Republic of the Philippines

PROVINCE OF SURIGAO DEL SUR


Municipality of Marihatag

PROJECT PROPOSAL

Concreting of JNR Curvada (Bayan) to


Panay-as to Kinitaan Farm to Market
Road
TOTAL PROJECT COST:
Php 98,823,987.73

Project Proponent:
Local Government Unit
Marihatag, Surigao del Sur
PROJECT PROPOSAL

Concreting of JNR Curvada (Bayan) to Panay-As to Kinitaan Farm to Market


Road

(Total Project Cost: Php 98,823,987.73)

I. Project Description
A. Brief Summary
The project (4.86km total length) addresses the need for more convenient access
from JNR Curvada (Bayan) to Panay-As to Kinitaan Farm to Market Road. Major
Crops produced such as Rice, Coconut, Abaca and other forest products have
more ease of access to the market and reduced costs of transporting farm goods.
There will also be ease of travelling of residents from Sitio Kinitaan, San Isidro, to
Sitio Panay-As, Bayan to Sitio Curvada, Bayan which is the junction road to the
national highway and vice versa.

The project supports the local government in its push to economic development
in terms of agriculture through expansion of crops production and eco-tourism.
Through this project more landowners and farmer residents will be encouraged
to develop and cultivate their land, venture into other varieties of produce and
livestock farming. Potential Eco-tourism spots be explored and developed in the
said area.

The project is deemed to make investors to discover other potential


developments in the area especially cultivation of land for livestock production. It
will also pave way for the residents of Barangay Mahaba a direct route to
Barangay Poblacion without passing Barangay San Isidro and Barangay Bayan.

B. Project Goals and objectives

Goal: To improve the socio-economic condition of the farmers of the barangay


San Isidro, Bayan, Mahaba and the neighboring areas.

Specific Objectives:

- To increase the individual household income of the farmers.


- To improve mobility and reduce transportation and hauling cost of farmers
- To reduce the risk of road mishaps and improve accessibility for all residents
and tourist alike.
- To discover the potentials for development in agricultural, industrial and eco-
tourism.

C. Target Beneficiaries

- Direct Beneficiaries: Farmer and residents of barangay’s San Isidro, Bayan,


Mahaba
- Indirect Benefiriacies: Local Business men
School children (Elementary and Secondary)

II. Site Location Map


III. Project Components and Implementation Schedule

No. Major Components/Activities Proposed Time Responsible


Frame Persons
I Documentary Requirements:
 Engineering, Publication
Posting, Bid Opening, Bid
Evaluation, Post
Qualification, Notice to
Commence & others
II Project Commencement
 Supervision
 Project Monitoring
 Quality Control
 HSE
III Project Turn-over and Acceptance
 Handing Over
Documentation
 Operation Maintenance
Support
 Voluntary Works
IV Sustainability Evaluation
 Regular joint evaluation for
sustainability of the project

IV.[III.] Project Scope and Financial Plan


Line Items Amount Php
1. Direct Cost
a. Mobilization/Demobilization 321,203.00
b. Design Engineering & Geotechnical Study 423,332.07
c. Item 101(3) – Removal of structure and obstruction 886,345.20
d. Item 102.00 – Excavation 240,328.33
e. Item 107(1) – Overhaul 284,457.47
f. Item 105(1) – Subgrade Preparation 711,281.50
g. Item 200 – Aggregate Subbase Course 5,621,201.26
h. Item 201 – Aggregate Base Course 1,468,796.78
i. Item 311(1) – Portland Cement Concrete Pavement 59,277,349.02
(Unreinforced 200mm thk.)
j. Item 404 – Reinforcing Steel 463,441.60
k. Item 405 – Structural Concrete 1,268,293.74
l. Item 500(1)a3 – Pipe Culverts, 910mm dia. 849,874.37
2. Indirect Cost
a. Contractor Profit 7,181,590.43
b. OCM 7,181,590.43
c. VAT 6,032,535.96
d. EAO 3,227,406.74
Total PhP 95,439,027.91

V.[IV.] Project Management

In the implementation of the project, the Municipal Engineering Office will be the
lead Local Government Unit agency to implement the project.

A regular monitoring during the implementation shall be conducted by the


implementing unit. Upon its completion, the project shall be turned-over to the
barangays concerned, who shall then responsible for the project maintenance
with the support of the people’s organization and other stakeholders in the
community.

VI.[V.] Project Sustainability

To ensure the project sustainability, the municipal and barangay government


units in partnership with the line government agencies concerned shall organize
Operation and Maintenance Group for the project. Maintenance operation
schedule and activity plan has to be prepared by the group leader and its
members.

Regular evaluation has to be conducted by the maintenance group and submit


reports to Barangay Officials or Local Chief Executive for updates and project
situation and status.

VII.[VI.] Risk Analysis

Weather condition and natural calamities are considered as major risk that cause
delay in the implementation. There might be days that the construction
operation would cease due to high intensity of rainfall which leaves the ground
saturated thereby rendering it unsuitable for earthwork operations as well as the
safety and mobility of the construction equipment’s and its operators. This may
cause undue delay or the project duration and completion.

Safety and security of the project construction materials should be of utmost


consideration. In this aspect, the farmers’ association and barangay government
officials shall secure the security of these said project materials. All project
partners/contractors shall also be held responsible and liable on this concern.
VIII.[VII.] Environmental Safety and Health

General

Sufficient welfare facilities including cool drinking water, shaded rest areas and
toilets shall be provided in close proximity to the workers. Members of the
construction team will be issued with personal protective equipment (PPE).

Traffic

Barriers and warning signs will be provided as appropriate measure. Barriers will
be used for edge protection, tape will be used as a warning of danger.

All drivers and equipment operators are with proper competent training.

Flagman directing vehicles and equipment shall be trained. Vehicles and


equipment shall be inspected regularly and prior to starting operation to ensure
good working condition.

Dust Control

Use all necessary means at the sire under occupation to control dust particles.
Thoroughly moisten all surface as required to prevent dust and nuisance or a
hazard to the residents and properties.

Erosion Control

The work shall consist of procuring, installing and maintaining a slit fence type
sediment barrier in accordance with the technical specification and construction
details, and as shown on the approved erosion, sedimentation and pollution
control plan (ESPC Plans).

Prepared by:

MEO, MPDO and MMO

Approved by:

JUSTIN MARC L. PELENIO


Municipal Mayor