in similar labor cost contributions to total project cost. This per-
other contracts, the owner participates in providing a signifi- centage represents the contractor labor cost contribution and,
cant portion of the materials. This observation was clear from hence, could be marginally higher.
the answers furnished by the remaining participating contrac- Contractors may engage subcontractors to execute parts of a
tors. Interestingly, one contractor indicated that materials cost project. It seems that contractors in certain circumstances
Shash and Qarra 55
50%
50%
40%
30% 33%
20%
10% 13%
4% 0%
0%
Less than 20% to less 30% to less 50% to less Equal to or
20% than 30% than 50% than 70% more than 70%
prefer to hire subcontractors to provide laborers to execute Table 4. Techniques Used to Pay for Equipment in Construction
elements of the project rather than hire laborers directly. One Projects
contractor reported that the labor cost contribution ranges from
Techniques Number of Responses Percentage
50% to 70% of the total project cost. It seems that this contrac-
tor provides his services to owners who supply most of the Advance payment 4 16
needed materials; thus, the scope of the contractor in these Company assets 15 60
contracts is mainly limited to providing the needed workforce Bank loans 4 16
Progress payments 9 36
for the project. Labor cost contribution to total project cost is
Credit 6 24
presented in Figure 4.
Mobilization
Equipment
The results demonstrated that about 88% of the participating
A high proportion of the participating contractors—almost contractors reported that mobilization costs typically account
83%—reported that the equipment cost (owning and operating) for less than 3% of the total project cost. The majority (80%) of
comprises less than 20% of the total project cost, although the participating contractors pay for mobilization costs using
about 8% stated that their average equipment cost was between the owners’ advance payments, when applicable. About 44% of
50% and 70% of the total project cost. Because the nature of the the participating contractors reported that they use their own
projects undertaken by the different contractors varies, it is cash to liquidate mobilization costs. The other contractors
understandable that there would be such a high variance in showed different financing modes, such as bank loans and lines
equipment cost. Most of the participating contractors construct of credit.
buildings, which are labor intensive rather than equipment
intensive. In addition, some contractors undertake projects that
rely mainly on providing costly types of special equipment.
Overhead
The results indicate that the majority (60% and 24%, respec- The results indicate that about 88% of the participating con-
tively) of the participating contractors use company assets and tractors stated that the project overhead cost was less than 10%
credit financing to pay for the equipment hired for short periods of the total project cost. Similarly, about 80% of the
56 Project Management Journal 49(5)
120%
100%
Percentage of Contract Price
80%
60%
40%
20%
0%
-20%
-40%
Project Project Project Project Project Project
Start Progress Progress Progress Progress Completion
Figure 5. Owners’ payments’ locations and values over a hypothetical project duration.
60%
Progress Payments Delay
Percentage of Respondents
50% 53%
40%
30%
26.70%
20%
10% 13.30%
6.7%
0%
Less than 30 days 30 to less than 60 days 60 to less than 90 days 90 to less than 120 days
beyond their due date beyond their due date beyond their due date beyond their due date
general, the idea behind this credit system is to establish a progress payment delay has major effects on contractors and
system that enables the owner to pay the project expenses in owners. The delay disturbs a contractor’s financial cash flow
a way that supports the contractor effectively while concur- and subjects the contractor to unnecessary stress from credi-
rently securing the owner. tors. The delay may increase the cost of the project through
The participating contractors reported that they are some- additional charged interests on the amount of delayed prog-
what satisfied with the timing of owners’ progress payments. ress payment.
Almost 52% stated that they receive payments on time, The participating contractors indicated that owners delay
whereas the other 48% showed that owners delay payments payments for several reasons. The majority (65%) of the con-
beyond their due dates. Figure 6 presents the delay distribution tractors stated that the approval process for invoiced work in an
in owners’ progress payments as reported by the contractors owner organization is a significant factor in delaying payments.
who receive payments beyond their scheduled times. In fact, It seems that invoices pass through many offices for approval.
58 Project Management Journal 49(5)
Table 6. Reasons for Owners’ Payment Delays and suppliers. This strategy is very harmful to the business of a
contractor. Labor productivity and reputation may suffer dearly
Reasons Number of Responses Percentage
from the application of such a policy. Few contractors (about
Disputes 1 5 7%) of the participants continuously and fiercely follow-up on
Not enough budget 1 5 payment requests with owners and possibly slow down work.
Bureaucracy 6 25 About 27% of the contractors, after exhausting the above
Corruption 0 0 actions, say that they stop work until payments are made. It
Approval process 17 65
is apparent that the contractors incorporate these delayed pay-
ments into their financial model.
