Sawang-2024-LMC( SUSTAL, JUSTIN B.)
Sawang-2024-LMC( SUSTAL, JUSTIN B.)
Uson, Masbate
UNIT COST ANALYSIS ( LMC )
Embankment Conctruction & Compaction (per cu.m.) - - - - - - - - - - - P 347.64
SUMMARY
Mark-up Total
(25%) Unit Cost
Materials - -P 100.00 25.00 125.00
Labor - -- 33.16 8.29 41.45
Rental - - - 60.67 15.17 75.84
Fuel Cost - - 84.28 21.07 105.35
UNIT COST - 278.11 69.53 347.64
Field Support & Supervision - - - -P 6.95
354.59
sheet 2 of 2
Sawang CIP
Uson, Masbate
SUMMARY
Mark-up Total
(19.5%) Unit Cost
Labor - -- - - - - - - - - - - - - - - - - 66.42 12.95 79.37
Rental - - - - - - - - - - - - - - - - - - 123.40 24.06 147.46
Fuel & Oil - - - - - - - - - - - - - - - 62.40 12.17 74.57
UNIT COST - - - - - P 252.22 49.18 301.40
Field Support & Supervision - - - -P 6.03
307.43
Sawang CIP
Uson, Masbate
2. Labor Cost
2.a Direct Labor Cost
2.a1. Fabrication. Placing & Dismantling Cost
Crew: 2-Carpenter; & 4 - Laborers
Capability : 6.00 cu.m./day
2.a2. Concreting & Curing Works
Crew : 1 - Foreman; 2 - Mason; 1 - L.E. Operator; 8 - Laborers
Capability : 6.00 cu.m./day
RATE L A BO R
POSITION PER Fab., Placing & Dismt'ng Concreting & Curing
DAY No. Cost No. Cost
Foreman - 1 -
Mason 700.00 2 1,400.00
Carpenter 1,042.00 2 2,084.00
L.E. Operator 2,240.00 1 2,240.00
Laborer 572.00 4 2,288.00 8 4,576.00
TOTAL UNIT COST 4,372.00 8,216.00
UNIT COST 728.67 1,369.33
SUMMARY
Mark-up Total
(19.5%) Unit Cost
Materials - - - - - - - - - - - - - - - - P 6,242.50 1,217.29 7,459.79
Labor - -- - - - - - - - - - - - - - - - - 4,883.35 952.25 5,835.60
Rental - - - - - - - - - - - - - - - - - - 2,889.42 563.44 3,452.86
Fuel & Oil - - - - - - - - - - - - - - - 715.03 139.43 854.46
UNIT COST - - - - - P 14,730.30 2,872.41 17,602.71
Field Support & Supervision - - - -P 352.05
17,954.76
DATA SHEET ( LMC Works )
Program No. : 1
NAME OF PROJECT : Sawang CIP Date : ###
LOCATION : Uson, Masbate FUND SOURCE :
NEW REHAB WATER SOURCE : Sawang River
AREA (Has.), Design :
Programmed Area :
RENTAL:
Dump Truck (4.5cu.m.) : P 1,500.00 /hr.
Cargo Truck(6-7 tons -4x2 DED) : 1,230.00 /hr.
Backhoe/loader(0.5-0.8/0.15-0.25cu.m.) : 1,500.00 /hr.
Concrete Mixer(0.16cum-1bagger) : 2,000.00 /hr.
Water Pump(centrifugal pump-100mm dia.) : 105.00 /hr.
Welding Machine : 500.00 /hr.
Tractor Crawler w/ dozer (55-84 HP swampy) : 2,830.00 /hr.
Truck-Tractor w / trailer( 4 hrs minimum) : 1,200.00 /hr
Cost of Materials
CEMENT : P 240.00 /bag LABOR COST: :
RSB : 60.00 /kg. FOREMAN : ### /day
C.W.NAILS : 750.00 /kg. CARPENTER : ### /day
#16 TIE WIRE : 800.00 /kg. MASON : ### /day
SAND : 650.00 /cu.m. HEO : ### /day
GRAVEL : 780.00 /cu.m. LEO : ### /day
BOULDER : 800.00 /cu.m. STEELMAN : ### /day
PLYWOOD 1/2 INCH THICK : 750.00 /pc. DRIVER : ### /day
Coconut Lumber : 60.00 /bd.ft. LABORER : ### /day
G.I. SHEET : 500.00 /pc.
Hacksaw Blade : 70.00 /pc.
5cm.Æ PVC Pipe :
10cm.Æ PVC Pipe : /pc.
SIGNATORIES
Prepared by: : JUSTIN B. SUSTAL
Designation : Engineer A
:
:
:
:
Republika ng Pilipinas
PAMBANSANG PANGASIWAAN NG PATUBIG
(National Irrigation Administration)
PANLALAWIGANG TANGGAPAN NG PATUBIG
Ligao City
Tel No. (052)-4852243
Respectfully submitted herewith for approval is the revised Program of Work for Busay-
Malabog CIP, Daraga, Albay in the amount of P4,800,000.00 under the BSPP funds. Revision
was effected due to the increase in the prevailing prices of materials and labor.
This program covers the construction of one (1) Diversion Works, eight (8) units Canal
Structures, 1.562 kms. Canalization Works, Terminal Facilities, Project Facilities, Mobilization
and Construction Survey.
Attached for evaluation are the following: Items of Work to be Undertaken as Programmed,
Unit Cost Analysis, Detailed Breakdown of Estimates, Breakdown of Sub-Total "A", S-Curve
and Printed Color-coded General Layout. Other attachments such as earthwork computations and
working plans are already in the Regional Office.
GEMENIANO V. PANTON
CALCULATION OF AGENCY ESTIMATE
NATIONAL IRRIGATION ADMINISTRATION
Sawang CIP
Uson, Masbate
ITEM ESTIMATED 10.50% MARK-Ups in Percent TOTAL COST UNIT
DESCRIPTION QUANTITY UNIT TOTAL COST
NO. COST TAX OCM PROFIT MOB/DEMOB % VALUE (ADJUSTED) COST
I DIVERSION WORKS
1 211 kgs/cm2.Renf. Conc. 155.80 cu.m. 3,303,337.52 346,850.44 9.5% 10% 19.5% 644,150.82 4,294,338.78 4,294,338.78 27,563.15
2 Rubble Masonry 375.00 cu.m. 4,231,450.96 444,302.35 9.5% 10% 19.5% 825,132.94 5,500,886.25 5,500,886.25 14,669.03
3 61 cmf RCP #REF! lin.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
4 Boulder Rip-rap - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
5 Grouted Rip-rap - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
6 Gravel Blanket - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
7 Filter Darin Bed #REF! cu.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
8 Cofferdam & Dewatering - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
9 Struct. Excav. (Mech.) - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
10 Struct. Backfill - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
11 Steel Gate & Sluiceway - unit - - 9.5% 10% 19.5% - - - #DIV/0!
12 Steel Gate & Intake - unit - - 9.5% 10% 19.5% - - - #DIV/0!
SUB-TOTAL #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
II CANAL STRUCTURES
1 211 kgs/cm2.Renf. Conc. #REF! cu.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
2 61 cmf RCP #REF! lin.m #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
3 Struct. Excavation #REF! cu.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
4 Struct. Backfill #REF! cu.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
5 Concrete Demolition #REF! cu.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
SUB-TOTAL #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
III CANALIZATION
1 211 kgs/cm2.Renf. Conc. - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
2 211 kgs/cm2 Plain Conc. - cu.m. - - 9.5% 10% 19.5% - - - #DIV/0!
