Kuwait Integrated Petroleum Industries Company
A Subsid iary of Kuwait Petroleum Co rporation

TEMPORARY PIPING/ HOSE CONNECTIONS


PROCEDURE

KUWAIT INTEGRATED PETROLEUM INDUSTRIES COMPANY


(KIPIC)
AL-ZOUR REFINERY, KUWAIT
o..lofil.o.J I <4J g;l+J I w l.cl.l.c..U a,µig111 o.5_µ1,J I

KIPIC
a.1..o l!u..o-1 I O+.,l g)-1..!.J I
~g...5...JI J g_µ.µI o....w....w~ ulSJ.-W u >....:)!
Kuwait Integrated Petroleum Industries Company
A Subsid iary of Kuwait Petroleum Corporation

KUWAIT INTEGRATED PETROLEUM INDUSTRIES COMPANY

DOCUMENT TITLE TEMPORARY PIPING / HOSE CONNECTIONS PROCEDURE

DOCUMENT No. KIPIC/MAINT/MM/18/P004

REVISION No. 0

ISSUE DATE 29th. MARCH 2018

LATEST REVISION DATE: 29th. MARCH 2023

VALIDITY FIVE YEARS FROM ISSUE DATE OR UNTIL REVISED

CONFIDENTIALITY

The information contained in this document is confidential to Kuwait Integrated Petroleum Industries Company.
Accordingly, copyright for this document is retained with KIPIC and no copying in any format of this document is
permitted without a written permission from KIPIC - Management.

Signatories

Author Mohammad AlamDar - Snr. Mechanical


Abdullah M Al Jazzaf - Eng.Mechanical Maint.

Reviewed by : Ahmed AI-Khaldi


JOB TITLE TL, Mechanical Maintenance Team

Approved by :
JOB TITLE

• -.......;::)dlll---===~--#--· irf+
Mohammed Mansour AI-Ajmi Ali Mohammed AI-Ajmi
Manager, Maintenance Group, AI-Zour Refinery Manager, Operation Group, AI-Zour Refinery

These signatures apply to the entire document


iil.ofil.o.J I 0.,!)gj.i.+J I .::, 1.. :1.ic.l.J 0,µ1~ I o.!>j-WJ I

KIPIC
a.Lo l.!u.o.J I ii.!,-1 gJ-i.!.J I
~ µ . J I Jg.J...l.+JI o....w....w,;µ, wlSJ-W ,p....:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

Revision History

Draft for internal review


of the Temporary Piping Mohammed AlamDar
A 28/ 12/2017 Ahmed AI-Khaldi Mohammed AI-Ajmi
/ Hose Connections Ahmed Makhlouf
Procedure

Mohammed AlamDar
First issue of the Abdullah M AI-Jazzaf Ahmed AI-Khaldi Mohammed AI-Ajmi
0 Temporary Piping /
29/ 03/2018
Hose Connections
Procedure
1

Distribution of Controlled Copies

To be i

Master Copy

1 DCEO-AI Zour Refinery

2 MANAGERS

Document Change Log Table

Page
Rev. No. Description of Amendment Approved by Effective Date
No.

Original Temporary Piping/


0 Manager, Maint. AI-Zour Refinery 29/03/2018
Hose Connections Procedure
o.J..olilo.J I <4Jg>4J I u Lcl.i.a.U <4l.!,;µJ I ~J-W-1 I

KIPIC
a.Lo~I a..!,,lg.J-4J I
a...µ...Jg...5..JI Jg_µ....µI Q...W..JJ.Jg._.o ulSJ-.W <.S~!
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

TABLE OF CONTENTS

SI. NO. DESCRIPTION PAGE

1.0 PURPOSE 4

2.0 CUSTODIAN 4

3.0 REVISION 4

4.0 DEFINITIONS 4

5.0 REFERENCE 5

6.0 SCOPE 5

7.0 EXCEPTIONS FROM THE PROCEDURE 6

8.0 TEMPORARY CONNECTION PROCEDURE FOR HANDLING 8


UTILITIES (AS PER# 6.1)
9.0 TEMPORARY CONNECTION PROCEDURE FOR HANDLING 9
PROCESS ITEMS (AS PER # 6.2)
10.0 GUIDELINES FOR TEMPORARY CONNECTIONS 11

