Professional Documents
Culture Documents
Project Report After Check(1)
Project Report After Check(1)
ON
Submitted by
BISHAL KALITA 200810001008
DEBASHISH ACHARJEE 200810001013
RIKUL DEKA SARANIA 200810001040
SIDDHARTHA PATHAK 200810001048
KAUSHIK GOHAIN 210850001003
Submitted to
AFFILIATED TO
ASSAM SCIENCE AND TECHNOLOGY UNIVERSITY
Design of frame for proposed Library and Computer
centre at JIST campus, Jorhat
Code No.: CE181822
Submitted by
BISHAL KALITA 200810001008
DEBASHISH ACHARJEE 200810001013
RIKUL DEKA SARANIA 200810001040
SIDDHARTHA PATHAK 200810001048
KAUSHIK GOHAIN 210850001003
Under the
Supervision of
Submitted to-
i
CERTIFICATE FROM SUPERVISOR
The results contained is this report have not been submitted in part or
full to any other institute or university for award of any degree of
diploma.
Date: ………….……………………..
Place: Dr. Atanu Kumar Dutta
Supervisor
Professor
Department of Civil Engineering
Jorhat Institute of Science and Technology,
Jorhat-10
ii
Certificate of Approval from Department of
Civil Engineering, Jorhat Institute of Science &
Technology
The undersigned certify that the project report entitled “Design of frame
for proposed Library and Computer centre at JIST campus, Jorhat”
have been read and recommended to the Department of Civil
Engineering for acceptance, in partial fulfillment for the Degree of
Bachelor in Civil Engineering.
Submitted by-
Bishal Kalita 200810001008
Debashish Acharjee 200810001013
Rikul Deka Sarania 200810001040
Siddhartha Pathak 200810001048
Kaushik Gohain 210850001003
………….…………………
Dr. Atanu Kumar Dutta
Supervisor
Professor
Department of Civil Engineering
Jorhat Institute of Science and Technology, Jorhat-10
………….…………………
Dr. Pranab Jyoti Barman
Head of the Department
Department of Civil Engineering
Jorhat Institute of Science and Technology, Jorhat–10
iii
Certificate of Approval from the Committee
On Final Examination for Evolution of the Project Report
………….…………………
(Signature of the External Examiner)
………….…………………
Dr. Pranab Jyoti Barman
Head of the Department
Department of Civil Engineering
Jorhat Institute of Science and Technology, Jorhat–10
iv
ACKNOWLEDGEMENT
We are also indebted to HoD, Dr. Pranab Jyoti Barman and all the faculty
members, Civil Engineering Department, Jorhat Institute of Science and
Technology, for showing us the wonderful practical approach of learning. We
remain grateful for providing us with facilities and advices for the completion of
the project.
Finally, we would like to express our heartfelt thanks to all supporting staff
members of Civil laboratory for helping with the equipment’s and to our friends
and family members for their encouragement for successful completion of the
project.
v
ABSTRACT
This project is based on the design of frame for proposed library and
computer center at Jorhat Institute of Science and Technology campus, Jorhat . In
this project, the Site Plan, Ground Floor and First Floor Plan and Front Elevation
Plan are provided by Archineer & Associates, Architects, Engineers & Planners.
Bordoloi Nagar, Sector-1, By Lane - 8. Based on the planes provided drawing
planes and support locations are drawn by using AutoCAD®, Gravitational load
analysis and load calculation is done by another project group of Civil engineering
department of Jorhat Institute of Science and Technology under the guidance of Mr.
Debasish Das. After that Seismic load analysis is done for different load
combinations by taking reference from IS 1893(Part 1): 2016. Moment calculation
is done using Kani's method by taking reference from Basic Structural Analysis
book by CS Reddy. Design of various structural element is done using IS:456-2000.
Ductile detailing is done by taking IS 13920:1993 guidelines into consideration.
Finally detailed cost estimation of the project is prepared as per CPWD schedule of
rates 2021.
vi
CONTENTS
TITLE PAGE
NO.