3 15 cm CHB - sq.m. - - 9.5% 10% 19.5% - - - #DIV/0!
4 10 cm CHB #REF! sq.m. #VALUE! #VALUE! 9.5% 10% 19.5% #VALUE! #VALUE! #VALUE! #VALUE!
5 Common Excavation 500.00 cu.m. 112,200.00 11,781.00 9.5% 10% 19.5% 21,879.00 145,860.00 145,860.00 291.72
6 Common Borrow 350.00 cu.m. 78,540.00 8,246.70 9.5% 10% 19.5% 15,315.30 102,102.00 102,102.00 291.72
SUB-TOTAL #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
I - DIVERSION WORKS
A.Diversion Weir 0+000 155.80 375.00
Total 155.80 375.00 - - - - - - - - -
Common Common
Excav. Borrow
(cu.m.) (cu.m.)
II - CANALIZATION
1. Main Canal 1+380 2+120
Prepared by:
JUSTIN B. SUSTAL
Engineer A
Sawang CIP
Uson, Masbate
Sub-Total
B. Lateral "A"
1). CHB Lined Canal
Sub-Total
C. Lateral A-1
1). CHB Lined Canal
Sub-Total
IV - CONSTRUCTION SURVEY - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P
-- 401,727.4
A. Profile & Cross-Section - 1 proj. @ P 401,727.48 /proj. = P 401,727.48
akdown of Estimates
P 9,795,225.02
P 247,962.00
P 401,727.48
P 417,796.58
BREAKDOWN OF SUB-TOTAL "A"
I - DIVERSION WORKS
1. 211 kgs/cm2 Reinf. Conc. cu.m. 155.8 11,099.38 10,252.24 5,273.19 938.34 27,563.15 1,729,283.40 1,597,298.99 821,563.00 146,193.37
2. Rubble Masonry cu.m. 375 3,859.06 6,136.36 3,614.41 1,059.20 14,669.03 1,447,147.50 2,301,135.00 ### 397,200.00
3. 61 cmf RCP lin.m. 0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4. Boulder Rip-rap cu.m. 0 1,000.00 2,492.68 #REF! #REF! #REF! - - #REF! #REF!
5. Grouted Rip-rap cu.m. 0 2,593.13 5,310.25 3,282.09 944.96 12,130.43 - - - -
6. Gravel Blanket cu.m. 0 975.00 2,354.80 #REF! #REF! #REF! - - #REF! #REF!
7. Filter Drain Bed cu.m. 0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
8. Cofferdam & Dewatering cu.m. 0 1,406.25 302.51 127.04 203.51 2,039.31 - - - -
9. Struct. Excavation (Mechanized) cu.m. 0 364.65 #REF! #REF! #REF! - - #REF! #REF!
10. Structure Backfill cu.m. 0 243.11 243.11 - - - -
11. Steel Gate @ Sluiceway unit 2 5,975.00 5,975.00 - - - -
12. Steel Gate @ Intake unit 2 7,068.43 7,068.43 - - - -
Sub-Total #REF! #REF! #REF! #REF!
BREAKDOWN OF COSTS
TOTAL
CONTRACT COSTS
- 4,294,338.77
- 5,500,886.25
- #REF!
- #REF!
- -
- #REF!
- #REF!
- -
- #REF!
- -
11,950.00 11,950.00
14,136.86 14,136.86
26,086.86 #REF!
BREAKDOWN OF SUB-TOTAL "A"
PROJECT/FUND SOURCE : Sawang CIP
Uson, Masbate
TOTAL
UNIT COSTS BREAKDOWN OF C
ITEMS OF WORKS UNIT QTY. UNIT
MATERIALS LABOR RENTAL FUEL S. PartsOFF. Suppl. IDP COSTS MATERIALS LABOR RENTAL
II - CANAL STRUCTURES
1. 211 kgs/cm Reinf. Conc. cu.m. 0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2. 76 f cm RCP lin.m. #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3. 61 f cm RCP lin.m. 0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3. Structure Excavation cu.m. 500 #REF! #REF! - #REF! -
4. Structure Backfill cu.m. 350 #REF! #REF! - #REF! -
Sub-Total #REF! #REF! #REF!
III - CANALIZATION
1. 211 kgs/cm Reinf. Conc. cu.m. 235.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2. 15cm CHB sq.m. 1,560.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3. Common Excavation cu.m. 0.00 291.72 291.72 - - -
4. Common Borrow cu.m. 0.00 291.72 291.72 - - -
Sub-Total #REF! #REF! #REF!
IV- PROJECT FACILITIES
1. Bunkhouse unit 1 #REF! #REF! #REF! #REF! #REF! -
Sub-Total #REF! #REF! -
V- CONSTRUCTION SURVEY
1. Profile & Cross-Section proj. 1 417,796.58 417,796.58 - 417,796.58 -
Sub-Total - 417,796.58 -
VII- INSTITUTIONAL DEV'T. PROGRAM
1. Institutional Works proj. 1 417,796.58 417,796.58 - - -
Sub-Total - - -
#REF! - - - #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! - - - #REF!
- - - - #REF!
- - - - #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! - - - #REF!
#REF! - - - #REF!
- - - - -
- - - - -
#REF! - - - #REF!
- - - - #REF!
- - - - #REF!
- - - - 417,796.58
- - - - 417,796.58
- - - 417,796.58 417,796.58
- - - 417,796.58 417,796.58
BY:
#REF!
#REF!
DETAILED BREAKDOWN OF COST
(SUB-TOTAL "A")
SUMMARY FOR CONSTRUCTION
Sawang CIP
Uson, Masbate
TOTAL Construction Field Support
ITEMS OF WORKS UNIT QTY. COSTS MATERIALS LABOR RENTAL Fuel & Oil CONTRACT Survey IDP & Supervision
I - DIVERSION WORKS
1. 211 kgs/cm2 Reinf. Conc. cu.m. 155.80 4,294,338.77 4,294,338.77 #REF!
2. Rubble Masonry cu.m. 375.00 5,500,886.25 5,500,886.25 #REF!
4. Boulder Rip-rap cu.m. 0.00 - - #REF!
5. Grouted Rip-rap cu.m. 0.00 - - #REF!
6. Gravel Blanket cu.m. 0.00 - -
8. Cofferdam & Dewatering cu.m. 0.00 - -
9. Struct. Excavation cu.m. 0.00 - -
10. Structure Backfill cu.m. 0.00 - -
11. Trashrack unit 0.00 - -
12. Flashboard unit 0.00 - -
13. Concrete Demoliton cu.m. - -
Sub-Total 9,795,225.02 9,795,225.02 - #REF!
