SAIC-Q-1039 Rev 7 (Final) Sub-grades, Elevation and Surface Preparation Inspection
SAIC-Q-1039 Rev 7 (Final) Sub-grades, Elevation and Surface Preparation Inspection
SAIC-Q-1039 Rev 7 (Final) Sub-grades, Elevation and Surface Preparation Inspection
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SATIP-Q-006-02
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Residential Streets 15 CM 8 CM 5 CM
Access Roadways 15 CM 9 CM 6 CM
Pavements including a Foamed Asphalt Stabilized Base Course shall
comply with the following layer thicknesses:
The sub-grade shall be restored by removing all vegetation, filling all SAES-Q-006
A4
depressions and leveling the surface. Sec. 5.1
Soft and unstable material that will not compact when rolled or tamped
SAES-Q-006
A5 shall be removed and replaced with material approved by the Saudi
Sec. 5.1
Aramco representative.
The entire sub-grade shall be compacted to not less than 95% of the
maximum dry density per (ASTM D1557 or AASHTO T180) while within SAES-Q-006
A6
1.5% of the optimum moisture content (for cohesive soils) or to 85% of Sec. 5.1
relative density (ASTM D4253 and ASTM D4254) (for cohesionless soils).
SAES-Q-006
A7 All holes, ruts, soft places and other defects shall be corrected.
Sec. 5.1
Page 1 of 3
The subgrade shall be constructed so that after being compacted it will
conform to the alignment, grade, and cross-section shown on the plans, SAES-Q-006
A10
which shall not vary by more than +6 mm as measured with a 3 m straight Sec. 5.1
edge, and as required by the Project construction specification.
Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MAR 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Sub-grades, Elevation and Surface Preparation Inspection SAIC-Q-1039 30-Apr-13 CIVIL -
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The sub-grade shall be kept drained during the placing and compaction of SAES-Q-006
A13
the base course or sub-base surface. Sec. 5.1
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 26 November 2012