DECLARATION i
CERTIFICATE FROM SUPERVISOR ii
CERTIFICATE FROM DEPARTMENT iii
CERTIFICATE OF APPROVAL iv
ACKNOWLEDGEMENT v
ABSTRACT vi
CONTENTS vii-viii
LIST OF FIGURES ix
LIST OF TABLES x
CHAPTER 1: INTRODUCTION 1
1.1 LIST OF PLANS 1-2
1.2 PROPOSED SUPPORT LOCATION 2
1.3 OBJECTIVE 3
1.4 METHODOLOGY 3
1.5 PLANNING OF THE PROJECT 4
1.6 CONCLUSION 4
CHAPTER2: SEISMIC LOAD ANALYSIS
2.1 INTRODUCTION 5
2.2 SEISMIC LOAD ANALYSIS BY STATIC ANALYSIS 5-6
METHOD
2.3 MOMENT COMPUTATION USING KANI’S MATHOD
2.3.1. FOR TRANSVERSE DIRECTION 7
2.3.1.1 DISPLACEMENT FACTOR 7
2.3.1.2 ROTATION FACTOR 8
2.3.1.3 ACTING STOREY MOMENT DUE TO 9
HORIZONTAL FORCES
2.3.1.4 MOMENT COMPUTATION 9
vii
TITLE PAGE
NO.
2.3.2 FOR LATERAL DIRECTION 10
2.3.1.1 DISPLACEMENT FACTOR 11
2.3.1.2 ROTATION FACTOR 11
2.3.1.3 ACTING STOREY MOMENT DUE TO 13
HORIZONTAL FORCES
2.3.1.4 MOMENT COMPUTATION 14
2.4 CONCLUSION 14
CHAPTER3: DESIGN OF VARIOUS STRUCTURAL ELEMENTS
3.1 INTRODUCTION 15
3.2 BEAM DESIGN 15
3.3 COLUMN DESIGN 22
3.4 FOOTING DESIGN 25
3.5 LINTEL BEAM DESIGN 32
3.6 DUCTILE DETAILING FOR FRAMES 37
3.7 CONCLUSION 38
CHAPTER 4: ESTIMATION OF COST
4.1 INTRODUCTION 39
4.2 BAR-BENDING SCHEDULE 39
4.3 DETAIL ESTIMATE FOR LIBRARY AND COMPUTER 44
CENTRE
4.4 CONCLUSION 50
CHAPTER 5: CONCLUSION 51
REFERENCES 52
viii
LIST OF FIGURES
Page
No.
Figure 1.1: Site Plan provided by Archineer & Associates 1
Figure 1.2: Ground Floor plan provided by Archineer & 1
Associates
Figure 1.3: First Floor Plan provided by Archineer & Associates 2
Figure 1.4: Front Elevation Plan provided by Archineer & 2
Associates
Figure 1.5: Support Location of Column 2
Figure 2.1: Horizontal Forces in Transverse Direction 7
Figure 2.2: Transverse Direction Moment Computation 9
Figure 2.3: Final Moment Computation for Transverse Direction 10
Figure 2.4: Horizontal Forces in Lateral Direction 10
Figure 2.5: Lateral Direction Moment Computation 14
Figure 2.6: Final Moment Computation for Lateral Direction 14
Figure 3.1: Reinforcement detailing of beam 21
Figure 3.2: Beam Cross Section Near Support 21
Figure 3.3: Beam Cross Section Near Mid Span 21
Figure 3.4: Reinforcement detailing of column 24
Figure 3.5: Stress Distribution Diagram 26
Figure 3.6: Reinforcement detailing of footing 31
Figure 3.7: Reinforcement detailing of footing 32
Figure 3.8: Reinforcement detailing of Lintel beam 37
Figure 3.9: Portal Frame reinforcement Detailing in Transverse 37
direction
Figure 4.0: Portal Frame reinforcement Detailing in Lateral 38
direction
ix
LIST OF TABLES
Page
No.
Table 1.1: Planning of Project Report 4
Table 2.1: Design Steps for Seismic force 5
Table 2.2: Horizontal Load Distribution with Height 6
Table 2.3: Displacement Factor Calculation 7
Table 2.4: Rotation Factor Calculation 8
Table 2.5: Storey Moment Calculation 9
Table 2.6: Displacement Factor Calculation 11
Table 2.7: Rotation Factor Calculation 11
Table 2.8: Storey Moment Calculation 13
Table 4.1: Bar-Bending Schedule for Library and Computer 39
centre
Table 4.2: Detailed estimation of cost of library and Computer 44
centre
x
CHAPTER 1
INTRODUCTION
A design for JIST Library and Computer centre is required. A Library
building is one amongst the necessary factors required for the event of the libraries.
The project aims to design a Library and Computer centre.
1
Figure 1.3 - First Floor Plan provided by Archineer & Associates
2
1.3 OBJECTIVE
1.4 METHODOLOGY
3
1.5 PLANNING OF THE PROJECT REPORT
1.6 CONCLUSION
In this chapter, an introduction of the project has been provided. The project
deals with the design of a Library and Computer centre. Planning of the project has
also been provided. The required structural elements of Library and Computer
centre are designed as per IS code in the following chapters.
