Name Of Agency:- Kaenat Glass Agencies Date:-
Name Of Project:- DLF Mid Town Plaza, Moti Nagar WIR NO:-
Location & Grid:- Quantity:-
KGA Representatie DLF Representative Remarks
Si No Description
YES NO NA YES NO NA
1 Check MIR Approval Prior to Fabrication
Check Fabrication of J Bolt Component done as per
2
GFC Drawing
3 Check the position of J Bolt as per GFC Drawing
4
Check the quality of welded joints are visually OK
Check the alignment and level of J Bolt after
5
installation
6
Check the J Bolt free from any physical damages
7 Check welded joints are grinded smoothly
Si No Remarks