Table 7. Actions Toward Owners’ Payment Delays
Retained profit 38% 29.5 High 1.2 High 1.4 High 1.3 Medium 1.6
Equity 35% 30.5 High 1.1 Medium 1.2 Medium 1.1 Medium 1.5
Trade credit 27% 23.3 High 1 High 1.4 High 1.4 Medium 1.4
Total/average 100% - High High High Medium
is considered a self-financing technique because banks are not contractors more than one year to construct, long- and mid-
part of the financing; this occurs between contractors and their term loans satisfy the financial requirements. The participat-
creditors, such as material suppliers. ing contractors believe that loan facilities are very suitable,
The participating contractors appreciated the self- effective, reasonable in finance charges, and moderate in the
financing techniques and stated that they are highly suitable risk involved.
for their businesses, highly effective in financing, and
involved average risk.
Overdraft Accounts
An overdraft allows contractors to borrow money through their
Debt-Financing Techniques bank accounts based on a loan arrangement under which the
Banks furnish various types of facility services to contractors. bank extends credit up to a maximum amount (called the over-
Commonly, once a bank committee approves a contractor’s draft limit) against a current (checking) account through which
request for a banking facility, the contractor has access to cash the contractor can write checks or make withdrawals. It is
in accordance with a loan agreement between the contractor simply an extension of credit from a lending institution when
and the financial institution (bank). This agreement states that an account reaches zero. It is, however, a demand loan; the
the bank finances the contractor with a specific amount of facility can be canceled and the entire outstanding amount may
capital and the contractor, in turn, provides guarantees to repay be called at any time by the lender at its discretion, without any
the lent money with an interest charge. warning or explanation. This type of banking facility is used
Generally, the types of banking facilities can range from only for emergencies or short-term borrowing, and contractors
short- to long-term financing. Short-term financing is usually diligently schedule overdraft payments within a short period.
used to fund changes in a predicted amount of a working capital The participating contractors showed that they understand the
of a project, while long-term financing is applied to fund the risk associated with this type of financing and, hence, only
general operations of the company (Ross & Williams, 2013). utilize it, on the average, at a rate of 4.5% of the different
The first column in Table 11 presents the various banking banking facilities. They believe that overdraft facility is appro-
facilities that banks commonly supply to contractors. Table priate because of its effectiveness, low interest charges, and
11 is similar to Table 10, but shows debt-financing rather than low risk. It seems that when contractors decide to use this type
self-financing techniques. The respondents were also asked to of facility, they use extra caution not to exceed the credit limit
measure the performance of debt-financing techniques in terms and pay the overdraft back on time.
of their suitability, finance effectiveness, cost, and involved
risk using similar measurements as those shown in Table 10.
Invoice Financing
Invoice financing is a form of short-term borrowing often used
Bank Loans to improve a company’s working capital and cash flow posi-
The results indicate that the contractors use all available bank- tion. Invoice financing allows a contractor to draw money
ing facilities to fund their construction operations. The largest against its invoices of progress payments before the owner has
amounts of funds that contractors secure from banks are the actually paid. In order to do this, the contractor borrows a
loan facilities. Loans are typical forms of banking facilities percentage of the value of its invoice from a bank, effectively
and consist of short-term, mid-term, and long-term loans. The using the unpaid sales invoices as collateral for borrowing. The
participating contractors reported that bank loans made up participating contractors indicated that invoice financing com-
44.2% of their banking facilities, with long- and medium- prises about 18% of the amount of cash they borrow to fund
term loans being the most popular, accounting for about their operations. It appears that contractors use invoice financ-
73% of the loans. Short-term loans make up only about 27% ing when owners delay progress payments, which is common.
of the loans used by contractors. The participating contractors believe that invoice financing is a
The nature of construction projects dictates the selection of highly effective and highly suitable technique, despite its high
the loan type. It seems that for projects that take participating risk and high interest charges.