4
CHAPTER 2
SEISMIC LOAD ANANYSIS
2.1 INTRODUCTION
1. DL+EQ
2. 1.5 (DL-EQ)
3. 1.5 (DL+EQ)
4. 1.2 (DL+LL-EQ)
5. 1.2 (DL+LL+EQ)
Table 2.1: Design Steps for Seismic Force by Static Analysis Method
For load combination of 1.2 (DL+LL+EQ)
Floor length in X-direction= 32m
Floor length in Y-direction= 17m
The floor area = 544sq.m
Live load= 8kN/sq.m
Earthquake load= 4kN/sq.m
Thickness or depth of the slab= 0.165m
Dead load of the slab= 4.125kN/sq.m
The total seismic weight on the floors and roofs
1st floor W1= 1162.128kN
Ground floor W2= 1426.4752kN
5
Above tie beam W3= 264.3472
Earthquake load and live load = 2611kN/sq.m
Total seismic weight in structure W= 6556.9805kN
Height of the building h= 9.7m
EL in X-Direction:
T=(0.09h)/√d 0.15sec
From Fig. 2 of IS: 1893, for T=0.15 sec,
Sa/g= 2.5
Ah={(Z/2)(Sa/g)}/(R/I)
Seismic zone factor Z (from table 3) 0.36
Importance factor I 1.5
Response reduction factor R 5
Ah= 0.1
Design base shear
VB=AhW 885.19236kN
EL in Y-Direction:
T=(0.09h)/√d 0.21sec
From Fig. 2 of IS: 1893, for T=0.21 sec,
Sa/g= 2.5
Ah={(Z/2)(Sa/g)}/(R/I)
Seismic zone factor Z (from table 3) 0.36
Importance factor I 1.5
Response reduction factor R 5
Ah= 0.1
Therefore, for this building the design seismic force in Y-direction is same as that
in the X-direction. Ah values are same.
Table 2.2: Horizontal Load Distribution with Height by the Static Method
Horizontal Load Distribution with Height by the Static Method
Horizontal Force
Storey 2
Wi (kN) hi(m) (Wihi )/1000 (Wihi )/∑Wihi2
2
at ith Level for EL
Level
in direction(kN)
1st
floor 1162.13kN 9.7 109.34 0.645385764 571.29kN
ground
floor 1426.48kN 6.4 58.43 0.344862618 305.27kN
above
tie
beam 264.34kN 2.5 1.65 0.009751618 8.63kN
6
2.3 MOMENT COMPUTATION USING KANI’S METHOD
7
2.3.1.2 Rotation Factor
8
2.3.1.3 Acting Storey Moment due to Horizontal Forces
Table 2.5: Storey Moment Calculation
TOTAL STOREY
LENGTH LOAD
FLOOR LOAD MOMENT
(m) (kN)
(kN) (kNm)
1st FLOOR 3.3 -571.29 -571.29 -628.42
Ground floor 3.9 -305.27 -876.56 -1139.53
In tie beam 2.5 -8.63 -885.19 -737.66
9
Figure 2.3 – Final Moment Computation for Transverse Dirrection
10
2.3.2.1 Displacement Factor
Table 2.6: Displacement Factor Calculation
Displacement
storey member k ∑k DF
factor
1 2 0.400I 0.125 -0.1875
26 3 0.400I 0.125 -0.1875
27 4 0.400I 0.125 -0.1875
BELOW 28 5 0.400I 0.125 -0.1875
TIE 3.200I
BEAM 29 6 0.400I 0.125 -0.1875
30 7 0.400I 0.125 -0.1875
31 8 0.400I 0.125 -0.1875
32 9 0.400I 0.125 -0.1875
2 17 0.256I 0.125 -0.1875
3 16 0.256I 0.125 -0.1875
4 15 0.256I 0.125 -0.1875
GROUND 5 14 0.256I 0.125 -0.1875
2.051I
FLOOR 6 13 0.256I 0.125 -0.1875
7 12 0.256I 0.125 -0.1875
8 11 0.256I 0.125 -0.1875
9 10 0.256I 0.125 -0.1875
17 18 0.303I 0.125 -0.1875
16 19 0.303I 0.125 -0.1875
15 20 0.303I 0.125 -0.1875
