Excel Power Query in Planning


You might have heard before about the Microsoft Excel Power Query. However, have you ever used
it in your daily planning tasks? In this article, I want to give you some more information about the
application of power queries in construction planning. Don’t worry, it is very simple and very easy.

A. What is a power query?


I will not talk from a technical point of view. I will talk from a practical and simple point of view.
This power query is your assistant. If you have a secretary who will listen to your requests and
do it perfectly whenever you ask.

B. Advantages of Power Query


1. It can do many tasks very Fast
2. It will do the tasks in the order you told it
3. Order comes First, Served First
4. It saves you orders in case you need to repeat it later on
5. It can do several tasks in one order

C. Power query in planning


Following I will give you some examples of Excel query applications in the construction planning
field. When you get used to it, I am sure you will use it in your daily tasks.

1- Replace values in your sheets:


We all copy data from Primavera P6 to use in reports in Excel. One common issue is when
you copy the data, some blank spaces before the activity ID are there. Using Excel power
query, you can set up an automatic process to remove blank spaces from a column
automatically.

Right Click on BOQ Ref and Choose Replace Values

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 1 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

2- Convert P6 data distribution to pivot table


If you are trying to create an Excel pivot table to show the weekly, and monthly progress for
example, you can copy the data from resource assignment; however, the data will be stored
in every week/month column.

Using power query you can unpivot the columns to store the date and value in 2 columns
only where you can perfectly use them in your pivot tables.

Choose the needed Columns and Right click on them choose Unpivot Columns

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 2 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

3- Combine 2 tables:
Using Power Query, we can combine two tables. This is very useful when you are doing cost
loading. If you define each activity with its relevant BOQ item, then you can combine these
two tables to create a new table with the activity budget cost.

We just need to tell what is the link between the two tables so it can create a proper Merge.
In our case, BOQ Ref is the link between the Two Tables

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 3 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

4- Create Custom Calculated Columns


This is a very useful feature. Let’s say you copy some data from Primavera, and you use this
data in an Excel report. However, you need to do some calculations before being able to
create your report. For example, you need to multiply the % completed by certain resources
in your schedule. You can do it easily using power query custom calculated columns.

5- Conditional Columns
You can create a column that gets its data from another column based on column value.
Something similar to VLockup. But here, it is much faster for large data and automated. It
means whenever your data is changed, the same conditions will apply. No need to drag
formulas. I am using this feature in the cost control process to define the materials costs,
labor costs, equipment costs…etc.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 4 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

6- Using different columns from different tables


By creating relationships between your tables, you can create a pivot table using different
columns from different tables.

I am using the Date for example to Order Date that should be done. Then I can compare it
with the actual date of the material duration to define the Procurement.

Now we will start creating relationships between tables. Click on a Column from a sheet to
another column in the other sheet

D. Following are some applications we used on the Intermediate Planning


Course:
• Calculate the quantity and value of each BOQ item per floor based on floor weight.

• Creating activities ID based on Master Activity ID.

• Create a Relationships sheet for all floors based on Mater Activity relationships.

• Create Relationships between Shop drawing approvals and relevant construction activities.

• Create Relationships between materials delivery and relevant construction activities based
on Master ID.

• Assign Crew hours to activities and calculate the detailed working hours per activity and
trade.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 5 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

To be honest, the Excel power query helped me a lot in my daily tasks as a planning manager. It is
amazing when you develop a data model to perform several steps with your data and store it in one
query which you can refresh in a few seconds to update all your data accordingly. Having such a
feature encouraged me to create a powerful course for cost control in construction projects using
this technique. It is powerful, simple, and easy. You are welcome to check the course from the below
link.

E. Want to learn more?


Check the below links for the cost control course and Intermediate Planning Course where you
will learn Excel Power Query and implement it in the Baseline creation & cost control data
model. This is a smart way to manage your project with minimal effort.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 6 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

Article Link: https://planningengineer.net/excel-power-query-in-planning/

---------------

Useful links:

Join our email Newsletter, we send useful free content regularly:


https://planningengineer.net/newsletter/

Our Services https://planningengineer.net/our-services/

Our Courses: https://planningengineer.net/lp-courses/

Support Forums: https://planningengineer.net/forums/

Free Arabic Basic Course Playlist:


https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J

---------------

Keep in Touch:

WhatsApp: +201277767728

Email: Info@PlanningEngineer.Net

English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos

Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906

Linked in: https://www.linkedin.com/company/planning-engineer-est/

Facebook Page: https://www.facebook.com/PlanningEngineerDotNet

Facebook Group: https://www.facebook.com/groups/1138400132963230

Twitter: https://twitter.com/PlanningEEst

Instagram: https://www.instagram.com/planningengineerest/

TikTok: https://www.tiktok.com/@planningengineerest

---------------

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 7 of 7

You might also like