PROJECT NAME : PANAPAAN 1A Date: June 24, 2024

PROJECT CODE : 24DQ0003


LOCATION : Panapaan, Bacoor, Cavite
PROGRAM LENGTH : 517.2 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : SSP, CW

SHEETPILING
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Drivin : 1,200.00 1,200.00 1,293.00 93.00 92.81%
Embankment : 250.00 860.00 1,293.00 433.00 66.51%
TOTAL 79.66%

CIVIL WORKS
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Pile Cap : 475.00 480.00 517.20 37.20 92.81%
Slope : 475.00 480.00 517.20 37.20 92.81%
Slab : 350.00 480.00 517.20 37.20 92.81%
Retaining Wall : 350.00 480.00 517.20 37.20 92.81%
Parapet Wall : 224.00 350.00 517.20 167.20 67.67%
Finishing : 224.00 260.00 517.20 257.20 50.27%
TOTAL 81.53%

Prepared by :
MARLON CARDOZA
CCS President
PANAPAAN PROJECT SHEETPILING ACCOMPLISHMENT

1,293.00
TARGET LENGTH
1,293.00
860.00
CURRENT STATUS
1,200.00
- 200.00 400.00 600.00 800.00 1,000.00 1,200.00 1,400.00

Embankment Drivin

PANAPAAN PROJECT CIVIL WORKS ACCOMPLISHMENT


CURRENT STATUS LENGTH

Fi n i sh i n g 331.00 517.20

P ar ap et W al l 331.00 517.20

R et ai n i n g W al l 444.30 517.20

Sl ab 388.00 517.20

Sl ope 388.00 517.20

P i l e Cap 444.30 517.20


Sl ope 388.00 517.20

P i l e Cap 444.30 517.20


PROJECT NAME : MOLINO EXT DAM Date: June 24, 2024
PROJECT CODE : 24DQ0045
LOCATION : Molino, Bacoor, Cavite
PROGRAM LENGTH : 400 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : SSP, CW

SHEETPILING
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Drivin : - 680.00 1,000.00 320.00 68.00%
Embankment : - 350.00 1,000.00 650.00 35.00%
TOTAL 51.50%

CIVIL WORKS
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Pile Cap : 98.00 118.00 400.00 282.00 29.50%
Slope : 54.00 98.00 400.00 302.00 24.50%
Slab : - - 400.00 400.00 0.00%
Retaining Wall : - - 400.00 400.00 0.00%
Parapet Wall : - - 400.00 400.00 0.00%
Finishing : - - 400.00 400.00 0.00%
TOTAL 9.00%

Prepared by :
MARLON CARDOZA
CCS President
MOLINO EXT DAM SHEETPILING ACCOMPLISHMENT
Drivin Embankment

TAR G ET L ENG TH 1,000.00 1,000.00

C UR RENT STATUS 680.00 237.50

MOLINO EXT DAM CIVIL WORKS ACCOMPLISHMENT


CURRENT STATUS LENGTH

P ar ap et
W al l - 400.00

R et ai n i n g
W al l - 400.00

Sl ab - 400.00

Sl ope 120.00 400.00

P i l e Cap 140.00 400.00


Sl ope 120.00 400.00

P i l e Cap 140.00 400.00


PROJECT NAME : MOLINO PAG ASA Date: June 24, 2024
PROJECT CODE : 24DQ00
LOCATION : Molino, Bacoor, Cavite
PROGRAM LENGTH : 140 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : SSP, CW

SHEETPILING

SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE

Drivin : 198.00 202.00 350.00 148.00 57.71%


Embankment : 145.00 145.00 350.00 205.00 41.43%
TOTAL 49.57%

Prepared by :
MARLON CARDOZA
CCS President
MOLINO PAG ASA PROJECT ACCOMPLISHMENT
Drivin Embankment

TAR G ET L ENG TH 350.00 350.00

C UR RENT STATUS 202.00 145.00


PROJECT NAME : KAWIT 1 PROJECT Date: June 24, 2024
PROJECT CODE : 24DF0104
LOCATION : Kawit, Cavite
PROGRAM LENGTH : 594 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : SSP, CW

SHEETPILING
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Drivin : - 850.00 1,485.00 635.00 57.24%
Embankment : - 813.00 1,485.00 672.00 54.75%
TOTAL 55.99%

Prepared by :
MARLON CARDOZA
CCS President
KAWIT 1 PROJECT SSP ACCOMPLISHMENT
Drivin Embankment

TAR G ET L ENG TH 1,485.00 1,485.00

C UR RENT STATUS 850.00 813.00


PROJECT NAME : MOLINO REPAIR SOLDIERS AREA Date: June 24, 2024
PROJECT CODE :
LOCATION : Soldiers, Molino, Bacoor, Cavite
PROGRAM LENGTH : 150 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : CW

CIVIL WORKS
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Pile Cap : 85.00 150.00 65.00 56.67%
Slope : 35.00 150.00 115.00 23.33%
Slab : - 10.00 150.00 140.00 6.67%
Retaining Wall : - 22.00 150.00 128.00 14.67%
Parapet Wall : - - 150.00 150.00 0.00%
TOTAL 20.27%

Prepared by :
MARLON CARDOZA
CCS President
MOLINO REPAIR SOLDIERS AREA
CURRENT STATUS LENGTH

P a r a p e t W a l l 10.00 150.00

R et ai n i n g W al l 22.00 150.00

Sl ab 12.00 150.00

Slope 40.00 150.00

P i l e Cap 85.00 150.00


PROJECT NAME : MOLINO REPAIR SAN NICOLAS AREA Date: June 24, 2024
PROJECT CODE :
LOCATION : SAN NICOLAS, Molino, Bacoor, Cavite
PROGRAM LENGTH : 71 LM
SUBCONTRACTOR : MARLON CARDOZA
SCOPE OF WORKS : CW

CIVIL WORKS
SCOPE OF WORKS PREVIOUS CURRENT STATUS LENGTH BALANCE % DONE
Pile Cap : 26.00 71.00 45.00 36.62%
Slope : 8.00 71.00 63.00 11.27%
Slab : - - 71.00 71.00 0.00%
Retaining Wall : - - 71.00 71.00 0.00%
Parapet Wall : - - 71.00 71.00 0.00%
TOTAL 9.58%

Prepared by :
MARLON CARDOZA
CCS President
MOLINO REPAIR SAN NICOLAS ACCOMPLISHMENT
Parapet Wall- 71.00

Retaining- 71.00
Wall

Slab - 71.00

Slope 14.00 71.00

Pile Cap 27.00 71.00

- 20.00 40.00 60.00 80.00 100.00 120.00

CURRENT STATUS LENGTH