1st 14 21 0.303I 0.125 -0.1875
2.424I
FLOOR 13 22 0.303I 0.125 -0.1875
12 23 0.303I 0.125 -0.1875
11 24 0.303I 0.125 -0.1875
10 25 0.303I 0.125 -0.1875
11
3 16 0.256I 0.220 -0.110
4 27 0.400I 0.348 -0.174
4 3 0.190I 0.166 -0.083
4 1.150I
4 5 0.303I 0.264 -0.132
4 15 0.256I 0.223 -0.111
5 28 0.400I 0.336 -0.168
5 4 0.303I 0.255 -0.127
5 1.189I
5 6 0.230I 0.193 -0.097
5 14 0.256I 0.216 -0.108
6 29 0.400I 0.370 -0.185
6 5 0.230I 0.212 -0.106
6 1.082I
6 7 0.196I 0.181 -0.091
6 13 0.256I 0.237 -0.118
7 30 0.400I 0.402 -0.201
7 6 0.196I 0.197 -0.099
7 0.994I
7 8 0.142I 0.143 -0.071
7 12 0.256I 0.258 -0.129
8 31 0.400I 0.377 -0.188
8 7 0.142I 0.134 -0.067
8 1.061I
8 9 0.263I 0.248 -0.124
8 11 0.256I 0.242 -0.121
9 32 0.400I 0.435 -0.217
9 9 8 0.263I 0.920I 0.286 -0.143
9 10 0.256I 0.279 -0.139
10 9 0.256I 0.312 -0.156
10 10 11 0.263I 0.823I 0.320 -0.160
10 25 0.303I 0.368 -0.184
11 8 0.256I 0.266 -0.133
11 12 0.142I 0.147 -0.074
11 0.964I
11 10 0.263I 0.273 -0.136
11 24 0.303I 0.314 -0.157
12 7 0.256I 0.286 -0.143
12 11 0.142I 0.158 -0.079
12 0.897I
12 13 0.196I 0.219 -0.109
12 23 0.303I 0.338 -0.169
13 6 0.256I 0.260 -0.130
13 14 0.230I 0.233 -0.117
13 0.985I
13 12 0.196I 0.199 -0.099
13 22 0.303I 0.308 -0.154
14 5 0.256I 0.235 -0.117
14 15 0.303I 0.277 -0.139
14 1.092I
14 13 0.230I 0.210 -0.105
14 21 0.303I 0.277 -0.139
15 4 0.256I 0.244 -0.122
15 15 16 0.190I 1.053I 0.181 -0.090
15 14 0.303I 0.288 -0.144
12
15 20 0.303I 0.288 -0.144
16 3 0.256I 0.240 -0.120
16 17 0.317I 0.297 -0.149
16 1.067I
16 15 0.190I 0.178 -0.089
16 19 0.303I 0.284 -0.142
17 2 0.256I 0.292 -0.146
17 17 16 0.317I 0.877I 0.362 -0.181
17 18 0.303I 0.346 -0.173
18 17 0.303I 0.488 -0.244
18 0.620I
18 19 0.317I 0.512 -0.256
19 18 0.317I 0.391 -0.196
19 19 16 0.303I 0.811I 0.374 -0.187
19 20 0.190I 0.235 -0.117
20 15 0.303I 0.380 -0.190
20 20 19 0.190I 0.797I 0.239 -0.120
20 21 0.303I 0.380 -0.190
21 14 0.303I 0.363 -0.181
21 21 20 0.303I 0.836I 0.363 -0.181
21 22 0.230I 0.275 -0.138
22 13 0.303I 0.416 -0.208
22 22 21 0.230I 0.729I 0.315 -0.158
22 23 0.196I 0.269 -0.134
23 12 0.303I 0.473 -0.236
23 23 22 0.196I 0.641I 0.306 -0.153
23 24 0.142I 0.221 -0.111
24 11 0.303I 0.428 -0.214
24 24 23 0.142I 0.708I 0.200 -0.100
24 25 0.263I 0.372 -0.186
25 24 0.263I 0.465 -0.232
25 0.566I
25 10 0.303I 0.535 -0.268
13
2.3.1.4 Moment Computation
2.4 Conclusion:
In this chapter, seismic load analysis by using Static Analysis Method as per
IS 1893(Part 1): 2016 is done. After Seismic load analysis by using Kani’s Method
final moment calculations are done.
14
CHAPTER 3
DESIGN OF VARIOUS STRUCTURAL ELEMENTS
3.1 INTRODUCTION
This chapter deals with the design of various structural elements of Library and
Computer centre. The various structural elements are beams, column and footing
etc.