Shash and Qarra 61
Loans Long term 11.80 18.8 Medium 1.5 Medium 1.5 Medium 1.3 Medium 1.1
Short term 26.20 34.5 Medium 1.4 Medium 1.2 Medium 1.0 Medium 1.0
Term 6.20 14.2 Medium 1.7 Medium 1.5 Medium 1.6 Medium 1.4
Overdraft accounts 4.60 6.0 Medium 1.2 Medium 1.3 Low 1.4 Low 1.2
Invoice financing 18.20 20.4 High 1.0 High 1.3 High 0.9 High 1.6
Bonds Bid 4.70 6.3 Medium 1.2 Medium 1.5 Medium 1.5 Medium 1.5
Advance 6.10 6.6 High 1.2 High 1.0 High 1.0 Medium 1.5
payment
Performance 4.80 5.4 Medium 1.5 Medium 1.2 Medium 1.4 Low 1.4
Retention 3.90 5.2 Medium 1.4 Medium 1.3 Medium 1.2 Medium 1.3
Letters of credit 11.40 13.2 High 0.9 High 0.9 High 0.8 Medium 1.3
Hire purchase/ 2.10 4.3 Medium 1.2 Medium 1.1 Medium 1.0 Medium 1.1
leasing
Total/average 100% – Medium Medium Medium High
contractors receive monthly progress payments, with delays Monitor and control subcontracts and ensure on-time
attributed to owners’ approval processes for invoiced work progress payments.
and bureaucracy. Restrict the available cash in a project account to its
The contractors depend on self-financing techniques, construction activities only and refrain from moving
including retained profit, equity, and trade credit, rather than cash from one project to another.
bank loans to finance construction projects. The contractors
also use all kinds of banking services, especially those required Owners are advised to be prompt in paying contractors’ prog-
by contracts, in running their businesses. These self-financing ress payments and to reconsider the implementation of reten-
and banking services are used to pay for material costs and tions in projects, especially in projects where performance and
labor salaries, equipment, subcontractors, overhead, and mobi- payments bonds are applied.
lization costs. Materials, subcontractors, and labor costs com-
prise the highest portion of a project’s total cost. A significant Declaration of Conflicting Interests
percentage of contractors in Saudi Arabia (40%) undergo a The author(s) declared no potential conflicts of interest with respect to
financial failure as a result of poor cash flow management in the research, authorship, and/or publication of this article.
at least one of their annual contracts. Delays in advance payment
and/or progress payments and project delays have very severe Funding
effects on cash flow over the duration of a project. The author(s) received no financial support for the research, author-
In conclusion, projects in Saudi Arabia are executed ship, and/or publication of this article.
according to the well-established cash flow baseline forecast
of cash inflow and outflow, used for control purposes. Some References
owners make advance payments to help contractors start proj- Akintoye, A., & Fitzgerald, E. (2000). A survey of current cost esti-
ects, pay progress payments to contractors on time, and pay mating practices in the UK. Construction Management and Eco-
final payments, including retentions, on time. Contractors nomics, 18(2), 161–172.
apply certain practices to manage their cash outflows and Al-Barrak, A. (1993). Causes of contractors’ failures in Saudi Arabia,
deficits. They tie their payments to suppliers and subcontrac- Arabia (M.Sc. thesis). King Fahd University of Petroleum and
tors to owners’ progress payments and make use of deficits Minerals, Dhahran.
from either their own accounts and/or from banks. Unfortu- Al-Dulaijan, S. U. (1987). Construction financing in Saudi Arabia
nately, some contractors, apply poor practices that subject (M.Sc. thesis). King Fahd University of Petroleum and Minerals,
their companies to bankruptcy situations. Some contractors Dhahran.
use cash from other ongoing projects to finance the activities Boussabaine, A. H., & Elhag, T. (1999). Applying fuzzy techniques to
of a project with a deficit. cash flow analysis. Construction Management and Economics,
The contractors are advised to improve current cash flow 17(7), 745–755.
management practices by implementing detailed forecasting Boussabaine, A. H., & Kaka, A. P. (1998). A neural networks
prior to the bidding stage, and monitoring and updating the approach for cost-flow forecasting. Construction Management and
forecasted model continuously over the stages of the project’s Economics, 16(4), 471–479.
execution. Following are suggestions that may improve the Bromilow, F. J. (1978, March). Multi-project planning and control in
cash flow process for contractors: construction authorities. Building Economist, 208–213.
Crundwell, F. (2008). Finance for engineers: Evaluation and funding
Study the characteristics of projects under bid and of capital projects. London, England: Springer-Verlag.
the contract conditions very thoroughly and ensure Cui, Q., Hastak, M., & Halpin, D. (2010, April). System analysis of
that they are adequate for the contractor’s financial project cash flow management strategies. Construction Manage-
status. ment and Economics, 28, 361–376.