11.0 RESPONSIBILITY CHART 13

12.0 RACI CHART 14

13.0 TRAINING 15

14.0 PERIODICAL AUDITING 15

15.0 APPENDIX-A - TEMPORARY CONNECTION REQUEST FOR 16


UTILITIES

16.0 APPENDIX-B - TEMPORARY CONNECTION REQUEST FOR 17


PROCESS ITEMS
17.0 GENERAL CONDITIONS AND GUIDELINES 18

18.0 CHECKLIST FOR MAINTENANCE PERSONNEL 19


oJ..o lll.o.J I o.,µgJ4.1 I uu:Lu:ill 0,µ,1,p.J I ~_µWI

KIPIC
a.Lo l!u.o.J I 0./,J gJJ:..µ I
CL,!-:i...i<;µ..J I Jg,-4..J I 6....w....wsµ, u lSJ-W ._s:,._:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corpora ti on

1.0 PURPOSE

The purpose of this procedure is to ensure safety of personal / equipment while making
temporary pipe / hose connection in a Refinery. This procedure is mandatory to:

a. Establish the necessary requirements to ensure that the connection can be made safely.
b. Ensure that the connection will not violate any of the Refinery safety and environmental
parameter limits.
c. Provide a record and control of such connections.

2.0 CUSTODIAN

The custodian of this procedure shall be Team Leader Mechanical Maintenance


Al-Zour Refinery and shall be responsible for any future updating of the procedure.

3.0 REVISION

This procedure is to be revised every 5 years , unless situation demands early


rev1s10n.

4.0 DEFINITIONS

Temporary Piping Connection:


Metallic piping / tubing / hose & rubber hoses / prefabricated pipe assemblies provided between
piping / equipment temporarily for a maximum of 30 Calendar Days, which may be extended
by another 15 days on request from Section Head, Operations with due risk assessment.

Temporary Piping:

Metallic piping / tubing / hoses & rubber hoses / prefabricated pipe assemblies including their
combinations that are generally used in the Refinery.

Prefabricated piping assemblies:

Manifolds, piping assemblies which have been fabricated according to the standard engineering
practice and have Standard I&C valid acceptance for use.
Plant Modification Procedure / MOC:

Procedure followed in a Refinery for providing new facilities/ modifying existing facilities
permanently. Any temporary connection that is required for more than 30 Calendar
days shall be subjected to Plant Modification Procedure / Management of Change
(MOC).
oJ.o~I 0,!-19J4ll wld.lz:>.l.l a,w~I ~_µWI

KIPIC
cU.o l!u...o.J I ~ gJ-L!-11
0...,!-1...iµ.JI JgJ-1-+J I 6-..u.u.u~ wlSJ---W ,s>....:>J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

5.0 REFERENCE
The following procedures should be referred to in conjunctions with this procedure:

• Procedure for Utility Station Hoses Care & Maintenance Document


NumberKIPIC / MAINT / MM / l 8/ P008.
• Procedure followed in a Refinery for "Plant Modification works".

6.0 SCOPE

The procedure is applicable to all such temporary connections where operating pressure is
not more than 150 psig (10.54 Kgs/Cm2) and temperature not more than 375°F (190 °C).

In general, the temporary connection shall be provided for a maximum of 30 calendar days.
This time limit shall be waived on a request from Section Head Operations, and with due
risk assessment carried out (If required). The temporary connection may be retained for a
maximum of another 15 days. Beyond this time period, the existing Plant modification
procedure shall be applicable.
The scope of temporary connection shall be divided in to the two following categories

a. Temporary pipe / hose connection for handling utilities.


b. Temporary pipe / hose connection for handling process items.
The temporary connections for utilities shall be limited to a maximum size of 4" pipes / hoses.
In case of process connection, the size shall be clearly defined in the risk assessment.

6.1 TEMPORARY PIPE / HOSES CONNECTIONS FOR HANDLING UTILITIES:


a . Utility stations to Process equipment
b. Process equipment to drains for draining / Venting of utilities.
The utilities that are covered under this category are-

• Low pressure steam - maximum header pressure of 60 psig (4.21 kgs/Cm2)

• Medium pressure steam-maximum header pressure of 150 psig (i.e. 10.54 kgs /Cm2).