(LMC) (Force Account)
Sawang CIP
Uson, Masbate
TOTAL Construction
ITEMS OF WORKS UNIT QTY. COSTS MATERIALS LABOR RENTAL Fuel & Oil CONTRACT Survey
III - CANALIZATION
1. 211 kgs/cm Reinf. Conc. cu.m. 0.00 - -
2. Cofferdam & Dewatering cu.m. 0.00 - -
2. Lean Concrete cu.m. 0.00 - -
4. Mortar Finish sq.m. 0.00 - -
3. 15 cm CHB sq.m. 0.00 - -
5. Common Excavation cu.m. 500.00 145,860.00 145,860.00
6. Common Borrow cu.m. 350.00 102,102.00 102,102.00
Sub-Total 247,962.00 247,962.00
417,796.58
417,796.58
417,796.58
(Force Account)
Sawang CIP
Uson, Masbate
HAULING COST
I. HAULING OF CEMENT
Ave. Hauling Dist. : 35 kms (from source to jobsite/nearest roadsite)
Type of Road : Concrete
Utilized : 6-7 Tons Cargo Truck w/ five (5) laborers
Base Cost of Cement : P 240.00 /bag
Capacity of Cargo Truck : 150 /bags/trip
Rental P 1230.00 /hr.
Cycle Time:
With Load : 35 km/trip x 60min/hr. / 35 km./hr. - - - - - - 60.00 min/trip
W/o Load : 35 km/trip x 60min/hr. / 45 km./hr. - - - - - - 46.67 min/trip
Manual Loading Capability of five (5) Laborers
Loading and unloading = 300 bags/hr.
Loading : 150 bags/trip x 60 min/hr / 300 bags/hr. - - - - 30.00 min/trip
Unloading : 150 bags/trip x 60 min/hr / 300 bags/hr. - - - - 30.00 min/trip
Total Time - - - - - - - 166.67 min/trip
Or - - - - - - - - - - - 2.78 hrs./trip
LABOR COST:
a) Mechanized (From Source to Nearest Roadsite/Jobsite)
Driver : 1x 665.00 x 2.78 hrs/trip ¸ 8 hrs x 150 bags/trip - - P 1.54 /bag
Laborers: 5x 572.00 x 2.78 hrs/trip ¸ 8 hrs x 150 bags/trip - - 6.63 /bag
Note: The travel time on w/ & w/o load were only considered & the loading &
unloading time were excluded on the fuel consumption.
-SUMMARY-
Base Cost - - - - - - - - - - - - - - - - - - - - - - P 240.00 /bag
Labor Cost - - - - - - - - - - - - - - - - - - - - - - 55.84 /bag
Fuel Cost - - - - - - - - - - - - - - - - - - - - - - - 7.82 /bag
Rental - - - - - - - - - - - - - - - - - - - - - - - - - 22.80 /bag
Total - - - P 326.46 /bag
16.66667
Sawang CIP
Uson, Masbate
HAULING COST
Cycle Time:
With Load : 35 km/trip x 60min/hr. ¸ 35 min./hr. - - - - - - - - - - - - - - 60.00 min/hr.
W/o Load : 35 km/trip x 60min/hr. ¸ 45 min./hr. - - - - - - - - - - - - - - 46.67 min/hr.
Manual Loading Capability of five (5) Laborers
Loading and unloading = 250 pcs/trip
Loading : 250 pcs./trip x 60min/hr x 250pcs./trip - - - - - - - - - - - 60.00 min/trip
Unloading : 250 pcs./trip x 60min/hr x 250pcs./trip - - - - - - - - - - - 60.00 min/trip
Total Time - - - - - - - 226.67 min/trip
Or - - - - - - - - - - - 3.78 hrs./trip
LABOR COST:
a) Mechanized (From Source to Nearest Roadsite/Jobsite)
Driver : 1x 665.00 x 3.78 hrs/trip / 8 hrs x 250 pcs./trip - - - - - - - P 1.26
Laborers: 5x 572.00 x 3.78 hrs/trip / 8 hrs x 250 pcs./trip - - - - - - - 5.41
EQUIPMENT :
Fuel Cost = 10.00 (1.1 ) lit/hr. x 1.78 hrs/trip x P 60.00 /lit. 6pcs/trip - - - - - - - P 4.70
Rental = P 1230.00 /hr. x 3.78 hrs./trip ¸ 250 pcs/trip - - - - - - - - - - - 18.60
Note: The travel time on w/ & w/o load were only considered & the loading &
unloading time were excluded on the fuel consumption.
-SUMMARY-
PLYWOOD GI SHEET
Base Cost - - - - - - - - - - - - - - - - - - - - P 750.00 /pc. P 500.00 /pc.
Labor Cost - - - - - - - - - - - - - - - - - - - - 38.45 /pc. 38.45 /pc.
Fuel Cost - - - - - - - - - - - - - - - - - - - - - 4.70 /pc. 4.70 /pc.
Rental - - - - - - - - - - - - - - - - - - - - - - - 18.60 /pc. 18.60 /pc.
Total Cost - - P 811.75 /pc. P 561.75 /pc.
Sawang CIP
Uson, Masbate
HAULING COST
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
-SUMMARY-
Sawang CIP
Uson, Masbate
HAULING COST
Cycle Time:
With Load : 35 km/trip x 60min/hr. / 35 min./hr. - - - - - - - - - - - - 60.00 min/hr.
W/o Load : 35 km/trip x 60min/hr. / 45 min./hr. - - - - - - - - - - - - 46.67 min/hr.
Manual Loading Capability of five (5) Laborers
Loading and unloading = 4000 bd.ft./hr.
Loading : 4000 bd.ft./trip x 60 min/hr /4000 bd.ft/hr. - - - - - - - - - 60.00 min/trip
Unloading : 4000 bd.ft./trip x 60 min/hr /4000 bd.ft/hr. - - - - - - - - - 60.00 min/trip
Total Time - - - - - - - 226.67 min/trip
Or - - - - - - - - - - - 3.78 hrs./trip
LABOR COST:
a) Mechanized (From Source to Nearest Roadsite/Jobsite)
Driver : 1x 665.00 x 3.78 hrs/trip / 8 hrs x 4000 bd.ft./trip - - P 0.08 /bd.ft
Laborers: 5x 572.00 x 3.78 hrs/trip / 8 hrs x 4000 bd.ft./trip - - 0.34 /bd.ft
EQUIPMENT :
Fuel Cost = 10.00 (1.1 ) lit/hr. x 1.78 hrs/trip x P 60.00 /lit. ¸ 4,000 bd.ft./trip - - -P- 0.29 /bd.ft
Rental = P 1230.00 /hr. x 2.61 hrs./trip ¸ 4,000 bd.ft./trip - - - - - - - - - - - -
3.78hrs./trip 1.16 /bd.ft
Note: The travel time on w/ & w/o load were only considered & the loading &
unloading time were excluded on the fuel consumption.