Benefit from cash flow analysis in determining the Gatti, S. (2008). Project finance in theory and practice. San Diego,
amount of deficit to decide on the proper financing tech- CA: Academic Press.
nique and, thus, estimate the cost of financing. Halpin, D. W., & Senior, B. (2009). Financial management and
Consider contingency factors while preparing a cash accounting fundamentals for construction. Hoboken, NJ: John
flow forecasting model. An owner’s payment delay, Wiley & Sons.
project delay, and absences of certain financing sources Hendrickson, C. (1998). Project management for construction. Pitts-
should all be accounted for in the forecasting process. In burgh, PA: Prentice-Hall.
other words, more “what if” models should be applied Isidore, L. J., & Back, W. E. (2002). Multiple simulation analysis
prior to considering the final shape of the cash flow for probabilistic cost and schedule integration. ASCE Journal of
forecast. Construction Engineering and Management, 128(3), 211–219.
Control project materials cost, ensure a good relation- Kaka, A., & Price, A. D. (1991). Net cash flow models: Are they
ship with project suppliers, and effectively utilize con- reliable? Construction Management and Economics, 9(3),
tractor credit with them. 291–308.
Shash and Qarra 63
Kaka, A., & Price, A. D. (1993). Modeling standard cost commitment Ross, A., & Williams, P. (2013). Financial management in construc-
curves for contractors. Construction Management and Economics, tion contracting. Oxford, England: John Wiley & Sons.
11(4), 271–283. Steffan, B. B. (2008). Essential management accounting: How
Kenley, R. (2003). Financing construction. London, England: Spon to maximise profit and boost financial performance. London,
Press. England & Philadelphia, PA: Kogan Page.
Kenley, R., & Wilson, O. D. (1986). A construction project cash flow Tarek, Z., & Yaqiong, L. (2014). Cash flow modeling for construction
model—An idiographic approach. Construction Management and projects. Engineering, Construction and Architectural Manage-
Economics, 4(3), 213–232. ment, 21(2), 170–189.
Likert, R. (1932). A technique for the measurement of attitudes. Tucker, S. N. (1986). Formulating construction cash flow curves using
Archives of Psychology, 140, 1–55. a reliability theory analogy. Construction Management and Eco-
Lipsey, M. (1990). Design sensitivity: Statistical power for experi- nomics, 4(3), 179–188.
mental research. Thousand Oaks, CA: Sage Publications. Watson, T., & Noble, P. (2007). Evaluating public relations: A best
Miskawi, A. (1989). An S-curve equation for project control. Con- practice guide to public relations planning, research and evalua-
struction Management and Economics, 7(2), 115–124. tion (2nd ed.). London, England & Philadelphia, PA: Kogan Page.
Mutti, C. D. N., & Hughes, W. (2002, September 2–4). Cash flow Yescombe, E. R. (2014). Principles of project finance (2nd ed.).
management in construction firms. In D. J. Greenwood (Ed.), 18th Kidlington, England: Elsevier Science.
annual ARCOM conference: Association of Research in Construc-
tion Management (Vol. 1, pp. 23–32). Northumbria, UK: Univer-
sity of Northumbria. Author Biographies
Navon, R. (1996). Company level cash-flow management. Journal of
Dr. Ali A. Shash is a Professor in the Construction Engineering
Construction Engineering and Management, 122(1), 22–29.
and Management Department of the College of Environmental
Odeyinka, H. A., Kaka, A., & Morledge, R. (2003, September 3–5). An
Design at King Fahd University of Petroleum and Minerals
evaluation of construction cash flow management approaches in
(KFUPM), Dhahran, Saudi Arabia. He is also the director of
contracting organizations. In D. J. Greenwood (Ed.), 19th annual
the Construction Industry Institute at KFUPM. He can be con-
ARCOM conference: Association of Researchers in Construction
tacted at aashash@kfupm.edu.sa or aashash854@gmail.com
Management (Vol. 1, pp. 33–41). Brighton, England: University of
Brighton. Abdulaziz Al Qarra is a graduate student at the Construction
Peer, S. (1982). Application of cost flow forecasting models. Journal Engineering and Management Program, King Fahd University
of Construction Division, AACE, 108(2), 226–232. of Petroleum and Minerals (KFUPM), Dhahran, Saudi Arabia.
Purnuş, A., & Bodea, C. (2015). Financial management of the con- He is also a Project Manager in the Project and Development
struction projects: A proposed cash flow analysis model at project Services Department, JLL (Jones Lang LaSalle)—MENA,
portfolio level. Organization, Technology and Management in Saudi Arabia. He can be contacted at asqarra@gmail.com or
Construction International Journal, 7(1) 1217–1227. Abdulaziz.AlQarra@eu.jll.com