• Plant air - maximum header pressure of 110 psig (7. 73 Kgs/Cm2}

• Utility water-maximum header pressure of 110 psig (7.73 Kgs/Cm2)

• Cooling water - maximum header pressure of 110 psig (7,73 Kgs/Cm2

• Nitrogen Connection from Trailer with a pressure regulator below 150 Psig
to be included.
cil.ofil.o.J I i:4Jgj4.J I u ld..i.=-U ~<;µJI ~_µWI

KIPIC
fil..ol1i..o..JI 0-/,Jg)-i.!.J I
o...,µ....i g...5...J I Jg.J--1...µI 0....U.L...Wg....o uts_µ.t, --s~ !
Kuwalt Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleu m Corporation

These temporary connections are generally used for steam flushing / water flushing / draining
/ gas freeing / cooling / ventilating a confined space / purging while handing over / during
shutdown / commissioning ofprocess equipment.
Check if the connection requires risk assessment or not and if required then the risk assessment
shall be carried out by Section Head, Operations and the report shall be attached with the
request.

6.2 TEMPORARY PIPE / HOSES CONNECTIONS FOR HANDLING PROCESS


ITEMS:

• Process equipment to Process Equipment not under operation


• Process equipment to drains
• Process equipment to Skid mounted equipment & vice versa
• Draining of battery limit lines
• Transfer of chemical to process equipment
• Connection from Cylinder (Ammonia, Chlorine etc. ,)
• Connection from sump / equipment / pipes to slop line using temporary pump

These temporary connections are generally used for draining of hydrocarbons / process
items other than the utilities listed in 4 .1 , transferring of material from process equipment to
process equipment / skid mounted equipment and handling of chemicals, the risk assessment for
process line shall be carried out as per KIPIC SWP on Work Permit Risk Assessment Doc.#
HSC-TSSA-06-2029, by the Section Head, Operations and the copy shall be attached with the
request

7.0 EXCEPTIONS FROM THE PROCEDURE

The following is a list of typical connections that are excluded from the Procedure for
temporary pipe/ hose connections and covered by its own systems / procedures:
• To and from process equipment under operation; Plant modification procedure
is to be followed for providing any temporary connection between equipment
under operation.
• Connections to the fire water system: These are covered by the procedure of SHE
Department.
• Potable water system: No connection shall be allowed between potable water system
and any other system.
• Plant air not to be connected with the BA Sets (Breathing Apparatus).
• Nitrogen connection from trailers with bypassing regulators where pressure exceeds
150 psig (10.54 Kgs/Crn2)
iil.ot!u.o.JI a,µg;4JI ul<=li.o.lJ o,µi~I ~;.w..11

KIPIC
ii.1..olii.o..JI ~g}-1.+JI
C>..,!-l..,i~I Jg.J.-l..+.JI ii...w...u.Jg....o ui'.>J----W ,p....:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary o f Kuwait Petrol eum Corporation

• Air hose connections for Exhaust fans / Ejectors (Used for equipment ventilation)
I Buffing machines/ Jack Hammers / and for on-stream leak sealing activities.
• Water hosed connections for filling water in the pipe lines / Equipment during hydro
test.
• Pipe I hose connection for de-plugging of any process system.

7.1 Temporary hose connections taken for miscellaneous activities other than process
equipment such as
• For putting off fire by using water / steam hoses
• For providing standby steam water hoses during welding activities and hot works.
• For providing blanketing during flange / gland leaks and smoking, mechanical
seal leaks, insulation smoking to prevent fire. To be regularized within 24 hours by
the temporary pipe I hose connections procedure.
• For general maintenance activities by maintenance crew such as cleaning of filters /
strainers / burners / steam traps / general washing of equipment components & floors etc.
• For carrying out hydro test of piping / equipment, as the pressure may exceed 150
psig (10.54 Kgs/Cm2].
o..Lo liloJ I i4)gJ41 I ul.cU=.U Q,!i.,i~ I o.5J.,WJI

KIPIC
o.J....ol.!u..o.JI 0./,.lgJ-4.l I
~g...5...JI Jg;..J....,.JI 6-w....wg....o ulSJ..-W ,p•..:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

8.0 TEMPORARY CONNECTION PROCEDURE FOR HANDLING UTILITIES


(As per# 6.1)
SR# JOB RESPONSIBILITY

Operation Supervisor should initiate the request by raising ''Temporary Connection


