Date : 02-Jul-24

Supplier : Marlon Cardoza


Contact no: 9817554093
Title : BOM Installation of Canopy (Labor and Materials )

Item Description Quantity Unit Materials Cost Labor Cost Amount


1 General Requirements
1.1 Mobilization/Demobilization 1.00 l.s 32,000.00 32,000.00
1.2 PPE and Safety 1.00 l.s 8,500.00 8,500.00
1.3 Scaffolding Set 1.00 l.s 23,000.00 23,000.00
T O T A L 63,500.00

2 Installation of Canopy ( including Consumables)


2.1 CCSR3 I-Beam 2,077.20 kls 62.00 29.14 189,316.01
2.2 CCSR1 I-Beam 3,137.40 kls 62.00 29.14 285,942.64
2.3 CCSB1 I-Beam 3,391.20 kls 62.00 29.14 309,073.97
2.4 CSR3 I-Beam 781.20 kls 62.00 29.14 71,198.57
2.5 CSR1 I-Beam 1,058.40 kls 62.00 29.14 96,462.58
2.6 CSR2 I-Beam 797.40 kls 62.00 29.14 72,675.04
2.7 Tubular ( 50x150x1.2mm thk @ 6 m 62.00 pcs 1,350.00 634.50 123,039.00
2.8 End Plate ( 550x800x32mm thk ) 2.00 pcs 6,500.00 3,055.00 19,110.00
2.9 End Plate ( 500x800x32mm thk ) 2.00 pcs 6,100.00 2,867.00 17,934.00
2.10 End Plate ( 250x800x25mm thk ) 2.00 pcs 5,800.00 2,726.00 17,052.00
2.11 Bolts and Nuts 52.00 pcs 850.00 95.00 49,140.00
T O T A L 1,250,943.79
Total Cost : 1,314,443.79
12% Vat : 157,733.26

AMOUNTING TO : 1,472,177.05

NOTE : As per Payment ( Bank Transfer )


70 % = Down Payment ( Purchase of Materials and Mobilization)
20 % = Progress Billing
10 % = Final Billing one week upon Inspection
100 % (Project Completion )

Prepared by : Approved by :

Marlon Cardoza
CCS President