M = 551.191 kNm
M = 585.600 kNm
−551.191 + 585.600
M = = 17.204 kNm
2
wl 25.75 × 2.65
M = = = 22.603 kNm
8 8
= 44.327 kNm
Shear force,
15
w L
V = + 𝑠ℎ𝑒𝑎𝑟 𝑓𝑜𝑟𝑐𝑒 𝑑𝑢𝑒 𝑡𝑜 𝑢𝑛𝑏𝑎𝑙𝑎𝑛𝑐𝑒𝑑 𝑚𝑜𝑚𝑒𝑛𝑡
2
= 275.506 kN
x 0 ⋅ 42x
M = 0.36f 1− bd
d d
∴𝐶=𝑇
𝑥
=> 0.87𝑓 𝐴 = 0.36𝑓 𝑏(𝑑 − 𝑑′)
𝑑
=> 𝐴 = 2105.85𝑚𝑚
∴M = 0.87𝑓 𝐴 × (𝑑 − 𝑑′)
=> 𝐴 = 447.845𝑚𝑚
16
Total reinforcement in tension zone,
𝐴 =𝐴 +𝐴
=> 𝐴 = 2553.695 𝑚𝑚
2553.695
Number of bars =
× 20
= 8.13~ 9nos.
𝜋
∴𝐴 = 9× × 20
4
=> 𝐴 = 2826 𝑚𝑚
0.0035 𝜖
=
0.0035 𝜖
=> =
0.48 0.48 −
𝑓 = 0.85𝑓
=> 𝑓 𝐴 = 0.87𝑓 . 𝐴
17
=> 0.85𝑓 𝐴 = 0.87𝑓 . 𝐴
0.87 × 447.845
=> 𝐴 =
0.85
=> 𝐴 = 458.382 𝑚𝑚
458.382
Number of bars =
× 20
= 1.45~ 2nos
τ = 2.8 N/ mm
V
τ =
bd
275.506 × 1000
=> 𝜏 =
500 × 600
= 0.918 N/ mm
Percentage of steel,
A × 100
p=
bd
2826 × 100
=
500 × 600
= 0.942%
18
From IS 456:2000, table 19
∴ 𝑉 = 𝑉 − 𝜏 𝑏𝑑
=> 𝑉 = 95.206 𝑘𝑁
π
A =2× ×ϕ
4
=2× ×8
= 100.53 mm
0.87𝑓 𝐴 𝑑
V =
s
=> s = 114.83mm
ii) 300 mm
19
Therefore 2 legged stirrups 8 mm diameter at 100 mm spacing centre to centre.
L L
= ×K ×K ×K
d d
A required
f = 0.58 × f ×
A provided
2553.695
= 0.58 × 415 ×
2826.00
= 217.506 N/mm
K = 1.2
K =1
K =1
Therefore,
L
= 26 × 1.2 × 1 × 1
d
= 31.2
L 2.65
=
d 0.60
20
Reinforcement Detailing
Figure 3.2- Beam cross-section near Figure 3.3- Beam cross-section near
support mid span
21
3.3 COLUMN DESIGN
For column AB
wl
Load on column, P =
2
=> P = 158.115 kN
=> P = 234.564kN
=> P = 424.306 kN
M = 589.331𝑘𝑁𝑚
d′ 65
= = 0.1
D 650
P 424.306 × 10
= = 0.065
f bD 20 × 500 × 650
M 589.331 × 10
= = 0.139
f bD 20 × 500 × 650
22
p
Therefore, = 0.8
f
=> p = 0.8 × 20
=> p = 1.6%
×
Percentage of reinforcement, p = ×
=> A = 5270 mm
A = 0.8% of bD
=> A = 2600 mm
∴A =A
5270
no. of reinforcement = = 16.77~17nos.
× 20
ii. 6 mm
23
b. The pitch of lateral tie should not be less than
i. Least lateral dimension of column = 500 mm
ii. 16 × Diameter of main reinforcement = 16 × 20 = 320 mm
iii. 300 mm
Reinforcement detailing
24
3.4 FOOTING DESIGN
due to moment,
= 712.688kN
1
Acting moment, M = × 484.204
1.2
= 403.503kNm
𝐿 650
=
𝐵 500
1
=> 𝐵 = 𝐿
1.3
P
Assuming, +f=q
LB
My M 6M
Where f is the bending stress, f = = =
I Z BL
P 6M
∴ + =q
LB BL
25
1.3P 6 × 1.3M
=> + =q
L L
=> L = 3.609 m
Assuming L=3.7 m
1.3P 6 × 1.3M
Maximum stress, p = + Figure 3.5- Stress Distribution Diagram
L L
1.3P 6 × 1.3M
And Minimum stress, p = +
L L
For L=3.7 m both conditions (p < safe bearing capacity (q) and
p > 0) are satisfied. Hence assumption is correct.