-SUMMARY-
Base Cost - - - - - - - - - - - - - - - - - - - - - - - - - - P 60.00 /bd.ft
Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - 2.33 /bd.ft
Fuel Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.29 /bd.ft
Rental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1.16 /bd.ft
Total - - - P 63.78 /bd.ft
HAULING COST
Sawang CIP
Uson, Masbate
HAULING COST
4. Hauling of RSBars, C.W. Nails & G.I. Tie Wire
LABOR COST:
a) Mechanized (From Source to Nearest Roadsite/Jobsite)
Driver : 1x 665.00 x 3.64 hrs/trip / 8 hrs x 6,000 kgs/trip - - P 0.05 /kg.
Laborers: 5x 572.00 x 3.64 hrs/trip / 8 hrs x 6,000 kgs/trip - - 0.22 /kg.
Note: The travel time on w/ & w/o load were only considered & the loading &
unloading time were excluded on the fuel consumption.
-SUMMARY-
RSB C.W.Nails Tie Wire
Base Cost - - - - - - - - - - - - - - - - P 60.00 P 750.00 P 800.00 /kg.
Labor Cost - - - - - - - - - - - - - - - - - 1.54 1.54 1.54 /kg.
Fuel Cost - - - - - - - - - - - - - - - - - - - 0.20 0.20 0.20 /kg.
Rental - - - - - - - - - - - - - - - - - - - - - 0.75 0.75 0.75 /kg.
Total - - - P 62.49 P 752.49 P 802.49 /kg.
Sawang CIP
Uson, Masbate
HAULING COST
5. Hauling of Sand, Gravel
Ave. Hauling Dist. : 35 kms (from source to jobsite/nearest roadsite)
Base Cost : Sand = 650.00 /cu.m. Gravel = P 780.00 /cu.m.
5b. Hauling Cost (Mechanized) From: Source to Jobsite)
Utilized : 4 - 6 Dump Truck Capacity = 4.50 /cu.m.
Rental = P 1500.00 /hr.
Cycle Time:
W/load : 35 km/trip x 60 min/hr / 35km/hr. - - - - - - - - - - - - - 60.00 min/trip
W/out load: 35 km/trip x 60 min/hr / 45km/hr. - - - - - - - - - - - - - 46.67 min/trip
Loading spot manuevers, unloading & delay - - - - - - - - - - - - - - - - - - - 20.00 min/trip 0.333333
Total Time - - - - - - - - 126.67 min/trip
Say - - - - - - - - - - - - 2.11 hrs/trip
LABOR COST:
a.Mechanized From: Source to Jobsite)
Driver : 1x 665.00 /d x 2.11 hrs/day / 8hrs/day x 4.5 cu.m./trip - - - 38.98 /cu.m.
Laborers: 1x 572.00 /d x 2.11 hrs/day / 8hrs/day x 4.5 cu.m./trip - - - 33.53 /cu.m.
EQUIPMENT :
Fuel Cost = 15.00 (1.1 ) lit/hr. x 1.78 hrs./tripx P 60.00 /lit. / 4.5cu.m./trip- P 391.60 /cu.m.
Rental = P 1500.00 / km x 2.11 hrs./trip / 4.5 cu.m./trip - - - - - - - 703.33 /cu.m.
Hauling Equipment Cost - - - - P 1094.93 /cu.m.
-SUMMARY-
SAND GRAVEL
Base Cost - - - - - - - - - - - - - - - - - - - P 650.00 P 780.00
Labor Cost - - - - - - - - - - - - - - - - - - - 1597.84 1597.84
Fuel Cost - - - - - - - - - - - - - - - - - - - - 391.60 391.60
Rental - - - - - - - - - - - - - - - - - - - - - - 703.33 703.33
Total - - - - - - - - - P 3,342.770 P 3,472.770
Sawang CIP
Uson, Masbate
HAULING COST
6. Hauling of Boulder
Ave. Hauling Dist. : 35 kms (from source to jobsite/nearest roadsite)
Base Cost : 800.00 /cu.m.
EQUIPMENT :
Fuel Cost = 15.00 (1.1 ) lit/hr. x 1.78 hrs./trip x 60.00 /lit. / 3.5cu.m./trip- P 503.49 /cu.m.
Rental = P 1500.00 /hr. x 1.98 hrs./trip / 3.5 cu.m./trip - - - - - - - 848.57 /cu.m.
Hauling Equipment Cost - - - - P 1,352.06 /cu.m.
-SUMMARY-
-SUMMARY-
Sawang CIP
Uson, Masbate
2. Labor Cost
a. Concreting Works:
Crew : 1 - Foreman; 2 - Mason; 1 - L.E. Operator; 10 - Laborers
Capability : 6.0 cu.m./day
b. Laying of Boulders
Crew: 1 - Laborer
Capability : 1.5 cu.m./day
RATE L A BO R
POSITION PER Concreting Works Laying of Boulders
DAY No. Cost No. Cost
Foreman 1,042.00 1 1,042.00
Mason 472.00 2 944.00
L.E. Operator 2,191.00 1 2,191.00
Laborer 572.00 10 5,720.00 1 572.00
TOTAL UNIT COST 9,897.00 572.00
UNIT COST 1,649.50 381.33
Rate LABOR
Position per Casting of Pipes Laying of Pipes
day No. Cost No. Cost
Foreman 1,042.00 1 1,042.00 1 1,042.00
Sr. Mason 700.00 1 700.00 1 700.00
Sr. Carpenter 700.00 1 700.00 1 700.00
L.E. Operator 2,191.00 1 2,191.00 1 2,191.00
Laborers 572.00 12 6,864.00 12 6,864.00
TOTAL COST 11,497.00 11,497.00
UNIT COST 1,916.17 1,149.70
( Continuation 76 cm dia RCP )
3. Equipment Cost
3.a. Casting
Utilized : 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 15.12 Bags/day x 10min/bag / 60min/hr.
= 2.52 hours
3.b. Laying
Utilized ; 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 9.30 Bags/day x 10min/bag / 60min/hr.
= 1.55 hours
Total Cost Unit Cost
Rental Cost = 1.55 hrs. x P 2,000.00 /hr. - - - - - - - P 3,100.00 P 310.00
Fuel & Oil = 1.55 hrs. x P 60.00 /lit. x 1.5lit./hr. 139.50 13.95
-SUMMARY-
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - -P 4,311.50 1,077.88 5,389.38
Labor - - - - - - - - - - - - - - - - - - - - 4,027.52 1,006.88 5,034.40
Rental - - - - - - - - - - - - - - - - - - - 1,570.32 392.58 1,962.90
Fuel & Oil- - - - - - - - - - - - - - - - - 262.75 65.69 328.44
TOTAL - - - - - - - - P 10,172.09 2,543.03 12,715.12
Field Support & Supervision 254.30
12,969.42
Sawang CIP
Uson, Masbate
2. Labor Cost
2a. Direct Labor Cost
2.a.1 Concreting (Casting)
Crew : 1 - Foreman; 1 - Sr. Mason ; 1 - L.E. Operator; 12-Laborers
Capability : 9.0 pcs/day
Rate LABOR
Position per Casting of Pipes Laying of Pipes
day No. Cost No. Cost
Foreman 1,042.00 1 1,042.00 1 1,042.00
Sr. Mason 700.00 1 700.00 1 700.00
Sr. Carpenter 700.00 1 700.00 1 700.00
L.E. Operator 2,191.00 1 2,191.00 1 2,191.00
Laborers 572.00 12 6,864.00 12 6,864.00
TOTAL COST 11,497.00 11,497.00
UNIT COST 1,277.44 958.08
3. Equipment Cost
3.a. Casting
Utilized : 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 16.38 Bags/day x 10min/bag / 60min/hr.