8.1 Operations Supervisor
Request'' for UtiLities. The fonnat is enclosed as Appendix -A
Temporary connection request for utilities shall be of white color with a unique serial
number (as a part of controlled documents procedure, fonnat should be given a serial
8.2 All Concerned
number (xxxx) and shall have 2 copies. The original shall be with the executor, the
first copy with issuer and the second copy for safety.
The Issuer shall fill the necessary requirements in Section 1,2 & 3 and clearly Operation
8.3 indicating the duration of temporary connection in Section 4. B. Supervisor
The temporary connection shall be started only after the request is duly signed by Operation / Maintenance
8.4 both issuer & checked by respective area operator (section 4B) Supervisor
The Maintenance Supervisor shall drop the second copy of the temporary
connection request in theSafety box Maintenance
8.5
available at the Operation shelter / CCR. Supervisor

The job shall be executed by the Maintenance Supervisor as per the set procedure
and guidelines. A checklist is also provided on the back of the temporary Maintenance
8.6
connection request for Maintenance Supervisors reference. Supervisor

The Area Maintenance Engineer / Safety Engineer / Shift Safety Engineer Area I Shift Safety Engineer &
assigned to operations, shall periodically (decide the audit frequency) audit the Area
8.7
temporary connection request and the execution of connections. Maintenance
Engineer
The temporary connection request copy shall be retained by the issuer and
the executor in a separate box file called "on going temporary connection", Operation / Maintenance
8.8
until the connection removed and then kept in "closed temporary connection" file. Supervisor

Temporary connection to be removed after completion of work or before the due date
whichever is earlier, after obtaining approval from Operation Supervisor using the Operation / Maintenance
8.9
same copies (section 5). Supervisor

Section4.C has provision for allowing an extension of the connection for a maximum Section Head
period of 15 days, provided it is approved by the Section head, Operation by canying /Operations/
8.10
outriskassessment (lfrequired) Maintenance
Supervisor
Afterremovalofthetemporaryconnection, the temporary connection request (issuer
& executor copy) shall be duly closed by issuer and executorlteemtris responsible
Operation / Maintenance
8.11 for restoring the site back to nonnal conditions as prior to making a temporary
Supervisor
connection, such as providing caps/boiler makers etc.

Copies of the closed request shall be filled and


kept for one month (After removal ofTemporaryconnections), by both Operations Operation / Maintenance
8.12
and Maintenance Supervisors for future records and reference. Supervisor

It is the responsibility ofthe Unit Section head / Maintenance Engineer to ensure Unit Section Head /
8.13 that no temporary connections are available beyond the maximum allowed Maintenance
duration. Engineer
cil.olilo.J I ci.J.J 9;4.II u l<:U=JJ o.A!,;µ.)I ~_µWI

KIPIC
a...Lo l!u..oJ I 0./,-1 g)-l.µ I
6...,;..l.ig...5...JI Jg;..J....;.JI o....w....wµ
Kuwait Integrated Petroleum Industries Company
A Subsidiary o f Kuwait Petroleum Corporation
ulSJ-W -5:,..;,J

9.0 TEMPORARY CONNECTION PROCEDURE FOR HANDLING PROCESS


ITEMS (As per# 6. 2)
Operations Supeivisorshould initiatetherequestby raising"TemporaiyConnection Request" for
Operations Supervisor/
ACll$ The temporruy Connection requ:s:9"'0111:e~~Section Head. The format is
9.1 Section Head / Shift
enclosed as Appendix-B.
Controller
Beyond normal working hours, the request shall be approved by Shift Controller.
The temporaiy connection request for process shall be of yellow color with a unique serial
number (As a part of controlled document procedure, format should be given a Serial
9.2
number -xxxx) and shall have 2 copies. The original shall be with the executor, the fut copy
All Concerned
with issuer and the second copy for Safety.

9.3 The Issuer shall fill the necessary requirements in Section 1,2 and 3, and clearly indicate Operation
the duration oftemporaiy connection in Section 4. B Supervisor
The Unit Section Head shall call for a Risk Assessment(lf Required) to be done prior to
execution of the connection. Based on the criticality of requirement, other
services department Engineers shall be called for Risk Assessment.

