Sample Form Process Change Request (Revisi)
Process Detail POTONG --> NOTCHING POTONG --> BENDING --> NOTCHING -->
POTONG --> SELEP
SM-CIRCSAW (1MS/1OP) --> SM-CNCBEND (1MS/1OP) -->
Resource (Machine/Operator) SM-GRDPOT (1MS/1OP) --> SM-NOTCHING (1MS/1OP) SM-NOTCHING (1MS/1OP) --> SM-GRDPOT (1MS/1OP) -->
* Include Quantity SM-ARBOGA (1MS/1OP)
Material LBPBW0100026 (BLACK PIPE DIA. 1” (T=2MM) LIGHT) TETAP
Target GP1: 1806 , NC1: 560 CS1: 1169 , CB1: 721, NC1: 736, GP1: 585,
AB1: 1300
Ingredients/BoM: 1 pcs Ingredients/BoM: 1 pcs
Nesting Improvement By Product/Afval: 0 kg By Product/Afval: 0.7 kg
Product : 14 pcs Product : 14 pcs
% Target Productivity : -141,3%
Procentage Improvement (%) % Nesting Improvement : 0,4 %
Etc :
Tgl : 04/12/22 Tgl : 05/12/22 Tgl : 06/12/22 Tgl : 07/12/22 Tgl : 08/12/22
PE PCR Note: 1. Cost Up / Cost Down: 141,3 % (Routing & Target) V PCR Diterima V PCR Diterima
2. Perbaikan proses perlu dilakukan karena terkait kualitas - PCR Ditolak - PCR Ditolak
*Jika terjadi penurunan produktivitas dan potensi Cost Up (di luar kasus Process Standardization & Quality), harus approval sampai Level Ka.Dept.Produksi