Rig Operation
TESTING ACTIVITY
Last 24 hrs
End Of Cleanup Operation (72/64 Fixed)
Final BU Period
IN flow test Well Head and SSSV.
Start Rig Down
Rigged Down Coflexip Hose and 4-1/16 Spool Riser
Next 24 hrs
Continue Rig Down
Consumed Item
Item Description Date of Use QTY
1 Ring Gasket RX46 1/10/2024 1
2 Ring Gasket BX155 1/10/2024 4
3 Ring Gasket BX155 1/11/2024 6