9.4 Beyond normal working hours, Shift Controllersha l I conduct the Risk Asses s ment Unit Section Head / Shift
(If Required) with the Shift Safety Engineer and Operations & Maintenance Supervisor. Controller

The same shall be regularized by the Section Head / Maintenance Engineer on the next working
day.
Unit Process Engi neer shal l provide the required process data if any requested by th e Section Unit Process
9.5 Head Engineer
Operations Supervisor/
The temporaiy connection shall be started only after the request is duly signed by both issuer, and Section Head/
9.6
executor. (Section 4) Maintenance
Supervisor

The Maintenance Supervisor shall drop the seco nd copy of th e temporary co nn ection request in Maintenance
9.7 th e Safety box avai lab le at th e Operation shelter / CC R. Supervisor

The job shall be executed by the Maintenance Supervisor as per the set procedures and
guidelines. A checklist is also provided on the back of the temporary connection req uest Maintenance
9.8
for Maintenance Supervisors reference. Supervisor

Area / Shift
The Area Maintenance Engineer / Safety Engi neer / Shift Safety Engineer ass igned to Safety
9.9 operation s, shall periodicall y (decide the audit frequency) audit the temporary connection Engineer & Area
request and th e exec ution of co nn ectio n. Maintenance
Emnneer
Operations/
The temporruy connection request copy shall be retained in a separate box file by the issuer
9.10 Maintenance
and the executors until the connection are removed.
Supervisor
The temporruy connection to be removed after completion of work or before the due date
Operations /
whichever is earlier, after obtaining approval from Operations Supervisor using the same
9.11 Maintenance
copies (section 5).
Supervisor

Section 4.cms puvisioo for allowing an extension of the connection for a period of 15 days,
9.12 Section Head
provided it is approved by Section Head, Operations.
cil.otil.c>J I <4JgJJ.+.II wl.cll=l.l ~~I <>5.)-WJI

KIPIC
a.Loli:i..o.JI 0./,-lg)-i.!JI
6...,f...i...ig...1.JI JgJ..l.+JI 0..J.il..il.liµ, wlSJ..W ..5:i....:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

After removal of the temporruy connection, the temporary connection request ( ~ & executor
Operations/
copy) shall be duly closed by issuer adem.i:rSectioo-5fire.m.t:ris responsible for restoring the
9.13 Maintenance
site back to normal conditions as prior to making a temporruy connection. such as providing
Supervisor
caps / boiler makers etc.

Copies of the closed form shall be filed and kept for one month (from the date of removal of Operations /
9.14 connections), by both Operations and Maintenance
Maintenance Supervisors fir future records and reference. Supervisor
Unit Section
It is the responsibility of the Unit Section head / Maintenance Engineer to ensure that no Head
9.15
temporary connection is available beyond the maximum allowed duration. /Maintenance
Engineer
iil.ofilDJ I ",f.19J:i+J I .::, ld..i.o.JJ ",!1,!~ I ~;.w.l I

KIPIC
OJ..o l.ii.o.J I Q./,.1 g}-L!-11
o..+-l-,!g....1...)IJ9)-..1...+..J l o.....w...w~ulSJ...W...s>-...:>J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

10.0 GUIDELINES FOR TEMPORARY CONNECTIONS:

Plant and Personnel safety are of utmost importance while carrying out any temporary
connection in the Refinery. Some of the precautions and guidelines to be taken while executing
the temporary connections are listed below: -

• All temporary connection shall be provided only for a maximum of 30 calendar days.
Any Extension beyond the 30 days must be requested by the Section Head, with due
risk Assessment exercise (If Required). The extension can be provided for a maximum of
15 days Any extension beyond this shall be subject to Plant Modification Procedure

• No temporary connection shall be provided from Process equipment under


operation (i.e._ running equipment].

• Temporary connection shall be provided only where operating pressure is up to 150


psig (10.54 Kgs/Cm2) and temperature is up to 375° F. (190.5' C)

• Flexible hoses used for temporary pipe connection should comply with the "Procedure
for Utility stations and hoses care and maintenaoce".

• It should be ensured that valve on either side (Process and utility side) are closed prior to
making the temporary connections.

• All flanged connections to be completely bolted and tightened even though the connection is
temporary.

• All temporary connection should be properly supported adequately enough to prevent


accidental movement or vibrations due to hammering_ The adequacy of the supports
shall be confinned by the Maintenance Engineer.
• The temporary connection should be properly inspected by the Maintenance Supervisor
I Engineer prior to its first use and should be periodically inspected (visual) once in a week,
to confirm its healthy condition when the connection is to be in use for long periods up
to 30 days. A check list is provided for guidance on the back of the temporary
connection request.