𝐿 3.7
∴𝐵= = = 2.84~2.85
1.3 1.3
Diameter of reinforcement = 12 mm
Clear cover = 50 mm
26
Check for one way shear
1
V= × (110.158 + 141.226) × 0.6 × 3.7
2
=> V = 279.036 kN
V
τ =
bd
334.843 × 1000
=> τ =
2850 × 600
27
Shear force(V) = P − {p × (area of the critical section − column area)}
∴ V = 723.812kN
V
τ =
bd
τ = 0.25 f
= 0.25√20
= 1.118 N/mm
=> k = 0.5 + 1
=> k = 1.5
∴ τ = τ ×k
28
=> p = 90.006 kN/m
= 202.247 kNm
= 634.682 kNm
Therefore,
Moment at the face of column= Moment from triangle 1 +Moment from triangle 2
x x
M = 0.36 1 − 0.42 bd f
d d
1004.315 × 10
=> d =
0.36 × 0.48(1 − 0.42 × 0.48)2850 × 20
A f
M = 0.87f . A . d 1 −
bdf
415A
=> 1004.315 × 10 = 0.87 × 415 × 600A 1−
2850 × 600 × 20
29
=> 1004.315 × 10 = 216630A − 2.628A
=> A = 4931.061 mm
= 2664 mm
Area of the reinforcement should not be less than minimum reinforcement required
value.
∴ Providing A = 4931.061 mm
×
× 2850
Spacing of reinforcement bar = = 65.33 mm~65 mm
4931.061
×
× 3700
Spacing of reinforcement bar = = 84.81 mm~80 mm
4931.061
Development length
0.87f ϕ
L =
4τ
0.87 × 415 × 12
=> L = = 564.14 mm
4 × 1.2 × 1.6
30
Reinforcement detailing
31
Figure 3.7- Reinforcement Detailing of Footing
Effective span,
=> l = 2020 mm
=> l = 2100 mm
32
LOAD CALCULATION
=> p = 7.64 kN
Self weight,
=> p = 3.33kN
Total load,
p=p +p
pl 10.97 × 2.02
M= = = 2.77 kNm
8 8
Shear force,
𝑝 10.97
v = = = 5.485 𝑘𝑁
2 2
𝑀 = 0.36f 1 − 0.42 bd
2.77 × 10
=> d =
0.36 × 20 × 0.48 × (1 − 0.42 × 0.48) × 300
=> 𝐷 = 180 + 35
33
=> D = 215mm ~ 220mm
A f
M = 0.87f A d 1 −
bdf
A × 415
=> 2.77 × 10 = 0.87 × 415 × A × 180 × 1 −
300 × 180 × 20
A 0.85
=
bd f
=> A = 110.602 mm
A = 0.04bD
= 2640 mm
110.602
Number of reinforcement = = 1.106
× 10
A = 2 × × 10
34
= 157 mm
τ = 2.8 N/mm
A 157
Percentage of steel = × 100 = × 100 = 0.29%
bd 300 × 180
v 5.485 × 1000
τ = = = 0.101N/mm > τ
bd 300 × 180
π
A =2× ×ϕ
4
=2× ×8
= 100.53 mm
Spacing of stirrups,
𝐴 0.4
=
𝑏𝑠 0.87𝑓
100.53 0.4
=> =
300 × 𝑠 0.87 × 250
35
From IS: 456-2000, clause 26.5.1.5
i) = 0.75 × 180
= 135 mm
ii) 300 mm
L L
= ×K ×K ×K
d d
A required
f = 0.58 × f ×
A provided
110.602
= 0.58 × 415 ×
157
= 169.566N/mm
K = 1.9
K =1
K =1
Therefore,
L
= 26 × 1.9 × 1 × 1
d
= 49.4
36
L 1.8
=
d 0.18
= 10 < 33.8
37
Figure 4- Portal Frame Reinforcement Detailing in Lateral Direction
3.7 CONCLUSION
In this chapter, the designing of frame of proposed library and computer centre
and reinforcement detailing as per IS code has been done.
38
CHAPTER 4
ESTIMATION OF COST
4.1 INTRODUCTION
This chapter deals with cost estimation of Library and Computer centre. Cost
estimation is the technique of calculating the various quantities and the expected
expenditure to be incurred on a particular work of project. The rates of different
item of work are determined by a list of rates called as schedule of rates (SOR). The
rates are finalised by government bodies such as Central Public Works Department
(CPWD), State Governments, etc. The cost estimation has been prepared on the
basis of CPWD Schedule of Rates for the year 2021.
The bar bending schedule is a tabular breakdown of reinforcing bars that includes
details such as bars types, total length, weight and drawing of the desired bending
shape of bar.
(Note: Slab and Stair design details are taken from Group no. 14 for BBS
preparation and estimation.)