= 2.73 hours
3.b. Laying
Utilized ; 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 8.64 Bags/day x 10min/bag / 60min/hr.
= 1.44 hours
Total Cost Unit Cost
Rental Cost = 1.44 hrs. x P 2,000.00 /hr. - - - - - - - P 2,880.00 P 240.00
Fuel & Oil = 1.44 hrs. x P 60.00 /lit. x 1.5lit./hr. 129.60 10.80
-SUMMARY-
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - - P 2,961.10 740.28 3,701.38
Labor - - - - - - - - - - - - - - - - - - - - 2,929.86 732.47 3,662.33
Rental - - - - - - - - - - - - - - - - - - - 1,149.80 287.45 1,437.25
Fuel & Oil- - - - - - - - - - - - - - - - - 188.51 47.13 235.64
TOTAL - - - - - - - P 7,229.27 1,807.33### 9,036.60
Field Support & Supervision 180.73
9,217.33
Sawang CIP
Uson, Masbate
2. Labor Cost
2a. Direct Labor Cost
2.a.1 Concreting (Casting)
Crew : 1 - Foreman; 1 - Sr. Mason ; 1 - L.E. Operator; 12-Laborers
Capability : 11.0 pcs/day
Rate LABOR
Position per Casting of Pipes Laying of Pipes
day No. Cost No. Cost
Foreman 1,042.00 1 1,042.00 1 1,042.00
Sr. Mason 700.00 1 700.00 1 700.00
Sr. Carpenter 700.00 1 700.00 1 700.00
L.E. Operator 2,191.00 1 2,191.00 1 2,191.00
Laborers 572.00 12 6,864.00 12 6,864.00
TOTAL COST 11,497.00 11,497.00
UNIT COST 1,045.18 821.21
3. Equipment Cost
3.a. Casting
Utilized : 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 13.42 Bags/day x 10min/bag / 60min/hr.
= 2.24 hours
3.b. Laying
Utilized ; 1Bagger Concrete Mixer
Rental : P ### /hr.
Total Time per day = 6.30 Bags/day x 10min/bag / 60min/hr.
= 1.05 hours
Total Cost Unit Cost
Rental Cost = 1.05 hrs. x P47.20/hr. - - - - - - - - - - - - 2,100.00 P 150.00
Fuel & Oil = 1.05 hrs x 1.5lit./hr x P15.00/lit. - - - - - - 18.90 1.35
-SUMMARY-
Materials - - - - - - - - - - - - - - - - P 2,855.12
Labor - - - - - - - - - - - - - - - - - - - 1,866.39
Rental - - - - - - - - - - - - - - - - - - - 557.27
Fuel & Oil- - - - - - - - - - - - - - - - - 5.02
TOTAL 5,283.80
Field Support & Supervision 105.68
5,389.48
Sawang CIP
Uson, Masbate
2. Labor Cost
A Laying of Boulders
Crew: 1 - Laborer
Capability : 1.5 cu.m./day
RATE L A BO R
POSITION PER Laying of boulder
DAY No. Cost
Laborer 572.00 1 572.00
TOTAL UNIT COST 572.00
UNIT COST 381.33
SUMMARY
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - - - P 800.00 200.00 1,000.00
Labor - -- - - - - - - - - - - - - - - - - - - 1,994.14 498.54 2,492.68
Rental - - - - - - - - - - - - - - - - - - - 848.57 212.14 1,060.71
Fuel & Oil- - - - - - - - - - - - - - - - - 503.49 125.87 629.36
UNIT COST - - - - - P 4,146.20 1,036.55 5,182.75
Field Support & Supervision 103.66
5,286.41
Sawang CIP
Uson, Masbate
Unit Cost Analysis ( LMC )
FILTER DRAIN BED (per cu.m.) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P P5,293.21
RATE L A BO R
POSITION PER Spreading of Aggregates: Laying of Gravel:
DAY No. Cost No. Cost
Laborer 572.00 1 572.00 1 572.00
TOTAL UNIT COST 572.00 572.00
UNIT COST 228.80 286.00
SUMMARY
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - - --P 1,027.00 256.75 1,283.75
Labor - -- - - - - - - - - - - - - - - - - - - 2,112.64 528.16 2,640.80
Rental - - - - - - - - - - - - - - - - - - - 703.33 175.83 879.16
Fuel & Oil - - - - - - - - - - - - - - - - 391.60 97.90 489.50
UNIT COST - - - - - P 4,234.57 1,058.64 5,293.21
Field Support & Supervision 105.86
5,399.07
Sawang CIP
Uson, Masbate
2. Labor Cost
a. Laying of Gravel:
Crew: 1 - Laborer
Capability : 2.0 cu.m./day
RATE LABOR
POSITION PER Laying of Gravel:
DAY No. Cost
Laborer 572.00 1 572.00
TOTAL UNIT COST 572.00
UNIT COST 286.00
SUMMARY
Mark-up Total
(25%) Unit Cost
1. Materials - - - - - - - - - - - - - - - P 780.00 195.00 975.00
2. Labor - -- - - - - - - - - - - - - - - - - 1,883.84 470.96 2,354.80
3. Rental - - - - - - - - - - - - - - - - - - 703.33 175.83 879.16
4. Fuel Cost - - - - -- - - - - - - - - - - - 391.60 97.90 489.50
UNIT COST - - - - - P 3,758.77 939.69 4,698.46
Field Support & Supervision 93.97
4,792.43
Sawang CIP
Uson, Masbate
2. Labor Cost
a. Screening of Sand
Crew: 1 - Laborer
Capability : 6.0 cu.m./day
b. Concreting Works
Crew: 2 - Masons
2 - Laborers
Capability : 12.0 sq.m./day (one side)
RATE LABOR
POSITION PER Screening Concreting
DAY No. Cost No. Cost
Mason 700.00 2 1,400.00
Laborer 572.00 1 572.00 2 1,144.00
TOTAL UNIT COST 572.00 2,544.00
UNIT COST 3.24 212.00
SUMMARY
Mark-up Total
(25%) Unit Cost
1. Materials - - - - - - - - - - - - - - - P 120.50 30.13 150.63
2. Labor - -- - - - - - - - - - - - - - - - - 292.46 73.12 365.58
3. Rental - - - - - - - - - - - - - - - - - - 33.26 8.32 41.58
4. Fuel Cost - - - - -- - - - - - - - - - - - 16.52 4.13 20.65
UNIT COST - - - - - P 462.74 115.70 578.44
Field Support & Supervision 11.57
590.01
Sawang CIP
Uson, Masbate
2. Labor Cost
1 - Carpenter @ P 700.00 /day - - - P 700.00
4 - Laborers @ P 572.00 /day - - - P 2,288.00
Total - - - P 2,988.00
Capability : 20.0 cu.m./day
Unit Cost - - - - - - -P 2,988.00 -------P 149.40
20.0 cu.m.
