Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015

116, Door Sanchar


Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/01
Work Order date : 18.04.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Prem Nagar,Lada Ka Bas,Papda and Paota BHQ in
Virat nagar block
Appx route length (in meter) : 6500 M
Completion time : 15 days (Fifteen days)
Estimate no. : Yet to be allotted
MB No. : 02
Site incharge : Virender Yadav SDE(NOFN) SHP, Dharam Singh Bargotiya
JTO(NOFN) SHP
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the
date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
2) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
3) The AO (works), O/o PGMTD, Jaipur.
4) The DGM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/02
Work Order date : 20.04.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement / Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atel Seva Kendra Kairodi,Ammai and Basai in Kotputli Block.

.Appx route length : 8.7 Km


Completion time : 20 days (Twenty days)
Estimate no. : Yet to be allotted
MB No. : 03
Site incharge : Virender Yadav SDE(NOFN) SHP, Dharam Singh Bargotiya
JTO(NOFN) SHP
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
6. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
7. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
8. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
9. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
10. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
11. The AO (works), O/o PGMTD, Jaipur.
12. The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/03
Work Order date : 23-04-2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement /Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Akera Dunger and Biharipura in Amber block
.Appx route length (in Km) : 8.3 Km
Completion time : 17 days (Seventeen days)
Estimate no. : Yet to be allotted
MB No. : 04
Site incharge : Virender Yadav SDE(NOFN) SHP, Dharam Singh Bargotiya
JTO(NOFN) SHP
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
6. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
7. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
8. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
9. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
10. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
11. The AO (works), O/o PGMTD, Jaipur.
12. The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/04
Work Order date : 14-05-2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement /Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Saiwar and Nangle Tulsidas in Jamwa Ramgarh
block
.Appx route length (in Km) : 15.8 Km
Completion time : 32 days (Thirty two days)
Estimate no. : Yet to be allotted
MB No. : 06
Site incharge : Sh. R.N. Meena SDE(NOFN) Rural Jp, Sh.Dharam Singh Bargotiya
JTO(NOFN) SHP
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
6. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
7. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
8. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
9. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
10. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
11. The AO (works), O/o PGMTD, Jaipur.
12. The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/05
Work Order date : 14-05-2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement /Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Sirohi in Amber block
.Appx route length (in Km) : 2.5 Km
Completion time : 10 days (Ten days)
Estimate no. : Yet to be allotted
MB No. : 07
Site incharge : R.N. Meena SDE(NOFN) Rural JP, Dharam Singh Bargotiya
JTO(NOFN) SHP
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
6. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
7. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
8. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
9. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
10. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
11. The AO (works), O/o PGMTD, Jaipur.
12. The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/06
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Work Order date : 17-05-2018


Contractor Name : M/s Jain Constructions, Dausa
Agreement /Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Indawa and Khemawas in Lalsot block
.Appx route length (in Km) : 2.95 Km
Completion time : 10 days (Ten days)
Estimate no. : Yet to be allotted
MB No. : 09
Site incharge : Sh. Bhojraj saini SDE(NOFN) Dausa, Sh.Virendra Yadav
JTO(NOFN) Dausa
The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
1. The detailed instructions regarding location/works can be obtained from site in charge.
2. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
3. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
4. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
5. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
6. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
7. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
8. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
9. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
10. The AO (works), O/o PGMTD, Jaipur.
11. The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/06
Work Order date : 17-05-2018
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Contractor Name : M/s Jain Constructions, Dausa


Agreement /Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Indawa and Khemawas in Lalsot block
.Appx route length (in Km) : 2.95 Km
Completion time : 10 days (Ten days)
Estimate no. : Yet to be allotted
MB No. : 09
Site incharge : Sh. Bhojraj saini SDE(NOFN) Dausa, Sh.Virendra Yadav
JTO(NOFN) Dausa
The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
12. The detailed instructions regarding location/works can be obtained from site in charge.
13. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
14. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
15. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
16. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
17. a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
18. b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
19. c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
20. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
21. The AO (works), O/o PGMTD, Jaipur.
22. The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/07
Work Order date : 26.06.2018
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Contractor Name : M/s Jain Constructions, Dausa


Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Kela ka Bas and Ramyawala in Jamwa Ramgarh
block
Appx route length (in meter) : 9.1 Km
Completion time : 20 days (Twenty days)
Estimate no. : Yet to be allotted
MB No. : 15
Site incharge : Dharam Singh Bargotiya SDE(NOFN) SHP