• Operations and Maintenance personnel shall follow all the safety precautions required,
depending upon the purpose for which the temporary connection is made. i.e. by not
over-pressurizing the line /not over-heating the line / avoiding hammering on steam service /
avoiding corrosiveness of material etc.

• Flexible hose is vulnerable for failure at road crossing and inside battery limit due to vehicle
movement. Therefore, the hoses must be property protected at these locations.
a.l.Dlil<>.II ",!lg;4J I u L<:U=.U o.,µ,i 1¢.JI a.!>J.,IW I

KIPIC
a...Lo ~ I a.i,.lgJ-4.l I
<4-1-.!g...!i...JI Jgµ.µ! o....w...wg...o utS_µi, ,p. ..:,J
Kuwa it Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

• All temporary utility connections to other systems must be equipped with positive isolation
devices and a check valve with bleeders between block valves & check valve (Positive
isolation devices arrangement can be done as per job requirement)

• For Nitrogen services the upstream block valve should be globe valve.

• Prefabricated connection manifolds as above should be kept in all process units and offsite
facilities. The service test has to be done for the prefabricated manifolds to ensure that
there is no passing.

• Electrical Safety aspects (bonding or earthing) to be taken care during risk assessment

• The simplified sketch below shows the minimum requirements for a temporary connection
(For Ex.)

Utility Side Process Side

--N-----
cilDl!u.AJI a,µgJ4JI wldl.c.J.J ~~I c:.5,ili.11

KIPIC
a.Lo lil.a.J I a..1,-1 gJ-4.J I
C>....,!--.1.,ig...5..JI Jg_µ...µI CL.W...i.U~ .::.15;....w ,p....:,J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

11.0 RESPONSIBILITY CHART:

BUSINESS PROCESS: PROCEDURE FOR TEMPORARY PIPE/ HOSE CONNECTION

Responsible
Individual Stan or End
<> Decision Task Control Point

Operations Provide Inputs/


Need for
Supervisor Details Required for
Connection
Connections

NO

Drop NO C.onduc:t
Section Head /
Temporary Risk
Shift Controller
Connection
YES

Remove YfS
Execute the
Connection i.------'1'-----__,J
Connection

Maintenance
Supervisor NO

YES

NO
o.J.olilo.J I <4)gJ4.11 uu:li=JJ o.A!~I ~_>.WJI

KIPIC
a..Lo l.!u..o.J I a.i,J g}-L+.J I
ii...,;..1..ig...5...JI Jg_j..J....µI a....w....wg...o ulSJ..-W <5>....:>J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

12.0 RACI CHART


12.1 RACI CHART for Temporary Piping/ Hose Connections Procedure
Title

Section
TASKS
Team Safety
Process Head Sup. Supv.
Leaders
Engrs Engr. /Shift (Maint.) (Op.)
Maint.
Controller

IDENTIFICAT ION OF
C C A 1 R
CONNECTION NEEDS

PROVIDING THE C C A R R
REQUIRED
RISK ASSESSMENT I C C R R C

EXTE SION C C A C R

EXECUTING THE
I I I R R
CONNECTION

REMOVAL OF I I I R R
CONNECTION
MAINTA INING I I R R
RECORDS
CONDUCTING R R A I
TRAINING
AUDIT I C R A I I
REVIEW OF R C C C
PROCEDURE

RACI " Responsible, Accountable, Consulted and Informed"


LEGEND:
R: RESPONSIBLE A : ACCOUNTABLE C: CONSUL TED I: INFORMED
o..LolllAJ I o,i.lg;J.+JI u Lcu.oJJ <41.!~I ~_µWI

KIPIC
a.Lo liX..o.J I 0./,J g_µ+J I
6....i-J.-.!g...1..)1 Jg_µ...µI 6..J.u...;.uc;µ:, ulSJ----W ._s=>-:>J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

13.0 TRAINING
All personnel involved shall be provided with training regarding the procedure before
implementation of the same. The following topics shall be prime aspects which shall be
covered in the training program:

• Clear definition of the scope of this procedure.


• Exclusions from the procedure.
• Roles and connection procedure for utilities and process.
• Temporary connection procedure for utilities and process.
• General guidelines for providing connections.
• Hazards ofhoses and hose connection.