B. DEWATERING - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 309.93
1. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 59.17
1 -Laborer @ P 572.00 /day- - - - P 572.00
No. of Dewatering Days - - - - - - 15 days = 120 hours
Cost of Labor - - - - P 572.00 /day x 15 days = P 8,580.00
Volume of Dewatering - - - - - - - 145 cu.m.
Unit Cost - - - - - - -P 8,580.00 -------P 59.17
145 cu.m.
SUMMARY
Mark-up Total
(25%) Unit Cost
1. Materials - - - - - - - - - - - - - - - - P1,125.00 281.25 1,406.25
2. Labor - -- - - - - - - - - - - - - - - - - 243.98 61.00 304.98
3. Rental - - - - - - - - - - - - - - - - - - 104.53 26.13 130.66
4. Fuel Cost - - - - -- - - - - - - - - - - - 168.27 42.07 210.34
UNIT COST - - - - - - - - P1,641.78 410.45 2,052.23
Field Support & Supervision 41.04
2,093.27
Sawang CIP
Uson, Masbate
2. Labor Cost
1 - Carpenter @ P 700.00 /day - - - P 700.00
4 - Laborers @ P 572.00 /day - - - P 2,288.00
Total - - - P 2,988.00
Capability : 20.0 cu.m./day
Unit Cost - - - - - - -P 2,988.00 -------P 149.40
20.0 cu.m.
B. DEWATERING - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 299.60
1. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 57.20
1 -Laborer @ P 572.00 /day- - - - P 572.00
No. of Dewatering Days - - - - - - 20 days = 160 hours
Cost of Labor - - - - P 572.00 /day x 20 days = P 11,440.00
Volume of Dewatering - - - - - - - 200 cu.m.
Unit Cost - - - - - - -P 11,440.00 -------P 57.20
200 cu.m.
SUMMARY
Mark-up Total
(25%) Unit Cost
1. Materials - - - - - - - - - - - - - - - - P1,125.00 281.25 1,406.25
2. Labor - -- - - - - - - - - - - - - - - - - 242.01 60.50 302.51
3. Rental - - - - - - - - - - - - - - - - - - 101.63 25.41 127.04
4. Fuel Cost - - - - -- - - - - - - - - - - - 162.81 40.70 203.51
UNIT COST - - - - - - - - P1,631.45 407.86 2,039.31
Field Support & Supervision 40.79
2,080.10
Sawang CIP
Uson, Masbate
Unit Cost Analysis ( LMC )
A. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 29.83
1 - H. E. O. @ P 472.00 /day- - - - - P 472.00
1 - Laborers @ 572.00 /day- - - - - 572.00
Output = 35.00 cu.m./ day
Unit Cost = P 1044.00 = P 29.83
35.00
S U M M A R Y
Mark-up Total
(25%) Unit Cost
1. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - P 29.83 7.46 37.29
2. Equipment Rental- - - - - - - - - - - - - - - - - - - - - 257.14 64.29 321.43
3 Fuel & Oil- - - - - - - - - - - - - - - - - - - - - - - - - - 56.57 14.14 70.71
TOTAL - - - - - - - - - - - - - - - - - 343.54 89.32 432.86
Field Support & Supervision 8.66
441.52
Manolib CIS
Uson, Masbate
BILL OF MATERIALS
& COST ESTIMATES
A. MATERIALS - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P87,690.00
1. Angle Bar 3/8 x 4 x 4 x 20' - 2 pcs. @ P 5,000.00 /pc.- - - - - - - - P 10,000.00
2. Angle Bar 3/8 x 3 x 3 x 20' - 4 pcs. @ 4,000.00 /pc.- - - - - - - - - 16,000.00
3. Black Sheet,5/16"x1.05x1.05 - 1 pc. @ 9,000.00 /pc.- - - - - - - - - 9,000.00
4. Lifting Stem(w/1.20 thread)
1½" f x 2.40m - 1 pc. @ 10,000.00 /pc.- - - - - - - - - 10,000.00
5. Housing Block (HB)
#30 with bearing - 1 pc. @ 20,000.00 /pc.- - - - - - - - - 20,000.00
6. Handwheel - 1 pc. @ 7,000.00 /pc.- - - - - - - - - 7,000.00
7. Flat Bar, ½" x 1½" x 10' - 1 pc. @ 800.00 /pc.- - - - - - - - - 800.00
8. Flat Bar, 3/8" x 2½" x 10' - 1 pc. @ 1,000.00 /pc.- - - - - - - - - 1,000.00
9. Anchor Bolt 5/8" x 12" - 8 pcs. @ 450.00 /pc.- - - - - - - - - 3,600.00
10. Machine Bolt 3/4 x 3½ - 1 pc. @ 400.00 /pc.- - - - - - - - - 400.00
11. Bolt w/ Nut - ½"f x 2" - 8 pcs. @ 150.00 /pc.- - - - - - - - - 1,200.00
12. Welding Rod - 2 kgs. @ 65.00 /kg.- - - - - - - - - 130.00
. 13. Oxygen & Acytelene - 1 pair @ 4,000.00 /pair - - - - - - - - 4,000.00
14. Hacksaw Blade - 6 pcs. @ 60.00 /pc.- - - - - - - - - 360.00
15. Collar Epoxy - 1 qrt. @ 200.00 /qrt.- - - - - - - - - 200.00
16. Red Oxide Primer - 2 qrts. @ 200.00 /qrt.- - - - - - - - - 400.00
17. Enamel Paint, Black - 2 qrts. @ 200.00 /qrt.- - - - - - - - - 400.00
18. Paint Brush #2 - 2 pcs. @ 50.00 /pc.- - - - - - - - - 100.00
19. Grease Gear - 0.5 kg. @ 200.00 /kg.- - - - - - - - - 100.00
. 20. Miscellaneous Expenses - 1 L.S. @ 3,000.00 - - - - - - - - - - 3,000.00