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
3) b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The DGM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/08
Work Order date : 16.07.2018
Contractor Name : M/s Jain Constructions, Dausa
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Bhavni and Sankotda in Jamwa Ramgarh block
Appx route length (in meter) : 5.5 Km
Completion time : 15 days (Fifteen days)
Estimate no. : Yet to be allotted
MB No. : 16
Site incharge : Vikrant Yadav SDE OFC CC

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
3) b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The DGM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/09
Work Order date : 19.07.2018
Contractor Name : M/s Jain Constructions, Dausa
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Dwarapura,Kesrisinghpura and Sodala in Bandikui
block
Appx route length (in Km) : 11.6 Km
Completion time : 25 days (Twenty five days)
Estimate no. : Yet to be allotted
MB No. : 17
Site incharge : Sh. Bhojraj saini SDE(NOFN) Dausa, Sh.Umesh Kumar SDE(NOFN)
Dausa
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
3) b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The DGM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/10
Work Order date : 19.07.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-


793&794/NOFN OFC Tender work/ 2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Jalsoo BHQ in Amber block
Appx route length (in meter) : 0.5 Km
Completion time : 7 days ( Seven days)
Estimate no. : Yet to be allotted
MB No. : 18
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

6. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
7. The detailed instructions regarding location/works can be obtained from site in charge.
8. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
9. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
10. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
8) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
9) a) Depth measurement entries of every tenth meter points shall be made in MB by JTO concerned
with signature.
10) b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
11) c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
12) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
13) The AO (works), O/o PGMTD, Jaipur.
14) The DGM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/11
Work Order date : 03.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-


793&794/NOFN OFC Tender work/ 2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Chimanpura & Udawala in Shahpura block
Appx route length (in meter) : 11.1 Km
Completion time : 27 days ( Twenty Seven days)
Estimate no. : Yet to be allotted
MB No. : 19
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/12
Work Order date : 03.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-


793&794/NOFN OFC Tender work/ 2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Bhurabpura & Lali in Jamwa Ramgarh block
Appx route length (in meter) : 9.6 Km
Completion time : 22 days ( Twenty Two days)
Estimate no. : Yet to be allotted
MB No. : 20
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/13
Work Order date : 04.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Approved rate (%) : 25.17% Below BSR of Jaipur


SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Khedi in Bandikui block
Appx route length (in meter) : 2.0 Km
Completion time : 13 days ( Thirteen days)
Estimate no. : Yet to be allotted
MB No. : 21
Site incharge : Sh. Bhojraj saini SDE(NOFN) Dausa, Sh.Umesh Kumar SDE(NOFN)
Dausa
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/14
Work Order date : 14.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Rajawas in Amber Block
Appx route length (in meter) : 6.5 Km
Completion time : 18 days ( Eighteen days)
Estimate no. : Yet to be allotted
MB No. : 22
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/15
Work Order date : 14.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

Approved rate (%) : 25.17% Below BSR of Jaipur


SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Khediki Veerbhan & Molaheda in Kotputli Block
Appx route length (in meter) : 2.7 Km
Completion time : 15 days ( Fifteen days)
Estimate no. : Yet to be allotted
MB No. : 23
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/16
Work Order date : 16.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

You are requested to execute OFC laying and associated works


for the following sites as per survey report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Todi in Shahpura Block
Appx route length (in meter) : 7 Km
Completion time : 18 days (Eighteen days)
Estimate no. : Yet to be allotted
MB No. : 25
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
3) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/17
Work Order date : 16.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

You are requested to execute OFC laying and associated works


for the following sites as per survey report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Kerli & Veer Tejaji Nagar in Virat Nagar Block
Appx route length (in meter) : 11 Km
Completion time : 30 days (Thirty days)
Estimate no. : Yet to be allotted
MB No. : 26
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

6. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
7. The detailed instructions regarding location/works can be obtained from site in charge.
8. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
9. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
10. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
8) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
9) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
10) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
11) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
12) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
13) The AO (works), O/o PGMTD, Jaipur.
14) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/18
Work Order date : 18.08.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

You are requested to execute OFC laying and associated works


for the following sites as per survey report and details given below:-
A End : As per survey
B End : Atal Seva Kendra Bhuranpura in Jamwa Ramgarh Block
Appx route length (in meter) : 4 Km
Completion time : 15 days (Fifteen days)
Estimate no. : Yet to be allotted
MB No. : 27
Site incharge : Sh. Dharam Singh Bargotiya SDE(NOFN) Shahpura.

11. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
12. The detailed instructions regarding location/works can be obtained from site in charge.
13. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
14. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
15. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
15) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
16) Depth measurement entries of every tenth meter points shall be made in MB by JTO/SDE concerned
with signature.
17) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
18) Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
19) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
20) The AO (works), O/o PGMTD, Jaipur.
21) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP/Work order/Zone-II/2018-19/20
Work Order date : 15.10.2018
Contractor Name : M/s Jain Constructions, Dausa
Agreement/Final Acceptance
Letter Number : DGM(Tx)/DE OFC(P&I)/Tech-793&794/NOFN OFC Tender work/
2017-18/55 dated 27.03.18
Validity up to : 20.03.2019
Approved rate (%) : 25.17% Below BSR of Jaipur SSA.
You are requested to execute OFC laying and associated works for the following sites as per survey
report and details given below:-
A End : As per survey ASK Mahangi
B End : Atal Seva Kendra Bhavni in Jamwa Ramgarh block
Appx route length (in meter) : 8.7 Km
Completion time : 25 days (Twenty Five days)
Estimate no. : Yet to be allotted
MB No. : 27
Site incharge : Vikrant Yadav SDE OFC CC

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The survey report is enclosed herewith. The work shall be executed as per approved survey report,
terms and conditions of the tender document and instructions issued by site incharge from time to
time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) a) Depth measurement entries of every tenth meter points shall be made in MB by SDE concerned
with signature.
3) b) Every alternate measurement points shall be cross checked by SDE concerned and entries shall
be signed accordingly.
4) c) Enteries in the hindrance register shall be made from time to time based on prevailing conditions
in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/21
Work Order date : 16.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799&800/Jaipur Jone-1&II/NOFN OFC
Mtce./2018-19/58&59 dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
You are requested to Maintenance the incremental OFC length of GPs working in Zone-I and Zone-II of
Jaipur SSA as per term & condition of the Nofn OFC maintenance tender.quantity of GPs and
incremental length as per A/T report are given bellow:-
Quantity : 372 GPs
Incremental OFC Length : 809.535Kms.
Completion time : 3 Month (90 days)
Estimate no. : Yet to be allotted
MB No. : 28
Site Incharge : Concern SDE of Nofn team of the area
1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your
authorized mail-id. The work shall be executed as per approved, terms and conditions of the tender
document and instructions issued by site incharge from time to time.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1. The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2. The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3. As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to
be attend within time fram as per the term & condition of the NOFN Mtce tender clause.
4. Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing
conditions in the field.
5. Bill of maintenance OF cable is to be submit DE Nofn office every month after all formulties from
field unit for further processing as per the term & condition of the tender.
6. The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
7. The AO (works), O/o PGMTD, Jaipur.
8. The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No. : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/21
Work Order date : 16.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799&800/Jaipur Jone-1&II/NOFN OFC
Mtce./2018-19/58&59 dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
You are requested to Maintenance the incremental OFC length of GPs working in Zone-I and Zone-II of
Jaipur SSA as per term & condition of the Nofn OFC maintenance tender.quantity of GPs and
incremental length as per A/T report are given bellow:-
Quantity : 372 GPs (As per list enclosed)
Incremental OFC Length : 809.535Kms.
Completion time : 3 Month (90 days)
Estimate no. : Yet to be allotted
MB No. : 28
Site Incharge : Sh R N Meena SDE Nofn team (Z-IA) of JP Rural area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC
(Store)” after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from
the date of issuance of work order, whichever is earlier.
4. Do not lay PLB pipe or pull OF cable without checking it by site in charge..
5. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your
authorized mail-id. The work shall be executed as per approved, terms and conditions of the tender
document and instructions issued by site incharge from time to time.
6. Service level agreement (S.L.A.) are to maintain as per clause 12 under schedule A .
7. Resources are to be deployed by the contractor as per Annexure -1