Shape of
bending Total Cross Total
SL Diameter Length
(all Nos. length in sectional weight in
No. in m in m
dimensions m area in m2 Kg
are in m)
0.440
0.20
39
0.55
0.40
3 4224 0.008 1.374 5803.4381 0.000050 2288.783
0.21
0.120
5 0
1332 0.008 0.48 639.36 0.000050 252.153
17660.805
Considering 5% wastage 18543.845
1.475
10.210
1.125
0.90
10.210
1.475
40
0.900
10.210
9 216 0.02 12.155 2625.48 0.000314 6471.546
1.125
10 2.750
512 0.012 2.75 1408 0.00011304 1249.409
3.60
11 512 0.012 3.6 1843.2 0.00011304 1635.589
0.875
16.820
0.875
15 2.450
252 0.02 2.45 617.4 0.000314 1521.829
32
41
19 1.725 22 0.01 1.725 37.95 0.0000785 23.386
26 1.02
3.06
57 0.01 5.1084 291.1788 0.0000785 179.432
27 1.41
48 0.01 7.0584 338.8032 0.0000785 208.779
4.23
42
28 57 0.01 3.8084 217.0788 0.0000785 133.769
0.76
2.28
30 0.53
102 0.01 2.6584 271.1568 0.0000785 167.094
1.590
35 32
42 0.01 32 1344 0.0000785 828.206
17
36 88 0.01 17 1496 0.0000785 921.873
71059.984
Considering 5% wastage 74612.983
43
4.3 DETAILED ESTIMATE FOR LIBRARY AND COMPUTER CENTRE
(Prepared on the basis of CPWD Schedule of Rates for the year 2021)
44
3 5.1 CONCRERTING
Providing and laying
in position specified
grade of reinforced
cement concrete,
excluding the cost of
centering, shuttering,
finishing and
reinforcement - All
work up to plinth level :
5.1.2 1:1.5:3 (1 cement : 1.5
coarse sand (zone-III)
derived from natural
sources : 3 graded stone
aggregate 20 mm
nominal size de rived
from natural sources)
Below ground level
32 × 2.85 × 3.7 ×
0.66 = 222.710
32 × 0.5 × 0.65 × 2.5
= 26.00
For columns
32 × 0.50 × 0.65 × 7.20
= 74.880
For beams
In transverse direction-
12 × 2.175 × 0.5 × 0.65
= 8.463
12 × 4.60 × 0.5 × 0.65 =
17.940
12 × 2.65 × 0.5 × 0.65 =
10.335
12 × 3.70 × 0.5 × 0.65 =
14.430
12 × 4.45 × 0.5 × 0.65 =
17.355
12 × 6.40 × 0.5 × 0.65 =
24.960
12 × 2.825 × 0.5 × 0.65
= 11.017
In lateral direction-
24 × 3.75 × 0.5 × 0.65 =
29.250
45
24 × 2.15 × 0.5 × 0.65 =
16.77
24 × 9.10 × 0.5 × 0.65 =
70.98
For slab
2 × 17 × 32 × 0.165 =
179.520
Total = 724.610m³ ₹
724.61 m³ 8364 60,60,638.04
4 5.22 & REINFORCEMENT
5.22A Steel reinforcement for
R.C.C. work including
straightening, cutting,
bending, placing in
position and binding all
complete up to plinth
level and above plinth
level.
(Taking values from
BBS table)
5.22.1 & Mild steel and Medium ₹
5.22.A1 Tensile steel bars 18543.8 kg 88.95 16,49,475.04
5.22.4 & Hot rolled deformed ₹
5.22.A4 bars 74613 kg 89.65 66,89,053.91
5 5.9 CENTERING &
SHUTTERING
Centering and
shuttering including
strutting, propping etc.
and removal of form for
5.9.1 Foundations, footings,
bases of columns, etc.