Sub-Total - - - - - - - - - - - - - - - - - P 87,690.00
SUMMARY
Mark-up Unit
(19.5%) Cost
1. Materials - - - - - - - - - - - - - - - P 87,690.00 17,099.55 P 104,789.55
A. MATERIALS - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P45,000.00
1. Angle Bar 9mmx100mmx10' - 4 pcs. @ P 1,200.00 /pc.- - - - - - - - P 4,800.00
2. Angle Bar 8mmx 75mmx10' - 2 pcs. @ 800.00 /pc.- - - - - - - - - 1,600.00
3. Flat Bar -12mmx40mmx20' - 1 pc. @ 700.00 /pc.- - - - - - - - - 700.00
4. Flat Bar - 9mmx89mmx20' - 1 pc. @ 500.00 /pc.- - - - - - - - - 500.00
5. HB Type Lifting
Mechanism (76cm) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 21,700.00
6. Hold-Down Plate - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 800.00
7. MS Plate 3/8" - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5,400.00
8. 76 cm diameter Handwheel & Lock Device - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2,500.00
9. 2: diameter Stem - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2,000.00
10. Assorted Nuts & Bolts - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,500.00
11. Welding Rod & Oxyacetelene - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2,500.00
12. Paint & Thinner - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,000.00
SUMMARY
1. Materials - - - - - - - - - - - - - - - - P P45,000.00
2. Labor - - - - - - - - - - - - - - - - - - - - - - 17,100.00
3. Hauling & Installation - - - - - - - - - - - 4,238.00
4. Profit - - - - - - - - - - - - - - - - - - - - - - 6,210.00
5. Taxes - - - - - - - -- - - - - - - - - - - - - - 7,452.00
TOTAL - - - - - - - - -P P80,000.00
Sawang CIP
Uson, Masbate
BILL OF MATERIALS
& COST ESTIMATES ( LMC )
A. MATERIALS - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P68,025.00
1. Angle Bar 3/8 x 4 x 4 x 20' - 2 pcs. @ P 3,900.00 /pc.- - - - - - - - P 7,800.00
2. Angle Bar 3/8 x 3 x 3 x 20' - 4 pcs. @ 3,000.00 /pc.- - - - - - - - - 12,000.00
3. Black Sheet,5/16"x1.05x1.05 - 1 pc. @ 7,500.00 /pc.- - - - - - - - - 7,500.00
4. Lifting Stem(w/1.20 thread)
1½" f x 2.40m - 1 pc. @ 6,000.00 /pc.- - - - - - - - - 6,000.00
5. Housing Block (HB)
#30 with bearing - 1 pc. @ 15,000.00 /pc.- - - - - - - - - 15,000.00
6. Handwheel - 1 pc. @ 5,500.00 /pc.- - - - - - - - - 5,500.00
7. Flat Bar, ½" x 1½" x 10' - 1 pc. @ 480.00 /pc.- - - - - - - - - 480.00
8. Flat Bar, 3/8" x 2½" x 10' - 1 pc. @ 750.00 /pc.- - - - - - - - - 750.00
9. Anchor Bolt 5/8" x 12" - 8 pcs. @ 330.00 /pc.- - - - - - - - - 2,640.00
10. Machine Bolt 3/4 x 3½ - 1 pc. @ 300.00 /pc.- - - - - - - - - 300.00
11. Bolt w/ Nut - ½"f x 2" - 8 pcs. @ 100.00 /pc.- - - - - - - - - 800.00
12. Welding Rod - 2 kgs. @ 65.00 /kg.- - - - - - - - - 130.00
. 13. Oxygen & Acytelene - 1 pair @ 4,000.00 /pair - - - - - - - - 4,000.00
14. Hacksaw Blade - 6 pcs. @ 50.00 /pc.- - - - - - - - - 300.00
15. Collar Epoxy - 1 qrt. @ 150.00 /qrt.- - - - - - - - - 150.00
16. Red Oxide Primer - 2 qrts. @ 150.00 /qrt.- - - - - - - - - 300.00
17. Enamel Paint, Black - 2 qrts. @ 100.00 /qrt.- - - - - - - - - 200.00
18. Paint Brush #2 - 2 pcs. @ 50.00 /pc.- - - - - - - - - 100.00
19. Grease Gear - 0.5 kg. @ 150.00 /kg.- - - - - - - - - 75.00
. 20. Miscellaneous Expenses - 1 L.S. @ 4,000.00 - - - - - - - - - - 4,000.00
Sub-Total - - - - - - - - - - - - - - - - - P 68,025.00
SUMMARY
Mark-up Unit
(26%) Cost
1. Materials - - - - - - - - - - - - - - - P 68,025.00 17,686.50 P 85,711.50
RATE L A BO R
POSITION PER Fab., Placing & Dismt'ng Concreting & Curing
DAY No. Cost No. Cost
Foreman 1,042.00 1 1,042.00
Mason 700.00 2 1,400.00
Carpenter 700.00 2 1,400.00
L.E. Operator 2,191.00 1 2,191.00
Laborer 572.00 4 2,288.00 8 4,576.00
TOTAL UNIT COST 3,688.00 9,209.00
UNIT COST 1,053.71 2,631.14
3. EQUIPMENT COST (One Bagger Concrete Mixer)
Utilized : Yanmar 1 Bagger Conc. Mixer ; Rental: P 47.20/hr.
Total Time per Day = 3.5cu.m./day x 9.0 bags/cu.m.x 10min.bag / 60min./hr.
= 5.25 hrs/day
Rental : = 5.25 hrs./day x P 2,000.00 /hr. /3.5 cu.m./day- - - - P 3,000.00 /cu.m.
Fuel Cost: = 5.25 hrs./day x P 60.00 /lit. x 1.5lits/hr.- - - - - - P 135.00 /cu.m.