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of
the agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to
be attend within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing
conditions in the field.
5) Bill of maintenance OF cable is to be submit DE Nofn office every month after all formulties from
field unit for further processing as per the term & condition of the tender.
6) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to
NOFN project.
7) The AO (works), O/o PGMTD, Jaipur.
8) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/05
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-I/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IA of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 90 GPs (As per list enclosed) of Block(Bassi,Chaksu,Phagi,Jhotwara,Sanganer)
Incremental OFC Length : 241.231Kms.
Completion time : 1 Year (365days)
Estimate no. : Yet to be allotted
MB No. : 28
Site Incharge : Sh R N Meena SDE NOFN team (Z-IA) of JP Rural area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strctly as per clause under schedule.
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/06
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-1/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IB of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 76 GPs (As per list enclosed) of Block(Dudu,Govindgarh,Sambhar)
Incremental OFC Length : 156.091Kms.
Completion time : 1 Year (365days)
Estimate no. : Yet to be allotted
MB No. : 29
Site Incharge : Sh N.S.Shekhawat JTO NOFN team (Z-IB) of Phulera area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule.
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/07
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-II/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IIA of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 119 GPs (As per list enclosed) of Block(Bandikui,Dausa,Lalsot,Sikrai)
Incremental OFC Length : 251.543Kms.
Completion time : 1 Year (365days)
Estimate no. : Yet to be allotted
MB No. : 30
Site Incharge : Sh Bhojraj Saini and Sh.Umesh Kumar SDE NOFN team (Z-IIA) of Dausa area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be striclty maintained as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/08
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-II/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IIB of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 87 GPs (As per list enclosed) of Block(Amber,Jamwa Ramgarh,Kotputli
Shahpura,Virat Nagar)
Incremental OFC Length : 160.808 Kms.
Completion time : 1 Year (365days)
Estimate no. : Yet to be allotted
MB No. : 31
Site Incharge : Sh Dharam Singh Bargotiya SDE NOFN team (Z-IIB) of Shahpura area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

CORRIGENDUM

It is continuation to the work orders DE (NOFN)/JP /Work order/Incremental OFC/GPs

Mtce/2018-19/05,06,07,08 Dated 17.10.2018 the following modification are hereby done as under:

1. Completion time of work order read as 90 Days instead of 1 year please.

DE (NOFN)
O/o PGMTD, Jaipur

Copy to:-

1) M/s. Alman Telecom Company, Jatiya Bazar , Sikar (Raj).


2) NOFN team SDE/JTO (JP_Rural,Phulera,Dausa,Shahpura)
3) The AO (works), O/o PGMTD, Jaipur.
4) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/05
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-I/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IA of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 90 GPs (As per list enclosed) of Block(Bassi,Chaksu,Phagi,Jhotwara,Sanganer)
Incremental OFC Length : 241.231Kms.
Completion time : 90 Days
Estimate no. : Yet to be allotted
MB No. : 28
Site Incharge : Sh R N Meena SDE NOFN team (Z-IA) of JP Rural area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strctly as per clause under schedule.
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/06
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-1/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IB of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 76 GPs (As per list enclosed) of Block(Dudu,Govindgarh,Sambhar)
Incremental OFC Length : 156.091Kms.
Completion time : 90 Days
Estimate no. : Yet to be allotted
MB No. : 29
Site Incharge : Sh N.S.Shekhawat JTO NOFN team (Z-IB) of Phulera area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule.
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/07
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-II/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IIA of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 119 GPs (As per list enclosed) of Block(Bandikui,Dausa,Lalsot,Sikrai)
Incremental OFC Length : 251.543Kms.
Completion time : 90 Days
Estimate no. : Yet to be allotted
MB No. : 30
Site Incharge : Sh Bhojraj Saini and Sh.Umesh Kumar SDE NOFN team (Z-IIA) of Dausa area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be striclty maintained as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/08
Work Order date : 17.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-II/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Maintenance the incremental OFC length of GPs working in Zone-IIB of Jaipur SSA as per
terms & conditions of the NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T
report given bellow:-
Quantity : 87 GPs (As per list enclosed) of Block(Amber,Jamwa Ramgarh,Kotputli
Shahpura,Virat Nagar)
Incremental OFC Length : 160.808 Kms.
Completion time : 90 Days
Estimate no. : Yet to be allotted
MB No. : 31
Site Incharge : Sh Dharam Singh Bargotiya SDE NOFN team (Z-IIB) of Shahpura area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/10
Work Order date : 18.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-I/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Restoration of existing fault of incremental OF cable in GPs and thereafter maintenance of
route as per S.L.A.of Tender terms and conditions and agreement singed. incremental OFC length of GPs Zone-IA
of Jaipur SSA under NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T report
given bellow:-
Quantity : 43 GPs (As per list enclosed) of Block(Bassi,Chaksu,Phagi,Jhotwara,Sanganer)
Incremental OFC Length : 165.334Kms.
Completion time : 1.5 Month (45days)
Estimate no. : Yet to be allotted
MB No. : 32
Site Incharge : Sh R N Meena SDE NOFN team (Z-IA) of JP Rural area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper
accounting of store materials related to NOFN project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/11
Work Order date : 18.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-1/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Restoration of existing fault of incremental OF cable in GPs and thereafter maintenance of
route as per S.L.A.of Tender terms and conditions and agreement singed. incremental OFC length of GPs Zone-IB
of Jaipur SSA under NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T report
given bellow:-
Quantity : 33 GPs (As per list enclosed) of Block(Dudu,Govindgarh,Sambhar)
Incremental OFC Length : 125.066Kms.
Completion time : 1.5Months (45days)
Estimate no. : Yet to be allotted
MB No. : 33
Site Incharge : Sh N.S.Shekhawat JTO NOFN team (Z-IB) of Phulera area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
4) Proper register of fault record with time and date is to be maintained
by contractor as well as site incharge,Enteries in the hindrance register shall be made from time to time based
on prevailing conditions in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/12
Work Order date : 18.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-1/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Restoration of existing fault of incremental OF cable in GPs and thereafter maintenance of
route as per S.L.A.of Tender terms and conditions and agreement singed. incremental OFC length of GPs Zone-IIA
of Jaipur SSA under NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T report
given bellow:-
Quantity : 39 GPs (As per list enclosed) of Block(Bandikui,Dausa,Lalsot,sikrai)
Incremental OFC Length : 131.641 Kms.
Completion time : 1.5Months (45days)
Estimate no. : Yet to be allotted
MB No. : 34
Site Incharge : Sh Bhojraj Saini and Sh.Umesh Kumar SDE NOFN team (Z-IIA) of Dausa area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per T&C clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
4) Proper register of fault record with time and date is to be maintained
by contractor as well as site incharge,Enteries in the hindrance register shall be made from time to time based
on prevailing conditions in the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