14.0 PERIODICAL AUDITING


Periodical audits shall be carried out by "Management/Team Leaders/ Sr. Engineers"
to ensure "Temporary piping I Hose Connections Procedure" has been followed and
the objective of the procedure has been achieved.
ii.Lo liloJ I <4,lg.J411 uu:Lu:ill ci.,w~I ~_µWI

KIPIC
a...Lo~I o.-1,JgJ-l-!.JI
6...,!...l...ig...1.J I Jg_)..l..µI o...J.JJ..;JJ9-0 ul5.J--.W ..s~J
Kuwait Integrated Petroleum Industries Company
A Subsidia ry of Ku wait Petroleum Corporation

15.0 Appendix-A - TEMPORARY CONNECTION REQUEST FOR UTILITIES

TEMPORARY CONNECTION REQUEST ...·•:• KIPIC KUWAIT INTEGRATED PETROLEUM INDUSTRIES COMPANY
FOR UTILITIES -=, ~g;.u.11 {KIPIC)

1 Exact Location:
D Refinery • LNG D Petrochemical
(Area/ Section/ Unit/ Train/ etc)
2 A. Description pf Work {From - To, Attach sketch if required) :
........................................................................................................................................................................................
....................................................................................................................... Using {Flexible Hose/ Metalic Piping)
B. Purpose of Installation: ..................................................................................................................................

3 Details of Connection:
From (Service) ............. Max operating condition : Pressure in Psig ......... . Temp in °F.........
To (Service) .................. Max operating condition : Pressure in Psig .......... Temp in °F.........
4 A. Issued to (Department/ Division/ Contractor)
.....................................................................................................................................................................................
B. Authorization for initial execution: It is safe to proceed with the connection
Is Risk Assessment required? Yes/ No {If yes, attach Risk Assessment report from Section Head Operations)
From (Date) ....................... To (Date)
Issuer (Supervisor, Operations): Signature ............. Name ................ Emp No .......... Date ............. .
Executor (Supervisor, Maintenance) : Signature ....... Name ....... Emp No .......... Date ..............
C. Authorization for extension
(Attach Risk Assessment report from Section Head Operations)
From (Date) ....................... To (Date)
Issuer (Supervisor, Operations): Signature ............. Name ................ Emp No .......... Date ..............
Approver (Section Head/ ZSC. Operations): Signature ....... Name ....... Emp No ......... . Date ..............
5 Authorization for Closure
The temporary connection is no more required and can be removed.
Issuer (Supervisor, Operations) : Signature ............. Name ................ Emp No ......... . Date ..............
The temporary connection has been removed and conditions are restored to normal
Executor (Supervisor, Maintenance) : Signature ....... Name ....... Emp No .......... Date ............. .
Issuer (Supervisor, Operations): Signature ............ . Name ................ Emp No .......... Date ..............
Origi na I: Executor. First Copy: Issuer, Second Copy: Safety DIAL "_ " IN CASE OF ANY EMERGENCY
o.l.o~I <4)gJ411 wldl=l.J ~~I ~..,i,JI

KIPIC
ii.Lo lii.o...J I a.i,..J gj-1.µ I
6...!----1-19--1-11 Jgµ....µ I 6...J..u....w (µ, wlSJ---.W -5:,__:,J
Kuwait Integrated Petroleum Industries Company
A Subsi d iary of Kuwa it Petroleum Corporation

16.0 Appendix-B - TEMPORARY CONNECTION REQUEST FOR PROCESS


ITEMS.