3.5cu.m./day
SUMMARY
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - - - - P 7,092.00 1,773.00 8,865.00
Labor - -- - - - - - - - - - - - - - - - - 3,684.85 921.21 4,606.06
Rental - - - - - - - - - - - - - - - - - - 4,208.45 1,052.11 5,260.56
Fuel & Oil - - - - - - - - - - - - - - - 747.57 186.89 934.46
UNIT COST - - - - - P 15,732.87 3,933.21 19,666.08
Field Support & Supervision 393.32
20,059.40
Sawang CIP
Uson, Masbate
211 kgs/sq.cm. REINFORCED CONCRETE (Per cu.m.) FOR CANAL STRUCTURES- - - - - P 28,748.69
1. Material Cost (Including Hauling Cost) - - - - - - - - - - - - - - - - - - - - - - - P 14,346.64
PER BASE HAULING COST
MATERIALS UNIT
CU.M. COST Labor Rental Fuel Cost
Cement bag 9.00 2,160.00 502.56 205.20 70.38
RSB kg. 40.00 2,400.00 61.60 30.00 8.00
Gravel cu.m. 0.90 702.00 1,438.06 633.00 352.44
Sand cu.m. 0.45 292.50 719.03 316.50 176.22
Lumber bd.ft. 25.00 1,500.00 58.25 29.00 7.25
Plywood pc. 1.25 937.50 48.06 23.25 5.88
C.W. Nails kg. 1.75 1,312.50 2.70 1.31 0.35
Tie Wire kg. 0.44 352.00 0.68 0.33 0.09
TOTAL 9,656.50 2,830.94 1,238.59 620.61
2. Labor Cost
2.a Direct Labor Cost
2.a1. Fabrication. Placing & Dismantling Cost
Cew: 2-Carpenter; & 4 - Laborers
Capability : 3.50 cu.m./day
2.a2. Concreting & Curing Works
Crew : 1 - Foreman; 2 - Mason; 1 - L.E. Operator; 8 - Laborers
Capability : 3.50 cu.m./day
2.a3. R.S. Bars (Cutting, Bending & Placing)
Crew: 1 - Steelman & 1 - Laborer
Capability : 80 kgs/day or 2.0 cu.m./day
RATE L A BO R
POSITION PER Fab., Placing & Dismt'ng Concreting & Curing (CBP) RSB
DAY No. Cost No. Cost No. Cost
Foreman 1,042.00 1 1,042.00
Steelman 2,191.00 1 2,191.00
Mason 700.00 2 1,400.00
Carpenter 700.00 2 1,400.00
L.E. Operator 2,191.00 1 2,191.00
Laborer 572.00 4 2,288.00 8 4,576.00 1 572.00
TOTAL UNIT COST 3,688.00 9,209.00 2,763.00
UNIT COST 1,053.71 2,631.14 1,381.50
a. Concreting Works:
Crew : 1 - Foreman; 2 - Mason; 1 - L.E. Operator; 10 - Laborers
Capability : 7.5 cu.m./day
b. Laying of Boulders
Crew: 1 - Laborer
Capability : 1.5 cu.m./day
RATE L A BO R
POSITION PER Concreting Works Laying of Boulders
DAY No. Cost No. Cost
Foreman 1,042.00 1 1,042.00
Mason 700.00 2 1,400.00
L.E. Operator 2,191.00 1 2,191.00
Laborer 572.00 10 5,720.00 1 572.00
TOTAL UNIT COST 10,353.00 572.00
UNIT COST 1,380.40 381.33
SUMMARY
Mark-up Total
(25%) Unit Cost
Materials - - - - - - - - - - - - - - - P 2,074.50 518.63 2,593.13
Labor - -- - - - - - - - - - - - - - - - - - - 4,248.20 1,062.05 5,310.25
Rental - - - - - - - - - - - - - - - - - - - - - 2,625.67 656.42 3,282.09
Fuel Cost - - - - -- - - - - - - - - - - - - - 755.97 188.99 944.96
UNIT COST - - - - - P 9,704.34 2,426.09 12,130.43
Field Support & Supervision - - P 242.61
12,373.04
Sawang CIP
Uson, Masbate
BILL OF MATERIALS
& COST ESTIMATES
B. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P3,166.00
1 - Foreman @ P 310.00 /day- - - - - - - - - - - - P 310.00
1 - Welder @ 665.00 /day- - - - - - - - - - - - 665.00
1 - Steelman @ 2,191.00 /day- - - - - - - - - - - - 2,191.00
2. INSTALLATION
A. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P922.00
1 - Foreman @ P - /day- - - - - - - - - - - - P -
1 - Mason @ 700.00 /day- - - - - - - - - - - - 700.00
2 - Laborers @ 572.00 /day- - - - - - - - - - - - 1,144.00
SUMMARY
Ceiling Unit
Cost Cost
1. Materials - - - - - - - - - - - - - - P 4,675.00 911.63 P 5,586.63
2. Labor - - - - - - - - - - - - - - - - - - - - 4,088.00 797.16 4,885.16
3. Rental - - - - - - - - - - - - - - - - - - - 4,000.00 780.00 4,780.00
4. Labor - - - - - - - - - - - - - - - - - - - - - 960.00 187.20 1,147.20
TOTAL - - - - - - -P 13,723.00 2,675.99 P 16,398.99
Sawang CIP
Uson, Masbate
BILL OF MATERIALS
& COST ESTIMATES
C. Sundries - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P2,702.54
SUMMARY
Mark-up Unit
(19.5%) Cost
1. Materials - - - - - - - - - - - - P 33,933.33 6,617.00 P 40,550.33
2. Labor - - - - - - - - - - - - - - - - - - 13,573.33 2,646.80 16,220.13
3. Sundries - - - - - - - - - - - - - - - - 2,702.54 527.00 3,229.54
TOTAL - - - - - - - P 50,209.20 9,790.80 P 60,000.00
Sawang CIP
Uson, Masbate
Output = 2 trips/day
Unit Cost = P 4,870.00 x 2 trips/day = P 9,740.00
2 trips/day
Output = 2 trip/day
Unit Cost = P 14,100.00 x 2.00 trip/day = P 28,200.00
Output = 2 trip/day
Unit Cost = P 29,040.00 x 2 trip/day = P 58,080.00
1 trip/day
S U M M A R Y
Unit
Cost
1. Labor - - - - - - - - - - - - - - - - - - - - - - - - - - P 9,740.00
2. E. Rental - - - - - - - - - - - - - - - - - - - - - - - - 28,200.00
3. Fuel & Oil - - - - - - - - - - - - - - - - - - - - - - 58,080.00
TOTAL - - - - - - - - - - - - - - P 96,020.00
Sawang CIP
Uson, Masbate
UNIT COST ANALYSIS
Rate LABOR
POSITION Per Casting Laying/Setting
Day No. Cost No. Cost
Sr. Mason 700.00 1 700.00
Laborer 572.00 2 1144.00 2 1144.00
Total Cost 1144.00 1844.00
Unit Cost 95.33 184.40
-SUM MARY-
Total Mark-up Total
Cost (25%) Unit Cost
Materials - - - - - - - - - - - - - - P 765.19 191.30 956.49
Labor - - - - - - - - - - - - - - - - - 659.34 164.84 824.18
Rental - - - - - - - - - - - - - - - - 164.59 41.15 205.74
Fuel Cost - - - - - - - - - - - - - 83.50 20.88 104.38
Unit Cost - - - - 1,672.62 418.17 2,090.79
Field Support & Supervision 41.82
2,132.61
Sawang CIP
Uson, Masbate
UNIT COST ANALYSIS
Sawang CIP
Uson, Masbate
UNIT COST ANALYSIS ( LMC )
ACCESS ROAD . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I- BORROW MATERIALS ( per sq.m. ) = P 10.00
2. Labor Cost :
2.a. Direct Cost
2.a.1. Casting:
Crew : 2 - Laborers
Capability : 16 sq.m./day
a.2 Laying/Setting:
Crew : 1 - Sr. Mason; 2 - Laborers
Capability : 15 sq.m./day
Rate LABOR
POSITION Per Casting Laying/Setting
Day No. Cost No. Cost
Sr. Mason 700.00 1 700.00
Laborer 572.00 2 1144.00 2 1144.00
Total Cost 1144.00 1844.00
Unit Cost 71.50 122.93
-SUM MARY-
Total Mark-up Total
Cost (25%) Unit Cost
Materials - - - - - - - - - - - - - - P 972.82 243.21 1,216.03
Labor - - - - - - - - - - - - - - - - - 194.43 48.61 243.04
Rental - - - - - - - - - - - - - - - - 116.39 29.10 145.49
Fuel Cost - - - - - - - - - - - - - 59.17 14.79 73.96
Unit Cost - - - -P 1,342.81 335.71 1,678.52
Field Support & Supervision 33.57
1,712.09
Sawang CIP
Uson, Masbate