1.0 Piling
Supply 150mm x 150mm precast concrete Piles
1.1 Initial 3m m
1.2 Initial 6m m
1.3 Extension 3m m
1.4 Extension 6m m
2.0 Excavation
2.1 Hardcore m3
2.2 Sand m3
3.0 Bricks
3.1 Clay Brick
No
3.2 Cement and Sand Bricks
No
SOMP 1
SCHEDULE OF MATERIAL PRICE
4.0 Cement
4.1 Cement (ordinary) Bg
4.2 Aggregate
Limestone
4.2.1 Limestone 20mm MT
4.2.2 Limestone 40mm MT
4.2.3 Limestone 19mm MT
Granite
4.3.1 Granite 38mm MT
4.3.2 Granite 25mm MT
4.3.3 Granite 19mm MT
5.0 Reinforcement
5.1 Mild Steel Bar 10mm Diameter MT
5.2 Ditto 12mm Dia MT
5.3 Ditto 16mm Dia MT
5.4 Ditto 20mm Dia MT
5.5 Ditto exc. 25mm Dia MT
5.6 High Tensile Bar 9/10mm Diameter MT
5.7 Ditto 16mm Dia MT
5.8 Ditto 20mm Dia MT
5.9 Ditto 25mm Dia MT
5.10 Ditto exc. 25mm Diameter MT
SOMP 2
SCHEDULE OF MATERIAL PRICE
6.1 A6 MS
6.2 A7 MS
6.3 B6 MS
6.4 B7 MS
6.5 B8 MS
6.6 C6 MS
6.7 C7 MS
6.8 C8 MS