WORK ORDER
Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/13
Work Order date : 18.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-800/Jaipur Zone-1/NOFN OFC Mtce./2018-19/59
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Restoration of existing fault of incremental OF cable in GPs and thereafter maintenance of
route as per S.L.A.of Tender terms and conditions and agreement singed. incremental OFC length of GPs Zone-IIB
of Jaipur SSA under NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T report
given bellow:-
Quantity : 55 GPs (As per list enclosed) of Block(Amber,Jamwa
Ramgarh,Kotputli,Shahpura,Virat Nagar)
Incremental OFC Length : 164.326 Kms.
Completion time : 1.5Months (45days)
Estimate no. : Yet to be allotted
MB No. : 35
Site Incharge : Sh Dharam Singh Bargotiya SDE NOFN team (Z-IIB) of Shahpura area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per T&C and clause of schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
1) The Site in charge with the instructions that work shall be supervised as per terms & conditions of the
agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
3) As soon as OFC fault complaint is received by the contractor fault of
incremental OF cable GP is to be attend within time fram as per the term & condition of the NOFN Mtce
tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.

No.-DE (NOFN)/JP/WO/Incremental OFc/GPs Mtce./2018-19/ Dated : 13-11-2018

To,
M/s.Alman Telecom Company,
Jatiya Bazar Sikar(Raj.)

Sub.-Regarding OFC Maintenance work order non compliance.


Ref. WO no.DE(NOFN)/JP/WO/incremental OFC/GPs Mtce/2018-19/5,6,7,8 dated 17.10.2018

In the above cited subject and reference letter four work orders were issued to your firm on dated
17.10.2018 for Nofn GPs (372Nos) incremental OFC maintenance purpose as per the tender approval
letter no.GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-1/NOFN OFC Mtce/2018-19/58 dated
05,10.2018 and GM(Tx) /DE OFC(P&I)/Tech-800/Jaipur Zone-1I/NOFN OFC Mtce/2018-19/59 dated
05.10.2018 but as per field report you have not provided Man Power and Mtce team for maintenance the
372GPs till now. Although daily pending fault detail of GPs are being send/emailed to you on given id
almantelecomcompany47@gmail.com, but no one Mtce team deployed/provided against above work
order till date and fault are not been attended by maintenance team, even after passing more than
20days.GPs fault are increasing day by day due to not attending/maintaining on daily basis,list of 372
GPs given in WO and no one GP fiber fault removed and update till date above.
As per clause Schedule A(d) rectification of fiber /OF cable cut faults made over by bsnl officer
to the vendor/tenderer must be rectified the fault within MOU time period otherwise penalty will be
imposed as per terms & conditions of MOU signed between BSNL & BBNL as per schedule-A terms &
conditions of the tender each team must having OTDR-1,Splicing machine-1,Fiber cleaver-1,Power
meter-1,Vehicle/splicing Van-1,Motorcycle-2,
Availability of Man power in Jaipur SSA as per MOU Labour-08Nos, Patroller / visitor for OF
routes/ASK-08Nos,Splicer Man-4Nos must be maintained so that fault can be rectified on timely, as per
NMS latest fault report is more than 100 GPs fault are pending and these faults are being monitoring on
higher level on daily basis,worthy CGMT sir taking very seriously higher GPs fault issue in Jaipur SSA.
Therefore you are requested please restore the GPs/incremental fiber faults immediately by
providing/engaging Man power as soon as fault received on your mail id within time period of 8Hrs and
update daily basis on evening so that any penalty can be avoided and strictly follow the terms &
conditions of the tender signed SLA please.