for mass concrete
32 × 2.85 × 3.70 =
337.440 337.44 sqm 308 ₹ 1,03,931.52
5.9.6 Columns, Pillars,
Piers, Abutments, Posts
and Struts
32 × 9.70 × 2.3 =
713.920 713.92 sqm 804.3 ₹ 5,74,205.86
5.9.5 Lintels, beams, plinth
beams, girders,
bressummers and
cantilevers
In transverse direction-
46
12 × 2.175 × 2.3 =
60.03
12 × 4.60 × 2.3 =
126.96
12 × 2.65 × 2.3 = 73.14
12 × 3.70 × 2.3 =
102.12
12 × 4.45 × 2.3 =
122.82
12 × 6.40 × 2.3 =
176.64
12 × 2.825 × 2.3 =
77.97
In lateral direction-
24 × 3.75 × 2.3 =
103.50
24 × 2.15 × 2.3 = 59.34
24 × 9.10 × 2.3 =
251.16
Total = 1153.68m² 1153.68 sqm 608.4 ₹ 7,01,898.91
5.9.3 Suspended floors,
roofs, landings,
balconies and access
platform
For slab
2 × 17 × 32 = 1088 1088 sqm 766.6 ₹ 8,34,060.80
5.9.7 Stairs, (excluding
landings) except spiral-
staircases
23.72 sqm 657.8 ₹ 15,603.02
6 6.1 BRICK WORK
Brick work with
common burnt clay
F.P.S. (non modular)
bricks of class
designation 7.5 in
foundation and plinth
in:
6.1.1 Cement mortar 1:4 (1
cement : 4 coarse sand)
227.2 × 0.3 × 0.6=
40.896 40.896 m³ 6882 ₹ 2,81,446.27
47
6.4 Brick work with
common burnt clay
F.P.S. (non modular)
bricks of class
designation 7.5 in
superstructure above
plinth level up to floor
V level in all shapes
and sizes in :
6.4.1 Cement mortar 1:4 (1
cement : 4 coarse sand)
(volume is directly
calculated from ₹
AutoCAD® drawing) 146.303 m³ 8512.1 12,45,345.77
7 13.12 PLASTERING WORK
18 mm cement plaster
in two coats under layer
12 mm thick cement
plaster 1:5 (1 cement : 5
coarse sand) and a top
layer 6 mm thick
cement plaster 1:3 (1
cement : 3 coarse sand)
finished rough with
sponge. 1950.71 sqm 461.85 ₹ 9,00,933.87
8 9.1 DOORS &
WINDOWS
Providing wood work
in frames of doors,
windows, clerestory
windows and other
frames, wrought
framed and fixed in
position with hold fast
lugs or with dash
fasteners of required
dia & length (hold fast
lugs or dash fastener
shall be paid for
separately).
Second class teak
wood(volume is
directly calculated from
AutoCAD® drawing) 1.0044 m³ 131577 ₹ 1,32,155.89
48
9.7 Providing and fixing
panelling or panelling
and glazing in panelled
or panelled and glazed
shutters for doors,
windows and clerestory
windows. Panelling for
panelled or panelled
and glazed shutters 25
mm to 40 mm thick :
9.7.1 Second class teak wood 135.36 sqm 2998.3 ₹ 4,05,849.89
9.17 Providing and fixing
stainless steel fancy
handle of approved
make fixed with SS
screws etc. complete as
per direction of
Engineer-in-charge
9.17.1 200 mm 89 each 153.15 ₹ 13,630.35
9 11.1 FLOORING
Brick on edge flooring
with bricks of class
designation 7.5 on a
bed of 12 mm cement
mortar, including
filling the joints with
same mortar, with
common burnt clay non
modular bricks:
11.1.1 1:4 (1 cement : 4 coarse
sand) 509.668 sqm 937 ₹ 4,77,558.45
11.16 Light shade pigment ₹
using white cement 1047.73 sqm 1309.9 13,72,421.53
10 12.24 CEILING
Providing and fixing
insulating board ceiling
of approved quality
with necessary nails
etc. complete (frame
work to be paid
separately) :
12.24.3 Flame retardant face
insulating board
12.24.3.1 12 mm thick 1047.73 sqm 936 ₹ 9,80,675.28
11 13.39 COLOUR WASHING
49
Colour washing such as
green, blue or buff to
give an even shade :
13.39.1 New work (two or
more coats) with a base
coat of white washing
with lime (for interior) 1496.5 sqm 44.25 ₹ 66,220.13
13.45 Finishing walls with
textured exterior paint
of required shade 551.07 sqm 245 ₹ 1,35,012.15
₹ 2,32,43,999
4.4 CONCLUSION
In this chapter, the cost estimation Library and Computer centre has been prepared
on the basis of Delhi Schedule of rates, CPWD.
50
CHAPTER 5
CONCLUSION
In this project, “Design of frame for proposed Library and Computer
centre at JIST campus, Jorhat “is carried out. The proposed Library and
Computer centre drawing plan has been provided by Archineer & Associates,
Architects, Engineers & Planners For designing various structural elements IS 456:
2000 has been followed. For Seismic analysis “Criteria for Earthquake Resistant
Design of Structures” of “IS 1893(Part I): 2016” has been followed. For moment
distribution portal frame method has been adopted and all structural elements
drawings has been prepared by following IS 13920:1993(Ductile Detailing of
Reinforced Concrete Structures subjected to Seismic Forces- code of practice). Bar-
bending schedule has been prepared for determining weight of reinforcements. A
detailed estimate has been prepared.
51
REFERENCES
52