TEMPORARY CONNECTION REQUEST . KIPIC KUWAIT INTEGRATED PETROLEUM INDUSTRIES


FOR PROCESS M.olllo.JI ~q.,..WI
COMPANY (KIPIC}

1 Exact Location:
D Refinery • LNG • Petrochemical
(Area/ Section/ Unit/ Train/ etc)
2 A. Description pf Work (From - To, Attach sketch if required) :
........................................................................................................................................................................................
....................................................................................................................... Using (Flexible Hose/ Metalic Piping)
B. Purpose of Installation: ..................................................................................................................................
If connection to drainage system: • Oily Water Sewer-DX • Process Sewer-DX • Chemical Sewer-DX
3 Details of Connection:
From (Service) ............. Max operating condition : Pressure in Psig .......... Temp in °F.........
To (Service) ........ .......... Max operating condition : Pressure in Psig .......... Temp in °F.........
4 A. Issued to (Department/ Division/ Contractor)
.....................................................................................................................................................................................
D Risk Assessment required (see attachment)
B. Authorization for initial execution: It is safe to proceed with the connection
Attach Risk Assessment report from Section Head Operations
From (Date) ....................... To (Date)
Issuer (Supervisor, Operations) : Signature ............. Name ............... . Emp No ......... . Date ............. .
Approver (Section Head/ ZSC. Operations): Signature ....... Name ....... Emp No ......... . Date ..............
Executor (Supervisor, Maintenance) : Signature ...... . Name ....... Emp No .......... Date ..............
C. Authorization for extension
Attach Risk Assessment report from Section Head Operations
From (Date) ....................... To (Date)
Issuer (Supervisor, Operations) : Signature .... ........ . Name ............... . Emp No .......... Date ............. .
Approver (Section Head/ ZSC. Operations) : Signature ....... Name ....... Emp No .......... Date ..............
5 Authorization for Closure
The temporary connection is no more required and can be removed.
Issuer (Supervisor, Operations) : Signature ............ . Name ................ Emp No .......... Date ..............
The temporary connection has been removed and conditions are restored to normal
Executor(Supervisor, Maintenance) : Signature ....... Name ....... Emp No .......... Date ..............
Issuer (Supervisor, Operations) : Signature ............. Name ................ Emp No ......... . Date ..............
Origi na l: Executor. First Copy: Issuer, Second Copy: Safety DIAL"_" IN CASE OF ANY EMERGENCY
a.1D l!w..l I <4JgJ4.11 wlcl.i..c.JJ Q,!.l.i~I ~ _µW I

KIPIC
a.l.ol1Lo.JI 0./,-lgJ,,l..!.JI
o...,µ.., 9---1-ll Jg;..1....J I ii..J.u...w~ ulSJ--W .s>-=>J
Kuwa it Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

17.0 GENERAL CONDITIONS AND GUIDELINES


• All temporary connections shall be provided only for a maximum of 30 calendar
days. Any extensions can be provided for a maximum of 15 Days, on a case to case
basis with Section Head approval after due risk assessment is carried out (Ifrequired).

• Temporary connections shall be provided only where operating pressure in not


more than 150 psig (10.54 Kg/ Cm2) and temperature not more than 375°F
(190.56° C)

• The authorization shall be displayed at worksite along with the attachments.


• Separate authorizations are required for different temporary connections.
• Only the authorized personnel can sign the authorization.
• White Color authorization is for utilities connections.
• Yellow Color authorization is for process connections.
• Issuer must ensure fill or tick the details from Section 1, 2 and 3.
• Executor must not start the connection before getting the authorization.
• Executor must ensure all protective measures before completion of job. A check list is
given below.
• Executor must provide adequate supervision and must be available during critical work.
• Both issuer and executer shall be present when the connection is lined up for the first
time.
• Issuer and Executor shall keep the copies in a file until removal ofthe temporary connection.
• Suspend all works in case of plant emergency or accident.
• Issuing division and Safety personnel have the right to stop the job any time on safety
reasons.
• Close the authorizations by completing the Section - 5 of original and Issuer copy.
• Closed authorizations shall be kept in a box file for 1 month after removal of
connection.
• Any exemptions shall be with prior approval ofKIPIC safety.
• The temporary connections shall be isolated / depressurized by Operations
before disconnection by maintenance.
cilDlil.c>J I &,+J g;l+J I wl<:w::ill &A!~I c.!>j-WJ I

KIPIC
fil.o 11i.o..J I li/,.J gj.l.µ I
ci..;..1.;~I JgJ--l.-µI o....u,._w,;µ, wlSJ-..W ..s~J
Kuwait Integrated Petroleum Industries Company
A Subsidiary of Kuwait Petroleum Corporation

18.0 CHECKLIST FOR MAINTENANCE PERSONNEL


• All required information provided by the issuer and authorization is complete.
• All required attachments (Risk assessment / Sketches) are available, (If any
• Is the correct pipe / hose selected for the service?
• Is the routing of pipe I hose safe?
• Is the pipe I hose adequately supported. (If any)
• In case of hose, is the test due date valid for a minimum of 1 month.
• In case of hose, is the safety device installed in coupling.
• Is positive isolation device provided to prevent doss contamination?
• Is the pipe I hose adequately protected at road crossings / vehicle movement areas.