SAIC-Q-1036 Rev 7 Raw Material Sampling, Testing & Asphalt Mix Design
SAIC-Q-1036 Rev 7 Raw Material Sampling, Testing & Asphalt Mix Design
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
Page 1 of 4
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Raw Materials Sampling, Testing & Asphalt Mix Design
SAIC-Q-1036 30-Apr-13 CIVIL -
Review
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Gradation when tested according to ASTM C117 and ASTM C136 for
combined mineral aggregates shall conform to the following:
Percent Passing
Asphalt Base
Sieve Size Asphalt Wearing Course Classes
Course Classes
A B A B C
1-½ inch 100 100 - - -
1 inch 75-90 100 - - -
SAES-Q-006
B2
¾ inch 65-80 80-100 100 100 - Sec. 5.5.1.B.1
½ inch 55-70 68-88 76-92 80-100 100
3/8 inch 45-60 60-80 64-79 - 80-100
No. 4 31-46 45-65 41-56 50-70 55-75
No. 10 18-33 30-50 23-37 32-47 32-47
No. 40 5-18 15-32 7-20 16-26 16-26
No. 80 3-13 - 5-13 10-18 10-18
Page 2 of 4
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Raw Materials Sampling, Testing & Asphalt Mix Design
SAIC-Q-1036 30-Apr-13 CIVIL -
Review
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAES-Q-006
D1 Sulfur shall be pelletized elemental sulfur.
Sec. 5.5.1.C
Hydrated lime, Portland cement or fly ash shall not be used as a mineral SAES Q-006
D3
admixture. (SABP Q-010, Sec. 5.2.3) Sec. 3.1
For sulfur extended hot asphalt mix, thirty percent (30%) by weight of
the bitumen (asphalt binder) shall be replaced with pelletized elemental
SAES-Q-006
E2 sulfur. (Exception: Sulfur extended asphalt is not required for
Sec. 5.5.2
maintenance work within plant areas and maintenance work that
includes handwork.)
Mineral Filler: When the combined grading of the coarse and fine
aggregates is deficient in material passing the No. 200 sieve, Mineral
Filler conforming to AASHTO M17 shall be added as approved by the
Company Representative. Mineral Filler shall conform to the following
grading: SAES-Q-006
C5
Sec. 5.5.1.B.2
Sieve Size Percent Passing (By Wt)
Page 3 of 4
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Raw Materials Sampling, Testing & Asphalt Mix Design
SAIC-Q-1036 30-Apr-13 CIVIL -
Review
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM SAES-Q-006
C5 ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No. Sec. 5.5.1.B.2
No. 30 100
No. 50 95 - 100
No. 200 70 - 100
Final asphalt mix when compared to the Job Mix Formula shall be within
the following limits:
Tolerance
Materials Sieve Size
Base Course Wearing Course
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 23 February 2011
2- Schedule "Q" -- Project Quality Requirements
Page 4 of 4