Divisional Engineer (NOFN)


O/o PGMTD Jaipur.
Copy to:
1.GM(Tx) O/o PGMTD Jaipur for information please.
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715

WORK ORDER Period ExtensionSubject


Work Order No : DE (NOFN)/JP /Work order/Incremental OFC/GPs Mtce/2018-19/10
Work Order date : 18.10.2018
Contractor Name : M/s. Aalman Telecom Company, Jatiya Bazar , Sikar (Raj).
Agreement/Final Acceptance
Letter Number : GM(Tx)/DE OFC(P&I)/Tech-799/Jaipur Zone-I/NOFN OFC Mtce./2018-19/58
dated 05.10.2018
Validity up to : 04.10.2020
Approved rate (%) : 27.86% Below BSR of Jaipur SSA.
Scope of contract to Restoration of existing fault of incremental OF cable in GPs and thereafter maintenance of
route as per S.L.A.of Tender terms and conditions and agreement singed. incremental OFC length of GPs Zone-IA
of Jaipur SSA under NOFN OFC maintenance tender. Quantity of GPs and incremental length are as per A/T report
given bellow:-
Quantity : 43 GPs (As per list enclosed) of Block(Bassi,Chaksu,Phagi,Jhotwara,Sanganer)
Incremental OFC Length : 165.334Kms.
Completion time : 1.5 Month (45days)
Estimate no. : Yet to be allotted
MB No. : 32
Site Incharge : Sh R N Meena SDE NOFN team (Z-IA) of JP Rural area

1. The material will be issued to you or your authorized representative by store in charge “SDE OFC (Store)”
after receipt of requisition through site in charge.
2. The detailed instructions regarding location/works can be obtained from site in charge.
3. Date of commencement of work means the date of actual commencement of work or 7 th day from the date of
issuance of work order, whichever is earlier.
4. The incremental OFC length detail /L-14 diagramm of GPs soft copy has been sent you on your authorized
mail-id. The work shall be executed as per approved, terms and conditions of the tender document and
instructions issued by site incharge from time to time.
5. Service level agreement (S.L.A.) are to be maintained strictly as per clause under schedule .
6. Resources are to be deployed by the contractor as per Annexure -1
7. Billing cycle Monthly - Bill of maintenance OF cable is to be submit DE Nofn office every month after all
formalities from field unit for further processing as per the term & condition of the tender.
8. All terms and conditions are as per Tender documents and agreement signed on dated 05-10-2018.

DE (NOFN)
O/o PGMTD, Jaipur
Copy to:-
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
1) The Site in charge with the instructions that work shall be supervised
as per terms & conditions of the agreement made with contractor.
2) The detail of faulty incremental OFC occurred of GPs will be obtained from NMS and concern site
incharge and record is to be maintained in register.
3) As soon as OFC fault complaint is received by the contractor fault of incremental OF cable GP is to be attend
within time fram as per the term & condition of the NOFN Mtce tender clause.
4) Proper register of fault record with time and date is to be maintained by contractor as well as site
incharge,Enteries in the hindrance register shall be made from time to time based on prevailing conditions in
the field.
5) The SDE OFC (Store), O/o PGMTD, Jaipur. Pl keep proper accounting of store materials related to NOFN
project.
6) The AO (works), O/o PGMTD, Jaipur.
7) The GM (Tx), O/o PGMTD, Jaipur for kind information please.
8)
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
Transmission Wing,Bhawan, Lal Kothi,,Jaipur–302015
116, Door Sanchar
Jaipur Telecom District,
116, Door Sanchar Bhawan, Lal Kothi,,Jaipur–302015
Tel : 0141-2743764, Fax: 2740715
9)

You might also like